Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

My business involves providing services to consumers. What are my legal obligations in relation to deposits paid by consumers for services that I have been unable to perform due to government restrictions?

Many businesses that supply directly to consumers have been concerned to understand their legal position in relation to services that have been cancelled, or that they have been unable to perform, because of the Covid-19 pandemic, and in particular how to deal with deposits paid by consumers for such services. With some degree of restriction on the hospitality and tourism sectors likely to remain in place for some time, such questions will remain important for the foreseeable future.

What impact does the Regulations have in respect of matters which arise from Fire Safety Audits - e.g. if balconies with wooden/decking elements are now considered higher risk and whether that would fall to developer to remedy the materials used to construct balconies?
The duty would fall on the owner of the building to control the hazards presented by balconies made from combustible materials. There may be scope (via warranties/indemnities or other terms) arising from the contract between the developer and owner for the owner to seek to recover the cost of remedial works.
What facilities are available under CBILS?

Lenders implementing the Scheme can assist in a number of ways, including:

  • Term loans
  • Overdrafts
  • Invoice finance
  • Asset finance facilities

The maximum value available under the scheme is £5m, with repayment terms of up to six years for term loans and asset finance. Overdrafts and invoice finance facilities will be available for up to three years.

Can I still progress with stopping up applications?

We are working with many of our clients to progress with stopping up applications in order to divert/stop up highways and public rights of way affecting development sites. Due to lockdown restrictions the Department for Transport stalled the progress of applications because they were unable to comply with the statutory publicity requirements. We have very recently been contacted by the Department for Transport casework team who have confirmed that the stopping up/diversion applications can now be progressed. We are aware that Councils across the country are also now progressing with applications. Please contact us if you require any advice/assistance in respect of your application.

How do I apply for an extension to Companies House?

The application is made via the Companies House website, and only takes a few minutes to complete. Companies House have indicated that the extension is “automatic and immediate” and will be for three months.

Having said that the extension is “automatic”, their website also says that Companies that have already extended their filing deadline, or shortened their accounting reference period, may not be eligible for an extension.

If an extension is granted, it will not affect the due date for filing accounts in future years – so the deadline will revert to the usual date for the next accounting period.