Are Public Bodies able to continue to pay contractors (and their supply chains) at risk as a result of Covid-19?
Yes: The Cabinet Office has published a number of Procurement Policy Notes to provide instructions to Public Bodies to enable payments to continue to be made to at risk suppliers (and their supply chains) who have been affected by Covid-19. Copies of this guidance can be obtained from the Government website at: https://www.gov.uk/government/publications/procurement-policy-note-0220-supplier-relief-due-to-covid-19
Related FAQs
You must exercise reasonable care in assessing status and making a status determination, considering what the position would be if the contractor was engaged directly by the end user client instead of via a PSC.
Status is usually determined by looking a number of factors and how they apply to the contractor’s working arrangements. This is a difficult exercise that is usually carried out by employment and tax lawyers and it is full of grey areas. We have a toolkit that can help you navigate this process which Paul will tell you more about at the end of the session.
The key factors used to determine status are:
- Control:
- How much control does the end user client have over the contractor in terms of working arrangements (hours, place of work) and how the work is carried out? Or is the individual contractor able to determine how and when they work and without direct supervision of the end user client?
- Personal service:
- Is the contractor required to perform the services personally without the right to send a substitute? If there is a right to appoint a substitute is this subject to end user client approval?
- Mutuality of obligation:
- Is the end user client obliged to provide the contractor work with a mutual obligation on the contractor to accept that work?
Although an employer is obliged to conduct consultation “with a view to reaching an agreement”, it is not required to actually agree to any counter proposals made by the employee representatives. Merely to consider them in good faith.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs