Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
No, there is no obligation on employers to offer a flexible furlough arrangement to staff. Operationally, flexible furlough may not be appropriate for your business and equally, returning on a part-time basis may not be suitable for individuals already furloughed for various reasons. Concerns about returning to work part-time or at all should be considered on a case-by-case basis.
There are four criteria which must be satisfied if an agreement is to be considered exempt:
- It must improve production or distribution, or promoting technical or economic progress – the guidance suggests that cooperation ensuring essential goods and services can be made available to the public, or an important sub-set of the public such as key workers, will satisfy this criterion.
- It must allow consumers a fair share of the resulting benefit – the guidance suggests this will be the case where the action prevents or reduces shortages.
- It must not impose on the undertakings concerned restrictions which are not indispensable to the attainment of the above benefits – the guidance suggests this will be the case where the cooperation is the only reasonable option due to the urgency of the crisis and where the cooperation is temporary in nature.
- It must not afford the undertakings concerned the possibility of eliminating competition – therefore the parties must endeavour to retain competition in respect of the products (in particular price competition).
The Bill allows the Secretary of State to make regulations to temporarily extend various filing date deadlines for companies. These include deadlines for filings accounts, confirmation statements, charges register, director and secretary appointments and resignations. The extended period must not exceed 42 days where the existing period is up to 21 days, or 12 months where the existing period is 3, 6 or 9 months.
The recommendation is every 3 years, however it is recommended that MHFAs receive regular ongoing training and support.