Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

How much will I get under the scheme?

If you are eligible you will get a taxable grant of 80% of the average profits from the following tax years (where applicable):

2016-2017

2017-2018

2018-2019

HMRC will add the total profit in each of the three tax years (if applicable). This will then determine the monthly payment, subject to the cap of £2500.

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
When does Flexible Furlough start?

The Flexible Furlough Scheme was introduced from 1 July 2020 and is due to come to an end on 30 September 2021.

Are there any differences in employment status for employment law or for tax purposes?

The key factors for determining status for employment and tax purposes are generally the same. However there are some cases that highlight the different approaches taken by employment tribunals and HMRC when determining status. The important thing to consider for IR35 purposes is that being deemed employed for tax purposes does not mean a contractor is ’employed’. PSC’s can still be used in moving forward but there are likely to be discussions on the commercial aspects of the contractor arrangement. Employment status for tax purposes is likely to come at a cost for both parties.