Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
There is less guidance in respect of whether an employee can refuse to go into the workplace as a result of health and safety concerns about their commute. An employer’s duties to ensure the health, safety and welfare of its employees only extend to the workplace or where an employee is acting in the course of their employment. This does not include the risks of travelling to and from work by public transport.
As there are various ways in which an employee can travel to work, it will be difficult for them to legitimately refuse to come to work due to their commute. Employers should discuss any concerns with the employee and seek to find an appropriate resolution. The government has published guidance on safer travel for passengers during the Covid-19 pandemic and employers should encourage flexibility as far as possible, such as allowing employees to travel at off-peak times and staggering workers’ hours.
Undeniably and understandably BAME staff, as well as those staff who are identified as being at a higher risk, are going to have high levels of stress and anxiety. For some, this may become of such severity that those staff should be considered to be disabled under the Equality Act 2010. The question as to whether someone is disabled is one that should be answered in conjunction with appropriate medical advice. But the question about how to support any staff suffering with stress and anxiety should not be left until that stage. Proactive steps need to be taken and expert advice obtained on what support measures should be put in place. We know that many NHS organisations are already giving the mental wellbeing of their staff the highest priority.
From our perspective, we would ask managers to be mindful that stress and anxiety is likely to feature in how an individual reacts to questions about the level of risk to their health and the impact on their duties. The conversations with some staff may not be easy to have and may be met with challenge.
For those staff who’s stress and anxiety is such that it would qualify as a disability, reasonable adjustments will need to be considered to the processes that you are applying.
An additional point to consider – it might be worth writing to all staff, asking them to come forward if they have any health conditions that they think you ought to be aware of, assuring them that such information is being given in the strictest confidence. You want to make sure that you are taking the appropriate measures to ensure their health and safety.
Companies House guidance on the impact of coronavirus on their services can be found at: https://www.gov.uk/guidance/coronavirus-guidance-for-companies-house-customers-employees-and-suppliers
This flexibility offered by Companies House could be a useful short-term help to businesses that are struggling to deal with the impact of the Covid-19 outbreak, but be sure to take action in advance of your filing deadline.
At the discretion of the lender, the Scheme may be used for unsecured lending for facilities of £250,000 and under.
Lenders were required to demonstrate lending additionality (i.e. lending that without the Scheme, wouldn’t have otherwise taken place). The Scheme has been extended to those businesses who would have previously met requirements for a commercial facility and would not have been eligible for CBILS. As a result it is suggested that all viable small businesses affected by Covid-19, and not just those unable to secure regular commercial financing, will now be eligible should they need finance to keep operating.
Primary Residential Property cannot be taken as Security under the Scheme. If the lender can offer finance on normal commercial terms without the need to make use of the Scheme, they will do so.
There are several options that can be used at this time to try and settle disputes. If it is not possible to settle a dispute via direct discussions between the parties then some form of Alternative Dispute Resolution (“ADR”) might be appropriate. Mediation is the most popular form of ADR. Most people’s perception of mediation is that it needs to be in person but that does not have to be the case.
Mediation can take place online or on the telephone. Most, if not all, ADR providers remain open for business and are quickly changing their business model to ensure that mediations can still take place. Mediation can be arranged at reasonably short notice and certainly so far as the online model is concerned, it mirrors the process that is adopted when parties appear in person. Online mediation allows for joint sessions with the mediator to take place and also for the parties to break out into their respective rooms for private discussions. If a dispute settles at mediation – and the vast majority do – then the agreement reached between the parties is binding and can be enforced.
A group of senior former judges and legal academics have now called for an acceleration in the use of ADR in light of the current circumstances. They have stated that courts should promote “and where appropriate require” the use of ADR. Mediation has particularly seen an increase in growth at this time.
ADR normally results in a quicker outcome than if the matter proceeds in the courts. Due to its conciliatory nature it is a very useful process where parties continue to be in a trading relationship. Contracting parties should also consider building ADR into dispute resolution clauses in their contracts so that in the event there is a dispute the focus is on resolving the dispute as soon as possible before it escalates into litigation.”