Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
You cannot include the following payments in a claim:
- Discretionary bonus or commission payments
- Tips
- Non-cash payments
- Non-monetary benefits including taxable benefits in kind
- Salary sacrifice benefits that reduce an employee’s pay (however HMRC has agreed that such arrangements can be stopped by agreement if due to COVID-19 and the contract is changed)
The updated guidance has confirmed that all of the grant claimed should be paid to the employee in the form of money and that none of the grant is to the used to pay for the provision of benefits or a salary sacrifice scheme.
Residents will be obliged to:
- Not act in a way that creates a significant risk of a building safety risk materialising
- Not interfere with building safety equipment in the common parts
- Comply with an Accountable Person’s request for information in relation to the assessment and management of building safety risks.
The Accountable Person then has powers in relation to these duties, including:
- Issuing a contravention notice, requiring a resident to pay for replacement or repair of safety equipment which they have interfered with
- Applying for court orders in certain situations
- Requesting access at a reasonable time (in writing with at least 48 hours’ notice) to a resident’s property for the purposes of assessing or managing building safety risks, or checking compliance with the resident’s duties as above.
Secondary legislation is still awaited to bring these provisions into force, so the timing is unknown, but it will likely be within the next 12 months in line with the anticipated timetable for the remainder of the Act.
The Commission has provided guidance as to measures which Member States can introduce without notification. These include:
- Measures which apply to all businesses within a Member State (for example the furloughing measures introduced by the UK Government)
- Measures providing support direct to consumers
- Measures which are already exempt from the notification requirement (discussed further below).
To respond to the crisis the European Commission has also issued a temporary framework to provide a basis for emergency aid to be notified for approval. The framework is initially in place until 31 December 2020. The Commission continues to keep this under review and has twice widened its scope to allow more types of aid to be notified. The type of measures covered include:
- The provision of guarantees (including guarantees for 100% of loans)
- The provision of loans at low interest rates, at zero interest rates or subordinated to senior debt
- Measures to support liquidity needs or to alleviate difficulties caused by the current crisis
- Measures to recapitalise businesses
- Measures to assist sectors hit particularly hard by the current crisis (eg transport)
- Measures targeted at COVID-19 such as research and development or production of products related to tackling the virus
The Commission has approved a UK Government “umbrella” notification to allow UK public authorities to adopt the measures permitted by the Commission framework. Therefore public authorities in the UK can use the Framework without notifying individual measures or schemes to the Commission.
The vast majority of disputes settle without ever reaching a final hearing with something in the region of 2-5% of all cases actually ending up in court at a final trial. So whilst it is very unlikely you would need to attend a court hearing, it is always a possibility.
That will depend on the terms of your facility and the stance taken by your bank.
Banking facilities often place obligations on businesses to stick to certain financial criteria. For example, an obligation to keep turnover or profit above certain levels or a commitment to keep the bank’s exposure within an agreed percentage of the value of the company’s assets (known as loan to value ratio).
The consequences of breaching those covenants will depend on the terms of your facility, but normally this amounts to an event of default. Events of default can result in the loan (or whatever form the facility takes) becoming repayable and could give the bank certain powers to take action to recover the money that they are owed.
Whether the bank will take action during these unprecedented times is another matter, particularly given the extent of support being offered to businesses via mainstream lenders and the political desire to keep viable businesses up and running. Lenders themselves will no doubt wish to remain supportive where possible. The underlying performance of the business (and whether but for the effects of Covid-19 it would have been in a healthy financial position), the relationship you have with the bank and your history with them will no doubt be relevant to the approach taken by the bank. However, early engagement with your bank (as well as other key stakeholders in the business) will be important.