Skip to content

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

What actions and measures should be avoided?

The CMA is particularly concerned about certain activities, its guidance highlights:

  • Exchange of commercially sensitive information where this is not necessary in response to the crisis
  • Collaboration which unfairly excludes third parties
  • Abuse of a dominant position (including a dominant position held as a result of the crisis) – particularly to charge excessive prices
  • Seeking to maintain prices or prevent reductions in prices
  • Cooperation going beyond what is necessary to respond to the crisis in the interests of consumers
Do you have to collectively consult for the minimum period of time before you can issue notice?

These periods are often mistakenly referred to as minimum lengths of consultation (especially by Trade Unions). That is not correct. Consultation can commence, conclude and notices of dismissal be issued within the 30 and 45 day periods. The expiry of the notice would just have to be outside of those restricted periods.

What is the guidance for doctors working during the pandemic?

The General Medical Council (GMC) have published guidance online for doctors during this time of uncertainty.

 

Alongside this, their website displays guidance for temporary registration to approximately 15,000 doctors, who left the register or gave up their licence to practise in the last three years.

 

These clinicians have been contacted to assist with the growing pandemic, outlining the process they would follow and informing them of their right to opt-out. The Secretary of State for Health can ask the GMC to grant such registration under Section 18a of the Medical Act 1983, in an emergency.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
There is a court order in place in relation to access to my child. What should I do?

If there is a court order then this should be complied with, unless you are unable to do so because the parent with whom the child lives is self-isolating, the other parent is self-isolating or the children are showing symptoms of the virus. If you are unable to comply with the court order, the other parent should be notified immediately in writing and proposals put forward for how they can see and speak to their children by telephone, FaceTime, Zoom or some other method.

If any necessary variations to the arrangements cannot be agreed then you should contact us for legal advice.