Are there any exceptions to the obligation to return deposits?
The CMA sees only limited circumstances in which a full refund would not be given. The CMA accepts that where public health measures prevent a business from providing a service or the consumer from receiving it, the business may be able to deduct a contribution to the costs it has already incurred in relation to the specific contract in question.
This view reflects a relatively complex area of law under which parties are released from obligations under a contract if performance of that contract becomes impossible or illegal. This is called “frustration” of the contract. Under a law passed during World War II, a party to a contract that is frustrated who has incurred expenses is permitted, if the court thinks fit, to retain an amount up to the value of those expenses out of any money they have been paid by the other party.
The CMA’s view, however, is that this will not happen often, and that deductions from deposits will be limited.
Related FAQs
The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.
For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf
It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.
If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.
It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.
Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.
Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Employers had until 31 July 2020 to make any claims for claim periods up to 30 June 2020. That was the end of the old scheme.
From 1 July 2020, claim periods must start and end within the same calendar month and must be for at least 7 days unless you are claiming for the first few days or the last few days in a month.
You can only claim for a period of fewer than 7 days if the period you are claiming for includes either the first or last day of the calendar month, and you have already claimed for the period ending immediately before it.
For example, if an employee is furloughed for 7 days spanning a month. You can claim the last 3 in one month, and 4 from the next.
The crucial point is that you cannot make claims that cross calendar months.
The first time that you could make a claim for days in July 2020 was 1 July 2020. You could not claim for periods in July 2020 before this point.
On 2 April 2020, the Government issued guidance relating to Private Finance Initiatives and PF2 Projects. The guidance, which is to be enforced with immediate effect (currently due to stay in place until 30 June 2020), is one of several guidance notes issued to date.
A link to the guidance is set out below:
Key messages to contracting authorities
- PFI contractors should very much consider themselves as being part of the public sector response to the current pandemic
- Covid-19 is not regarded as, and is not to be classified as a force majeure event
- PFI contractors must ensure that contingency plans are up to date and have been reviewed and discussed with contracting authorities to enable the continuity of full services to respond to the pandemic and maintain vital public services
- Contracting authorities should work closely with PFI contractors to use all available options to maintain public services during the emergency period
- Local arrangements should be made where PFI contractors can’t deliver the agreed requirements and performance standards
- “Best efforts” should be made by all parties for the continuation of service provision