Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

What support did the Chancellor announce for employers to be attracted to take on apprentices?

The Chancellor announced that employers will be given £2,000 to employ apprentices and £1,500 for apprentices over the age of 25 for each apprentice they hire from 1 August 2020 to 31 January 2021. These payments will be in addition to the existing £1,000 payment the Government already provide for new 16-18 year old apprentices.

He also announced that employers would be given £1,000 for taking on trainees in response to the traineeship scheme being extended.

Who is exempt from wearing a face mask at work?

Those individuals who are already exempt from the existing face covering obligations, will continue to be exempt from the new rules. These include:

  • Those unable to put on or wear a face covering because of a physical or mental illness or disability
  • People for whom wearing or removing a face covering will cause severe distress
  • Anyone assisting someone who relies on lip reading to communicate
VIDEO: Can trade credit insurance help to keep the supply chain moving?

On Tuesday 23rd June, partner Emma Digby was in conversation with Steve Hamstead and Mark Smith from AON along with Ward Hadaway commercial lawyer Nathan Bilton in a webinar titled Can trade credit insurance help to keep the supply chain moving?

The insurance market is under untold pressure as a result of the pandemic, and in such times there is a risk that insurers will cancel or reduce credit lines, particularly in certain high risk sectors such as retail. However the Government has stepped in to effectively underwrite the existing trade credit insurance agreements, and to keep trade supplies moving. Will this be enough?

In this webinar, we discussed:

  • the Government backed scheme and how it will operate
  • the prospects of obtaining insurance going forward, and whether it will become too cost prohibitive
  • could the new legislation put your business at risk and jeopardise your insurance cover if you cannot cancel a contract when you are not getting paid for your goods or services
  • the Brexit effect, and how this will affect the insurance market
  • protecting your business with proper risk assessment processes and paperwork
We are conscious that asking a particular group of people, who have a protected characteristic under the Equality Act 2010, to restrict their duties, could expose the Trust to allegations of discrimination. What steps can we take to avoid someone/a group of people feel that they have been treated differently because of their protected characteristic?

A claim for indirect discrimination is the most likely risk here. The first point to make is that the decision to review duties is being made based on the growing amount of medical evidence that the BAME community is being disproportionately adversely affected by the COVID 19 pandemic compared to other ethnic groups. The key is to ensure that blanket policy decisions are not taken, nor should assumptions be made about the risk to each individual concerned. Decisions should only be made on an individual basis with an open dialogue with the individual concerned. You as their employer, need to ensure that the individual feels listened to and heard; that this is not just a tick box exercise.

Consider having a working group which has an overview of the policy decisions being made. That working group should contain representatives from across the staff groups including staff side, but importantly, representatives from different ethnic backgrounds to ensure the important voices are heard. Accountability should be built into that group. This group should also be a safe environment for staff to raise concerns about their health and safety and safe systems at work.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements