Are benefits to be included in the claim for a grant?
You cannot include the following payments in a claim:
- Discretionary bonus or commission payments
- Tips
- Non-cash payments
- Non-monetary benefits including taxable benefits in kind
- Salary sacrifice benefits that reduce an employee’s pay (however HMRC has agreed that such arrangements can be stopped by agreement if due to COVID-19 and the contract is changed)
The updated guidance has confirmed that all of the grant claimed should be paid to the employee in the form of money and that none of the grant is to the used to pay for the provision of benefits or a salary sacrifice scheme.
Related FAQs
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:
- Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
- Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
- Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
- Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
- Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
- Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
- Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
- Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
- Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!
In general. there is often a stick or twist decision. If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful. Conversely, withholding payments from the contractor may make insolvency a self-fulfilling prophecy. The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.
The current guidance issued by Mr Justice Hayden confirms that remote hearings may be conducted using the following facilities and that this will be the default position until further direction:
- By way of an email exchange between the court and the parties;
- By way of telephone using conference calling facilities;
- By way of the court’s video-link system, if available;
- The use of the Skype for Business App installed on judicial laptops;
- Any other appropriate means of remote communication, for example BT MeetMe, Zoom or FaceTime.
It has also been proposed in the Corporate Insolvency and Governance Bill that public companies who were due to file their accounts in the period from 26 March 2020 to 30 September 2020 will have until the earlier of the 30 September 2020 and the date which is 12 months after the end of their relevant accounting period to do this.
This is separate from the pre-existing scheme, announced on 25 March 2020, whereby companies can apply to Companies House for a 3 month extension for filing their accounts.
Yes. The Government continues to support the construction industry and the Prime Minister’s recent statement supports the return to work of those who cannot work from home, if they can work safely. This has seen an immediate surge in industry workforce returning to work. Banks and storage and distribution businesses are permitted to operate as essential businesses.
Solicitors and estate agents may still not permit members of the public to enter their premises, but can operate remotely via website, phone, email and other methods, as normal. The Government’s latest guidance published on 13 May now advises that moving house need not be postponed, provided social distancing and safe ways of working can be adopted. Restrictions remain for those who are infected or who are self-isolating or vulnerable, and they should not move house or accept visitors.