Skip to content

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

Do leaseholders who have more than three properties in the UK have to pay the full contribution for building safety works and is there a way of finding out how many properties out leaseholders have in the UK?

The first point to note is that it is the position as at 14 February 2022 which is relevant, as whether or not a lease is a ‘qualifying lease’ for the purposes of recovering costs under the Building Safety Act was effectively frozen at that time.

If a leaseholder owned more than three properties in the UK (and the property in question was not their principal home) at that time, then the lease will not be a qualifying lease. The protections under the Act which prevent or restrict the landlord’s ability to recover the cost of remedial works through the service charge will not therefore apply to that lease (save potentially for the provision that costs cannot be recovered where the landlord is responsible for the defects, which does not expressly refer to qualifying leases).

The lack of a searchable database to assess how many properties a leaseholder has in the UK is however one of the difficulties to be resolved in this regard, as there is currently no way of searching the Land Registry to obtain a list of properties owned by one individual. The guidance appears to rely on the leaseholder completing the leaseholder deed of certificate being open and honest in this regard, and that deed of certificate being passed onto subsequent owners. Making false representations or failing to disclose required information in the deed of certificate may be a criminal offence, although reliance on this to discourage mis-reporting is clearly less satisfactory than having a searchable register.

What is the current guidance relating to Private Finance Initiatives and PF2 Projects in light of coronavirus?

On 2 April 2020, the Government issued guidance relating to Private Finance Initiatives and PF2 Projects. The guidance, which is to be enforced with immediate effect (currently due to stay in place until 30 June 2020), is one of several guidance notes issued to date.

A link to the guidance is set out below:

https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/877804/2020_04_01_PFI_and_COVID19_final.docx.pdf

Key messages to contracting authorities

  • PFI contractors should very much consider themselves as being part of the public sector response to the current pandemic
  • Covid-19 is not regarded as, and is not to be classified as a force majeure event
  • PFI contractors must ensure that contingency plans are up to date and have been reviewed and discussed with contracting authorities to enable the continuity of full services to respond to the pandemic and maintain vital public services
  • Contracting authorities should work closely with PFI contractors to use all available options to maintain public services during the emergency period
  • Local arrangements should be made where PFI contractors can’t deliver the agreed requirements and performance standards
  • “Best efforts” should be made by all parties for the continuation of service provision
Can I have legal documents signed and witnessed?

Solicitors can be authorised to sign contracts for their clients – a signed letter of authority should be scanned and sent to avoid posting potentially contaminated documents.

Solicitors should exchange supplemental agreements on behalf of their clients to agree to postpone exchange and completion dates if it has been agreed to push these back.

The Law Society advises that electronic signatures be used as much as possible for contracts, to avoid possible contamination. However, the Land Registry confirms that the legal transfer document cannot be validly executed with an electronic signature. Solicitors should agree a completion undertaking that the original transfer document will be sent when received and after the restrictions have been lifted.

The Land Registry’s latest guidance https://www.gov.uk/guidance/coronavirus-covid-19-impact-on-hm-land-registrys-services published on 14 May states:

We accept deeds that have been signed using the ‘Mercury signing approach’.

For land registration purposes, a signature page will need to be signed in pen and witnessed in person (not by a video call). The signature will then need to be captured, with a scanner or a camera, to produce a PDF, JPEG or other suitable copy of the signed signature page. Each party sends a single email to their conveyancer to which is attached the final agreed copy of the document and the copy of the signed signature page.

Solicitors should be willing to adopt this procedure for completing transactions to enable them to be registered by the Land Registry.

The execution of a transfer is a deed and must be witnessed. Members of the family can witness signatures so long as they are not also a party to the document. A witness will be more credible if they are 18 or over, but this is not a legal requirement. The legal requirement is for the witness “to be present” when the document is signed. It would be possible for a witness to be on the other side of the room or the other side of a window, and validly witness the execution of a deed. The witness does need to take precautions to avoid possible contamination from the document.

A statutory declaration does not need to be witnessed but must be administered by a solicitor or commissioner for oaths. There is no legally prescribed process for this, and there is nothing to suggest that this could not be validly done via a video telephone call if the signature on the declaration can clearly be seen by the person commissioning the oath when the oath is made.

Can colleagues meet outside of work during the national lockdown?

Yes, but only for work purposes and where it is unreasonable to do so from home. Work colleagues cannot meet to socialise.

Is there anything else I should consider from a health and safety perspective?

Increased hygiene measures should be introduced to limit the spread of infection. Increase the frequency of cleaning, particularly higher risk contact points such as door handles. Avoid the use and sharing of hardcopy in favour of electronic documents; avoid sharing of tools and work equipment; increase the availability of handwashing facilities and hand sanitisers; issue anti-bacterial wipes and tissues to staff, and remind everyone to maintain good personal hygiene practices, including regular hand washing. Prominent and repeat signage will be vital in reminding workers of these steps they can take to protect themselves.

PPE – e.g. disposable gloves and face masks – are not currently legally required in the UK, but especially where social distancing might not be possible, it may be necessary to make appropriate PPE available to staff. If so, you will need to make sure there is enough available train everyone so it used properly and provide for safe disposal of used items.

MOST IMPORTANTLY – communicate with your people; invite their input and suggestions and act on them. Communication and participation in the process of a safe return to work are going to be crucial to its’ success.
Monitor for illness: train managers how to spot the symptoms of COVID-19 and have a clear process if someone is potentially infected. Continue to remind staff to only come into work if they are well and not experiencing any symptoms. A number of businesses are planning on using testing and screening methods, such as temperature checks. Remember, these steps create data privacy considerations which you will need to consider.

Do not forget existing health and safety obligations, such as maintaining sufficient numbers of fire marshals and first aiders on-site. Employers should also be aware that the Health and Safety Executive must be notified under RIDDOR of any workplace incidents that lead to exposure to COVID-19 and any cases where there is “reasonable evidence” that it was caused by exposure in the workplace. Be aware that workers are being encouraged to report to HSE failures of their employers to keep them safe from the threat of the virus.