Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

What are my potential liabilities if a customer, supplier or other visitor contracts Covid-19 on my premises?

As an occupier of premises, you owe a duty of care to your visitors to take reasonable care to see that the visitor will be reasonably safe in using your premises.

It is therefore essential that you are taking reasonable steps and strictly adhering to up-to-date Government advice in all aspects of your business to avoid any potential liability.

Failure to follow Government advice could leave you vulnerable to claims for compensation for pain and suffering should a visitor on your premises contract Covid-19.

However, each case will be fact-specific and it would be very difficult for a visitor to establish that they contracted Covid-19 specifically from those premises (as opposed to being exposed to the virus anywhere else).

If someone suggests that they are going to make a claim make sure that you report matters to your insurer or insurance broker immediately.

Who is responsible for arranging the remote hearing in COP matters?

Where one or more of the parties is represented, responsibility for making the arrangements for the remote hearing will fall on either the applicant or the first represented party. If no party is legally represented, the court office will contact the parties to explain that the hearing will be held by telephone conference and will send them instructions on how this is to be achieved.

All remote hearings must be recorded. The responsibility for arranging the recording will be addressed on a case by case basis.

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

I have essential workers who do home visits. How do I assess the risks?

The fundamentals of risk assessment remain the same as for any other foreseeable risk.

Focus on risk controls which reflect Government guidance; social distancing (2 metres) and avoiding contact with occupiers if possible, high-quality PPE – disposable overalls, gloves and fluid repellent surgical face masks, ready access to antibacterial wipes for surfaces, tools and equipment and plentiful hand sanitizer.

How should contracting authorities work with PFI providers?
  • Working with PFI providers to get contingency plans up to date
  • If a PFI provider is struggling to achieve service delivery requirements due to Covid-19, then local arrangements should be put in place to:
    • maintain unitary charge payments
    • revise contract requirements/standards

moderating payment and performance regimes where appropriate.

  • In any event, you may wish to review and adjust your requirements to reflect the current situation. It is possible that some requirements can be relaxed, whereas others need to be tightened. For example, there may be an increased need for cleaning and maintenance in certain areas of your PFI premises or the layout of the premises and/or room uses may have temporarily changed. With staff illness and shortage likely to be an issue, you may also wish to consider if the resource can be moved from one area to another to help maintain essential services.
  • When putting local bespoke arrangements into place it is vital that:
    •  Contract requirements or performance standards are not relaxed to the point where health and safety are put at risk.
    • It is made clear that the arrangements are temporary and that matters will return to normal as soon as the Covid-19 emergency is over. Indeed the guidance note makes clear that if assets temporarily close they should be kept in such condition that they can be immediately up and running when this emergency is over. In such instances, likely a basic level of maintenance and security will therefore be required as a minimum.