Skip to content

Are permitted development rights now in existence for the creation of emergency medical facilities?

Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:

  • Preventing an emergency
  • Reducing, controlling or mitigating the effects of an emergency
  • Taking other action in connection with an emergency

It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.

The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.

Further detail of the permitted development right is available at the link below.

http://www.legislation.gov.uk/uksi/2020/412/made

Related FAQs

Capability issues

All organisations have underperformers. Capability is a potentially fair reason to dismiss and is separate to any redundancy procedures.

Generally, capability falls into either absences through illness or underperformance in the role. Those who are absent through sickness can be furloughed, but when furlough comes to an end they will need to go back onto sickness. If you are looking to tackle absence then you need to tackle long term and short term absence in a different way.

Long term absence: You need to establish whether the employee is able to return to work (with or without reasonable adjustments) in the medium term. This requires medical opinion and be careful of disability issues. Reasonable adjustments are likely to be important.

Short term absence: You will need to demonstrate that you have fair absence triggers in place and there is normally be a 3 stage procedure: warning and final warning followed by dismissal on notice. Each stage needs a fair procedure, with written information, a fair hearing and the opportunity to appeal. Be careful of disability issues.

As for underperformance: To tackle this, you will need to have clear SMART objectives in place and evidence of the employee failing to meet these. There would then normally be a 3 stage procedure: warning and final warning followed by dismissal on notice. Each stage needs a fair procedure, with written information, a fair hearing and the opportunity to appeal.

What actions and measures should be avoided?

The CMA is particularly concerned about certain activities, its guidance highlights:

  • Exchange of commercially sensitive information where this is not necessary in response to the crisis
  • Collaboration which unfairly excludes third parties
  • Abuse of a dominant position (including a dominant position held as a result of the crisis) – particularly to charge excessive prices
  • Seeking to maintain prices or prevent reductions in prices
  • Cooperation going beyond what is necessary to respond to the crisis in the interests of consumers
What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

Have you had any safeguarding issues in relation to staff they see and do you follow your normal safeguarding pathway?

Safeguarding issues are relatively uncommon, however, if they do occur, the normal safeguarding procedure of the organisation should be followed.

How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.