Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

Other considerations – the mental health and wellbeing of BAME staff and others

Undeniably and understandably BAME staff, as well as those staff who are identified as being at a higher risk, are going to have high levels of stress and anxiety. For some, this may become of such severity that those staff should be considered to be disabled under the Equality Act 2010. The question as to whether someone is disabled is one that should be answered in conjunction with appropriate medical advice. But the question about how to support any staff suffering with stress and anxiety should not be left until that stage. Proactive steps need to be taken and expert advice obtained on what support measures should be put in place. We know that many NHS organisations are already giving the mental wellbeing of their staff the highest priority.

From our perspective, we would ask managers to be mindful that stress and anxiety is likely to feature in how an individual reacts to questions about the level of risk to their health and the impact on their duties. The conversations with some staff may not be easy to have and may be met with challenge.

For those staff who’s stress and anxiety is such that it would qualify as a disability, reasonable  adjustments will need to be considered to the processes that you are applying.

An additional point to consider – it might be worth writing to all staff, asking them to come forward if they have any health conditions that they think you ought to be aware of, assuring them that such information is being given in the strictest confidence. You want to make sure that you are taking the appropriate measures to ensure their health and safety.

Are there any limitations on who can be furloughed?

 

Employees on any type of employment contract including full-time, part-time, agency, flexible or zero hours and foreign nationals who are eligible to work in the UK on any visa can be furloughed subject to the following excluded categories:

  • Anyone who was not employed prior to 30 October 2020
  • Anyone for whom you haven’t made a PAYE Real Time Information submission to HMRC between 20 March 2020 and 30 October 2020.
  • Employees who are working but on reduced hours or for reduced pay
  • Employees currently receiving SSP (see FAQ on SSP and self-isolation below)
  • Public sector employees
  • Employees of businesses or organisations in receipt of public funding for staff costs (except for those who are not primarily funded by the government and whose staff cannot be redeployed to assist with the Covid-19 response)
Is there a time limit on making an insurance claim?

All policies will impose a stringent obligation, often with time limits, for you to notify insurers of circumstances that may give rise to a potential claim under the policy and non-compliance may well negate your cover. If therefore you have potential cover under your policy you must make a precautionary notification to Insurers as soon as possible.

My visa is about to expire, can I apply to extend it?

Yes, you should submit a new visa application before your current visa expires.

The visa application is a two stage process:

  • First you submit the online application and pay the fee
  • Second you attend a visa application centre to enrol your biometrics and verify your passport.

Submitting a valid online application before your current visa expires secures your right to continue living and working in the UK, even after your current visa has expired.

Visa application centres across the world have been closed due to covid19 but are now mostly re-open to enable you to book an appointment to complete your application, albeit some are experiencing a backlog of applications.

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.