Skip to content

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

Does a sponsor need to report a change in workplace if a Tier 2 visa holder is working from home as a result of Covid-19?

No. The Home Office has confirmed that sponsors do not need to report sponsored workers as working from home, where this is directly related to the coronavirus outbreak.

However any UK employers who sponsor overseas workers, should also ensure that they remain compliant with their other sponsor licence duties, which includes reporting any change to an employee’s salary and duties.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Business support organisations

The Confederation of British Industry

“What you need to know about coronavirus and how it will impact your business”. This includes the very influential and highly regarded daily webinars hosted by Director General Dame Carolyn Fairburn.
https://www.cbi.org.uk/coronavirus-hub/

The Entrepreneurs’ Forum

Links to valuable resources collected by the Entrepreneurs’ Forum team as requested by its members and partner network, including on People, Finances, Physical and Mental Wellbeing, Technology and Leadership.
https://entrepreneursforum.net/support-hub

RTC North

Billed as containing “all the UK government information in one place”, this resource includes information on access to finance, employees, planning and leadership, Growth hub toolkits, and working from home.
https://www.rtcnorth.co.uk/covid-19/

Newcastle Gateshead Initiative (NGI)

Businesses across the UK and around the world are sharing their expertise in everything from remote working to business planning. The team at NGI have collated some of the most useful resources, alongside its own content which is designed to help partner organisations and other businesses across North East England.
https://www.ngi.org.uk/covid-19-business-resources/

North East of England Chamber of Commerce

The NEECC brings together its latest advice and guidance for businesses, as well as some of its own FAQs.
https://www.neechamber.co.uk/covid-19

Greater Manchester Chamber of Commerce

The Chamber has pulled together information about how it and others in the area are supporting all businesses during the Covid-19 outbreak.
https://www.gmchamber.co.uk/covid-19-coronavirus/

North East Growth Hub

The North East Growth Hub toolkit is intended to provide businesses with the latest advice, guidance and support available from government in response to the COVID-19 pandemic. Topics covered include:

  • Financial support available for businesses
  • Official guidance for employees, employers and businesses
  • Advice on effective home working
  • How to care for staff/suppliers/customers and prevent the spread of COVID-19

https://www.northeastgrowthhub.co.uk/toolkits/covid-19-coronavirus-toolkit

Pro-Manchester

Links to valuable resources collected by the Pro-Manchester team, including national Government support and advice, regional support and cyber security advice.

https://www.pro-manchester.co.uk/home/covid-19-support/

Innovation SuperNetwork

The Innovation SuperNetwork, a “network of networks”, detail on their website what their team of Innovation Managers are offering during these difficult times, as well as details of funding available, and what is being offered by their numerous partners.

https://supernetwork.org.uk/

What measures are being implemented to protect residential property tenants?

On 18 March 2020, the Government announced that it would pass emergency legislation which would prevent landlords, both social and private, from bringing possession proceedings against tenants who are unable to pay their rent. The Housing Secretary, Robert Jenrick, stated that “no renter who has lost income due to coronavirus will be forced out of their home, nor will any landlord face unmanageable debts.”

The announcement came after several organisations, including housing charity Shelter, expressed concerns that more than 50,000 households could face possession proceedings due to the economic uncertainty following the Covid-19 outbreak.