Are permitted development rights now in existence for the creation of emergency medical facilities?
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.
Related FAQs
If changed circumstances mean that a business wants to exit from a contractual arrangement, then before trying to terminate it, a careful review should be carried out to see whether a right to terminate actually exists. For example:
- Not every contract for the sale of goods contains the right for the buyer to terminate in circumstances where the supplier hasn’t done anything wrong. If a business has entered into a contract on the supplier’s standard terms, it is unlikely to contain any such provision
- A contract for the provision of services is unlikely, if drafted by the customer, to contain a provision that allows the supplier to walk away from the arrangement at short notice, or perhaps at all
If a party tries to terminate a contract when it doesn’t have the right to do so, the other party will likely claim breach of contract and could sue for damages. In the case of a long term or high-value contract, this could amount to a very significant liability.
Even if the right to terminate the contract does exist, there might be particular rules about the following:
- How much notice has to be given
- How such notice has to be served (for example, it might have to be in writing to a particular address)
- When the notice can be served (perhaps on an anniversary of the start of the contract)
- How much a party has to pay if it cancels (for example, for raw materials, for work done to date, or even the whole contract price)
All of these factors must be taken into account, and any contractual processes for termination are followed.
Some employers falling into the third group of organisations described above could understandably feel aggrieved that on the first reading of the guidance they are not able to furlough employees and rely on the Government scheme. Many publicly funded organisations that are not public sector employers, receive a package of public funding with little expectation on how that funding is used or applied, other than broadly for it to be used in providing the services it is contracted to deliver. Also, several publicly funded organisations have many different income streams and the element of funding that is received from the public purse can be only an element of their operating costs.
Unfortunately there is still no clear guidance on when employers falling into the third category identified above can use the scheme. The only reference in the guidance on this states that where organisations are not “primarily funded” from the public purse and whose staff cannot be redeployed to assist with the coronavirus response, the scheme might be appropriate to be used for some staff. This seems to suggest that where an employing organisation is not wholly or mainly funded by public funding and staff cannot be redeployed to work in areas in the effort to combat coronavirus, then it would be appropriate for the employer to access the scheme.
If considering applying for grants under the scheme a sensible approach would be to look at the combined total of your public funding and payments under the scheme and make sure it will not represent more than 100% of the level of total income you would have expected to receive during this period in a non-Covid scenario.
Local Authorities are expected to maintain support to suppliers and this should be considered:
The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.
With time and resource precious commodities, focus should be given to documenting:
- The key changes to your PFI requirements
- The temporary nature of the measures
- The requirement for best efforts on behalf of the PFI Contractor
- The importance of continued health and safety measures at all times
On 7 May the Government published guidance on how contracting parties can act responsibly in order to assist the effort to deal with Covid-19. The guidance seeks to persuade contracting parties to act reasonably and recognise the impact of Covid-19 on contractual counterparties. This will continue to be relevant as business begins to emerge from lockdown.
The definition of a relevant establishment is a question of fact for an Employment Tribunal. Guidance from case law says that ‘establishment’ should be interpreted very broadly (so as to avoid employers escaping the need to collectively consult), and may consist of:
- A distinct entity
- With a certain degree of permanence and stability
- Which is assigned to perform one or more tasks
- Which has a workforce, technical means and a certain organisational structure to allow it to do so
However, there is no need for it to have the following:
- Legal, economic, financial, administrative or technological autonomy
- A management which can independently effect collective redundancies
- Geographical separation from the other units and facilities of the undertaking