Skip to content

Are benefits to be included in the claim for a grant?

You cannot include the following payments in a claim:

  • Discretionary bonus or commission payments
  • Tips
  • Non-cash payments
  • Non-monetary benefits including taxable benefits in kind
  • Salary sacrifice benefits that reduce an employee’s pay (however HMRC has agreed that such arrangements can be stopped by agreement if due to COVID-19 and the contract is changed)

The updated guidance has confirmed that all of the grant claimed should be paid to the employee in the form of money and that none of the grant is to the used to pay for the provision of benefits or a salary sacrifice scheme.

Related FAQs

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
Can I use my Business Interruption insurance to make a claim?

The FCA’s test case in the Supreme Court ruled overwhelmingly in favour of policyholders.  However, business interruption cover generally has the prerequisite of physical damage or loss to the property (or in some circumstances, the presence of a notifiable disease at the property or within a certain radius of it), to recover losses caused by the interruption to your business. The onus is on insurers to re-assess those claims which are impacted by the Supreme Court’s judgment and to make contact with the policyholders regarding next steps. If you have not already made a claim, in the first instance the terms of any policy should be checked carefully to see whether business interruption cover is provided.

Will councillors still be able to vote if they can’t meet in person?

Local government legislation formerly stipulated that councillors must be physically present to vote and this requirement has already led to the widespread cancellation of Council meetings.  There is a limit to what can be achieved under the chair’s emergency powers and delegation to officers.

The Government has now legislated to allow for remote voting until 7 May 2021. The secondary legislation required was issued in draft on 2 April and has been in force since Saturday 4 April.

The legislation allows for committee meetings to go ahead where members and any members of the public attending remotely can all times “hear (and where possible see) and be heard (and where possible be seen) by the other members in attendance”.

It remains to be seen how many local authorities take up the opportunity to hold a virtual committee meeting. Concern has been expressed that the demographic of local councillors may mean that members have difficulty with the technological mechanisms for holding such meetings. However, the message from the Secretary of State is clear that wherever possible, the planning system should keep moving in these current times.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

What is the penalty for failing to comply with the collective consultation obligations?

Failure to comply with the collective inform and consult obligations could impact on the fairness of any dismissals – see next question. In addition, a Tribunal can award a protective award of up to 90 days gross pay for each affected employee. The purpose is intended punish the employer for not complying with the obligations, not to compensate the employee for their individual financial loss.