Skip to content

Are benefits to be included in the claim for a grant?

You cannot include the following payments in a claim:

  • Discretionary bonus or commission payments
  • Tips
  • Non-cash payments
  • Non-monetary benefits including taxable benefits in kind
  • Salary sacrifice benefits that reduce an employee’s pay (however HMRC has agreed that such arrangements can be stopped by agreement if due to COVID-19 and the contract is changed)

The updated guidance has confirmed that all of the grant claimed should be paid to the employee in the form of money and that none of the grant is to the used to pay for the provision of benefits or a salary sacrifice scheme.

Related FAQs

The employee I need to consider suspending is a doctor – do I have to follow MHPS

Yes probably in our opinion, even if you are not considering taking any formal action against them. Ultimately if a doctor is suspended this could be considered as causing them reputational damage and it therefore is correct that they are afforded the protections (in particular in relation to keeping exclusion/suspension under review) of MHPS. Under Part V of MHPS there is provision for excluding practitioners if they are a danger to patients and they refuse to recognise it or if they refuse to co-operate. It doesn’t refer to a particular risk for the practitioner themselves, but it would appear logical that it would apply.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
What routes of challenge are available to an insurer's rejection of my business interruption claim?

Many policies will only provide business interruption cover if it arises from property damage. The FCA has acknowledged that insurers are entitled to reject claims in relation to such policies, notwithstanding the success of the FCA’s test case in the Supreme Court, and which was generally favourable to policyholders [Insert a link here to our update on the test case]. In other cases the policy wording will be less clear and businesses may legitimately feel that their insurer is wrongly withholding payment.

One route of challenge to an insurer’s decision is via one of the well-publicised class actions. Another route of challenge is by a complaint to the Financial Ombudsman Service (FOS). This service is open to consumers and small and medium-sized businesses, ‘micro-enterprises’, charities and trusts. The service will be an attractive option for many businesses, as it is free and relatively quick (although it remains to be seen how the service keeps up with an increase in demand as a result of the pandemic). You will need to have complained to your insurer before bringing a complaint with the FOS.

Further details can be found here.

What should an employer do when an employee has been told to self-isolate under the coronavirus Test and Trace scheme?
  • Do not require them to work
  • Continue to communicate with and support them
  • Allow them to work from home, is there alternative work for them to do if they can’t do their work from home
  • Offer SSP or allow them to take holiday if they want to.