Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
As a result of the CJRS being extended, the Job Retention Bonus will no longer be paid in February 2021.
In practice this means that any risk assessment will need to be reviewed constantly and adjusted as our understanding of the nature and level of the risk grows.
Some service-providers are instigating special Oversight Groups to keep this issue under review but engagement and consultation with those affected is critical and making sure they feel confident to raise concerns and refuse to work if they believe they are not safe.
If you don’t want to make redundancies, or if you can’t reduce employee resource, either in a particular department or across the workforce as a whole, then you need to think about alternatives to redundancy.
Equally, you may want to flex the resource you have available to you – without making drastic changes. For example you may want to consider:
- unpaid leave and sabbaticals
- retraining and redeploying
- forcing annual leave
- flexible working
- capability issues
- lay off
- short time working
- reductions in salary
- reductions in working hours
- changing to shift working
You will claim a pro rata’d amount of 80% of salary, based on the proportion of hours not worked out of the employee’s normal working hours (their “usual” hours).
There are 2 ways to calculate an employee’s usual hours, depending on whether they have fixed or variable hours/pay:
- For those with fixed hours/pay, you take the number of hours worked in the pay period before 19 March 2020.
- For those with variable hours/pay, you take the higher of:
- the average number of hours worked in the tax year 2019 to 2020 or
- the corresponding calendar period in the tax year 2019 to 2020.
If employees are paid per task or piece of work done, you should work out the usual hours for these employees in the same way as for other employees who work variable hours, if possible.
When you calculate the usual hours, you should include any hours of leave for which they were paid their full contracted rate (such as annual leave) and any hours worked as overtime (but only if the pay for those hours was not discretionary).
The workplace will not revert to its pre-Covid-19 state overnight, with social distancing in the work place likely to remain in place for quite some time to come.
This could mean that businesses will need to think carefully about how their capacity will be impacted, and how this will affect their ability to perform contractual obligations.
For example, if a business has an outsourcing contract under which it has to perform a business process, or produce a particular output, will it be able to comply with contractual performance standards whilst social distancing is still in place? In the context of a manufacturing business, what will be the impact on production schedules and delivery dates? There might also be an impact on operating costs, for example if processes are changed and additional shifts are introduced – can these additional costs be sustained?
Businesses need to plan a safe system of work for their employees to ensure they comply with Health and Safety legislation, but they also need to consider how this will impact on their ability to perform pre-existing contractual obligations. Ultimately, contractual arrangements with customers might need to remain on a revised footing for a number of months.
Getting to a point where agreement is reached on allocation of additional costs and/or changes to key elements of a contract such as scope of work, performance standards and delivery date will require co-operation between contracting parties. Again, it is important that any variations that are agreed are recorded properly and follow the required contractual procedures.