Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

Capability issues

All organisations have underperformers. Capability is a potentially fair reason to dismiss and is separate to any redundancy procedures.

Generally, capability falls into either absences through illness or underperformance in the role. Those who are absent through sickness can be furloughed, but when furlough comes to an end they will need to go back onto sickness. If you are looking to tackle absence then you need to tackle long term and short term absence in a different way.

Long term absence: You need to establish whether the employee is able to return to work (with or without reasonable adjustments) in the medium term. This requires medical opinion and be careful of disability issues. Reasonable adjustments are likely to be important.

Short term absence: You will need to demonstrate that you have fair absence triggers in place and there is normally be a 3 stage procedure: warning and final warning followed by dismissal on notice. Each stage needs a fair procedure, with written information, a fair hearing and the opportunity to appeal. Be careful of disability issues.

As for underperformance: To tackle this, you will need to have clear SMART objectives in place and evidence of the employee failing to meet these. There would then normally be a 3 stage procedure: warning and final warning followed by dismissal on notice. Each stage needs a fair procedure, with written information, a fair hearing and the opportunity to appeal.

Reductions in working hours

Another obvious cost cutting measure is to reduce working hours, either temporarily or permanently. Again, it should be done fairly, either across the board or by selecting teams/individuals based on objective business reasons. Imposing without agreement would create significant risk, therefore would require fair selection and consultation.

VIDEO: An update from cashflow.co.uk expert Chris Silverwood about access to finance

Partner at Ward Hadaway Adrian Ballam catches up with corporate finance expert and CBILS specialist Chris Silverwood (CorpFin and cashflow.co.uk) a month after their initial conversation to talk about what the last couple of months have taught us about access to finance.

Sections of the video and their timings are as follows:

(01.06) – example of continuing appetite for certain businesses (e.g. tech sector)

(02.06) – conflict between incumbent bank and different CBILS lenders, plus brief discussion of CBILS II

(05.36) – bounce back loans have been a distraction

(06.27) – muted impact of fintech CBILS lenders

(07.52) – discussion about invoice discounting

(11.59) – looming insolvency environment

(12:52) – emerging themes

 

What is the new Permitted Development Right for restaurants, cafes and drinking establishments?

A new Permitted Development Right has been introduced providing restaurants and cafes, drinking establishments with expanded food provision to temporarily provide takeaway food. The new right came into force on 24 March 2020 and expires on 23 March 2021. The right is subject to three conditions:

  • The developer must notify the local planning authority if the building and any land within its curtilage is being used, or will be used, for the provision of takeaway food at any time during the relevant period
  • Change of use to the provision of takeaway food under the Right, does not affect the use class which the building and any land within its curtilage had before the change of use
  • If the developer changes use to the provision of takeaway food under the Right, the use of the building and any land within its curtilage reverts to its previous lawful use when the Right expires or, if earlier, when the developer ceases to provide takeaway food.

Alcohol will still be subject to the same licensing requirements. At this stage, it is not clear how the Right will interact with any current planning conditions placed on an establishment.  Enforcement however remains discretionary. A link to Statutory Instrument 2020 No.330 is below.

http://www.legislation.gov.uk/uksi/2020/330/made

Is my business covered by insurance for notifiable diseases?

Unfortunately, losses caused by pandemics are not often covered expressly under standard policies, as the risk has been difficult for insurers to price and understand.

Even where additional cover in respect of notifiable diseases has been purchased, it typically will not include Covid-19 within the range of diseases covered by the policy. If the policy includes a list of notifiable diseases, and which does not include Covid-19, it is very unlikely that cover will be available for pandemic-relates losses.

The most common types of covers that could be afforded by insurance policies for coronavirus-related losses and liabilities are traditional business interruption insurance, contingent business interruption insurance, liability insurance, as well as cancellation and abandonment insurance.