Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

What challenges to planning permission does the current lockdown situation present?
  • Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
  • Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
  • Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
  • The ability to get people on site to undertake material operations

In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.

If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.

I’m the director of a company. What should I think about before accepting any of the funding that has recently become available?

Directors of a company that is in, or potentially facing, financial difficulty have a duty to act in the best interests of creditors as a whole. Failure to comply with that duty can have consequences for directors (including personal liability and disqualification if directors get it wrong).

The duty to act in the best interests of creditors as a whole begins when the company is (or in some cases is potentially or at risk of becoming) insolvent i.e. its assets are worth less than its liabilities and/or the business is unable to pay its liabilities as and when they fall due. However, just because a company is insolvent doesn’t always necessarily mean than an insolvency process is inevitable. Sometimes, the insolvency might just be caused by a temporary cashflow problem or perhaps wider problems in the business that can be overcome by making changes to the business itself.

In addition to that, the potential liability of directors ramps up even further when the company reaches the stage that the directors have concluded (or ought to have concluded) that there was no reasonable prospect of the business avoiding liquidation or administration. If the business reaches that stage, in addition to having to act in the best interests of creditors as a whole, directors can find themselves personally liable unless, from the time the directors ought to have reached that conclusion, they took every step that they ought to have done to minimise the loss to creditors. This is known as wrongful trading.

On the 25th June 2020, the government introduced new legislation – the Corporate Insolvency and Governance Act 2020 – which includes measures to temporarily relax the rules around wrongful trading with the proposed changes to take effect retrospectively from the 1st March 2020. Essentially, the changes say that any court looking at a potential wrongful trading claim against a director is to assume that the director is not responsible for worsening the company’s financial position between 1st March 2020 and the 30th September 2020. Whilst the wrongful trading rules have relaxed, directors still need to proceed with caution if the business is potentially insolvent as the new Act does alter other potential pitfalls for directors, like the risk of breaching their duties or allowing the company to enter into transactions that can potentially be challenged.

The support being offered by the government is potentially a lifeline for businesses under pressure through no fault of their own, but notwithstanding the recent changes to the wrongful trading rules it is still likely to be important for the board to carefully consider whether it is appropriate to make use of the loans, grants and tax forbearance that are on offer.

Exactly what the board should consider will vary from business to business and getting it right can sometimes involve balancing several different (and at times conflicting) priorities, challenges and concerns.

What is the new Permitted Development Right for restaurants, cafes and drinking establishments?

A new Permitted Development Right has been introduced providing restaurants and cafes, drinking establishments with expanded food provision to temporarily provide takeaway food. The new right came into force on 24 March 2020 and expires on 23 March 2021. The right is subject to three conditions:

  • The developer must notify the local planning authority if the building and any land within its curtilage is being used, or will be used, for the provision of takeaway food at any time during the relevant period
  • Change of use to the provision of takeaway food under the Right, does not affect the use class which the building and any land within its curtilage had before the change of use
  • If the developer changes use to the provision of takeaway food under the Right, the use of the building and any land within its curtilage reverts to its previous lawful use when the Right expires or, if earlier, when the developer ceases to provide takeaway food.

Alcohol will still be subject to the same licensing requirements. At this stage, it is not clear how the Right will interact with any current planning conditions placed on an establishment.  Enforcement however remains discretionary. A link to Statutory Instrument 2020 No.330 is below.

http://www.legislation.gov.uk/uksi/2020/330/made

What happens if a patient is admitted to critical care during the pandemic?
  • On admission to critical care, the risks, benefits and likely outcomes of the different treatment options should be discussed with patients, families and carers so they can make informed decisions about their treatment wherever possible.
  • A member of the critical care team should be involved in these discussions whenever the patient or team needs advice about critical care to make decisions about treatment.
What is the new Permitted Development Right for the construction of new dwellinghouses?

A new Permitted Development Right has been introduced by The Town and Country Planning (Permitted Development and Miscellaneous Amendments) (England) (Coronovirus) Regulations 2020 providing for the construction of new dwellinghouses on detached blocks of flats.

The new Right comes into force on 1 August 2020 and from this date development consisting of works for the construction of up to two additional storeys of new dwellinghouses immediately above the existing topmost residential storey which is a purpose-built, detached block of flats is permitted development.  The Right additionally covers specified associated works, the construction of fire escapes and ancillary structures, bin stores for example.

The Right is subject to detailed criteria being met and to a prior approval process to the Local Planning Authority who can consider the acceptability of the proposed development in a range of respects.  A link to the Regulations is here.

The Regulations additionally include a number of further amendments including additional rights for the holding of markets and for additional temporary uses of land for a time limited period.  They additionally include amendments to existing permitted development rights for the change of use of buildings to dwellinghouses through a requirement that there be adequate natural light in all habitable rooms.