Are permitted development rights now in existence for the creation of emergency medical facilities?
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.
Related FAQs
No. Before continuing any negotiations, you need to strongly consider whether now is the best time to settle. There is a myriad of uncertainty due to the pandemic, with unemployment rates increasing, volatility in the stock markets and difficulties regarding placing valuations on assets. This could all lead to the financial settlement being unfair to you and cause you financial difficulties in the future.
Any financial settlements reached following marital separation should be embodied in to a Court Order, to prevent future claims from your ex-spouse. As a general principle, although maintenance orders are always variable, financial orders in respect of capital (e.g. house, cash, investments, pensions) are final and it is very difficult to set aside a Court Order. The question will be whether or not the pandemic is judged as a Barder event, which broadly means something viewed as unforeseen. It would be challenging for you to argue that the effects of COVID-19 are unforeseen given the widespread expectation of an economic crisis. The Court previously found against a husband who wanted to revisit an Order that he said was unaffordable following the 2008 financial crisis, with one Judge commenting that a 90% drop in the Husband’s share price was a “natural process of price fluctuation”.
Even if you informally agree a settlement with your ex-spouse, and you do not have this reflected in a Court Order, your ex-spouse may still rely on this agreement within future Court proceedings and argue that you should be held to it.
It is, therefore, very dangerous to be reaching any financial settlements at this time with your ex-spouse without careful consideration and legal advice. Further, even if an agreement is reached, market volatility can mean longer implementation times, especially when a settlement relies on the sale of property.
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
Mortuaries are a sui generis use, unless ancillary to some other use of land, a hospital for example.
Sui generis uses are not within any Use Class. Consequently planning permission is required for the:
- Change in the use to a sui generis use
- Subsequently for the change in the use to an alternative use, whether that be another sui generis use or a use within a Use Class
Acknowledging the above, if the scale of the use is above de minimis, planning permission is likely to be required to change the use of a warehouse or factory unit into a temporary mortuary.
Should planning control be breached, a local planning authority must decide whether to take enforcement action or not. That enforcement is discretionary was recently reiterated in a Ministerial Statement issued on 13 March 2020 a link to which is below.
Depending on the form of the enforcement action, there could be a right of appeal.
Failure to comply with the individual consultation obligations could render the dismissal unfair and expose you to a financial penalty of the lower of up to 1 years gross pay or the maximum statutory limit (currently £88,519).
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.