Are permitted development rights now in existence for the creation of emergency medical facilities?
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.
Related FAQs
If your visa has expired or will do before you are able to safely leave the UK, you can apply for “Exceptional Indemnity” by contacting the Coronavirus Immigration Team. You will need to provide evidence as to why you cannot leave, which could include a positive Covid-19 test or evidence of being unable to make travel arrangements to leave the UK in time.
You should note that “Exceptional Indemnity” does not extend your leave, but temporarily protects you from adverse action being made against you as result of overstaying your visa.
The current guidance issued by Mr Justice Hayden confirms that remote hearings may be conducted using the following facilities and that this will be the default position until further direction:
- By way of an email exchange between the court and the parties;
- By way of telephone using conference calling facilities;
- By way of the court’s video-link system, if available;
- The use of the Skype for Business App installed on judicial laptops;
- Any other appropriate means of remote communication, for example BT MeetMe, Zoom or FaceTime.
If suppliers still wish to terminate the contract, they must contact the directors or the officeholder dealing with the insolvency process and obtain their approval to terminate the contract – which, of course, might not be given.
If the continued obligation under the contract to supply goods/services to the customer would place the supplier in financial hardship the supplier can apply to court for permission to terminate the contract. This will involve time and legal expense.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
The golden thread requirements will be retrospective, so will apply to existing buildings as well as new build. This is part of the reason for the Building Safety Regulator’s ‘get to know your building’ guidance referred to in the talk, with the link in the Powerpoint presentation. While the details of the golden thread requirement are still to be confirmed, now is a good time to start to gather as much information as can be obtained about existing buildings as possible in preparation. The Government guidance anticipates that the Principal Accountable Person will be responsible for developing and coordinating the golden thread for existing buildings.