Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
Put simply, if it is a requirement of a particular role that PPE is worn, then this should be provided to the employee. If an employer dismissed an employee for refusal to carry out their role due to lack of PPE then this is likely to be an automatically unfair health and safety dismissal.
Furthermore, anyone who is subject to a detriment as a result of raising a health and safety concern, e.g. someone in this situation who refuses to work due to lack of PPE and is sent home without pay, will also have a potentially valid claim in the Employment Tribunal for that detriment, even if they are not dismissed.
Read more about thisThe Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
The formal Government position relating to construction sites is that construction work should continue on site if it can be conducted safely, and the Business Secretary, Alok Sharma, has written an open letter to the UK Construction Industry thanking it for all its help in the current crisis. The letter also confirms the Government’s current official policy of keeping construction sites open. The full text of the letter can be downloaded.
This also remains the formal position of the Construction Leadership Council (CLC) with the qualification that sites should operate in accordance with Public Health England instructions; without compromising health and safety; and in accordance with the Site Operating Procedures issued last week by the CLC.
In practice, many construction sites have been closed by national developers and house builders due to difficulties with staffing and supply chain, and practical issues with compliance with the social distancing and site operating procedures.
The Scottish Government has recently issued guidance that all non-essential construction sites, which includes housing, office, leisure, schools and retail sites, must close to reduce the risk of the spread of Covid-19.
Read more about thisDuring the COVID-19 global pandemic, trials and hearings have been mostly conducted over Skype for Business and various other online platforms. Looking forward to the future, what we have experienced during the lock-down may continue and we believe will make litigation a more streamlined, user friendly experience for litigants.
One example of a regime which has been introduced is hybrid trials for lower value claims. Hybrid trials allow for parties and their witnesses to be linked into the court room by video link, whilst the judge and advocates are present in court. This makes it easier and frees up more time for witnesses, which would otherwise be spent in travel and waiting time, especially for those with other commitments.
With hybrid trials, clients still get a full legal experience and the judge will still apply normal legal principles during the trial. The procedure for the case is the same, both leading up to the trial or hearing and during the case itself; except without the need to physically attend court. It may also mean that there will be less of a backlog arising from the current crisis with cases continuing to be heard, allowing for matters to be listed earlier and a quicker outcome for the parties involved.
The shift to the use of online platforms may prove more practical for all those involved in legal matters. Interim hearings can be heard remotely resulting in a time and cost saving for litigants. Even for the final hearing only the legal representatives need to attend court – again resulting in time and cost savings for all concerned.
Read more about thisIn our latest “in conversation” webinar we discussed the outlook for the corporate transaction market. Whilst it would be a brave person to predict the future of anything at the moment given current circumstances, we were joined by two organisations who are very well placed to provide their views.
John Laud, Head of Corporate Banking for North and West Yorkshire for Barclays, his colleague Stephen Loureda from their Credit Analysis Team, and Jill Williams, Investment Director of Mercia Asset Management’s Growth Fund, were in conversation with Ward Hadaway corporate partners Adrian Ballam and Jonathan Pollard to share their thoughts about how the ‘new normal’ for the transactions market may look:
- With supply chain and forecast prediction challenges, how will banks and investors determine what represents a sound opportunity?
- How will distressed and opportunistic acquisition opportunities be funded, and what is investor appetite for such opportunities?
- How have seller and buyer pricing expectations been impacted as a result of the pandemic?
- How are funders reacting, and how should ambitious businesses respond to the very low, or even negative, interest rates?
We expect this video to be of real value to those businesses whose plans of buying, selling or investment may have been impacted by the current economic crisis, but who are looking at opportunities to determine how they may shape their futures – #gettingbacktobusiness.
Read more about this