Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
All policies will impose a stringent obligation, often with time limits, for you to notify insurers of circumstances that may give rise to a potential claim under the policy and non-compliance may well negate your cover. If therefore you have potential cover under your policy you must make a precautionary notification to Insurers as soon as possible.
On 6 April 2020 the Government published further guidance to clarify the position with apprentices during the Covid-19 outbreak. The full guidance is available from here https://www.gov.uk/government/publications/coronavirus-covid-19-apprenticeship-programme-response/coronavirus-covid-19-guidance-for-apprentices-employers-training-providers-end-point-assessment-organisations-and-external-quality-assurance-pro
The guidance includes details of the measures implemented by the Education and Skills Funding Agency (ESFA) in order to provide flexibility in delivering apprenticeships in current circumstances. This includes breaks in learnings, delayed end point assessments and alternative arrangements for end point assessments. These measures apply immediately and until further notice.
There are a number of FAQs within the Government guidance which deal with common queries. The guidance contains some technical provisions and we recommend that you take advice if you are furloughing or making apprentices redundant. If you have any additional queries on the practicalities of implementing the ESFA measures please get in touch.
Further guidance changes to apprenticeships due to coronavirus can be found here.
The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.
For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf
Yes, but your claim will be limited to any enhanced contractual payments you make to employees who qualify for the relevant family related pay.
All maternity and parental rights remain in force for anyone in this category who is furloughed. However you may need to calculate average weekly pay differently if the employee was furloughed and then started family related leave on or after 25 April 2020.
Furlough pay cannot be claimed for the period that an employee is receiving Maternity Allowance. An employee can agree to accept furlough pay but they must contact Jobcentre Plus to stop their Maternity Allowance payments for this period.
The CMA is particularly concerned about certain activities, its guidance highlights:
- Exchange of commercially sensitive information where this is not necessary in response to the crisis
- Collaboration which unfairly excludes third parties
- Abuse of a dominant position (including a dominant position held as a result of the crisis) – particularly to charge excessive prices
- Seeking to maintain prices or prevent reductions in prices
- Cooperation going beyond what is necessary to respond to the crisis in the interests of consumers