Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

Will remote court hearings be permitted?

Court hearings have been conducted remotely, with the judgment in Kerry v SSCLG being given via telephone. The Senior President of Tribunals issued emergency Practice Directions which will apply to Property and Lands Chambers’ respectively. This has made provision for remote hearings. Inspections of properties have been suspended with immediate effect, with photographs, videos or external visits permitted where appropriate. Where inspections are essential, the case should be stayed.

What is my legal position if emergency legislation to tackle the outbreak makes performance of a contract illegal or impossible?

As the coronavirus outbreak continues to develop, we have seen many countries begin to implement emergency procedures and legislation in an attempt to control the spread of the disease.

These have included bans on gatherings and public events, closures of shops, bars, restaurants and public spaces, and full lockdowns which restrict all but key workers to their homes except in certain limited circumstances.

This has a direct impact on businesses and their ability to operate. So what happens if a contract becomes impossible to perform because of emergency legislation?

For example:

  • If you are a hospitality business, you have agreed to host an event, and gatherings are prohibited
  • If you are a manufacturer or service provider, and your staff are required to remain at home, making performance of the contract impossible
Do I still need to pay instalments of Community Infrastructure Levy (CIL) while the development site is closed?

Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.

New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.

For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.

Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.

For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.

What type of matters are the Courts still dealing with?

Civil Court listing priorities, last updated by HMCTS on 24 April 2020, categorise the Court’s work into the following:

Priority 1 – work that must be done: this includes any applications in cases listed for trial in the next 3 months, any applications where there is a substantial hearing listed in the next month, all multi-track hearings where parties agree that it is urgent (subject to triage).

Priority 2 – work that could be done: Infant and Protected Party approvals, Applications for interim payments in multi-track / personal injury / clinical negligence cases, Applications to set aside Judgment in default, Preliminary Assessment of costs.

The full guidance can be found at:

https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/881019/Civil_court_listing_priorities_24_April_2020.pdf

Can I have legal documents signed and witnessed?

Solicitors can be authorised to sign contracts for their clients – a signed letter of authority should be scanned and sent to avoid posting potentially contaminated documents.

Solicitors should exchange supplemental agreements on behalf of their clients to agree to postpone exchange and completion dates if it has been agreed to push these back.

The Law Society advises that electronic signatures be used as much as possible for contracts, to avoid possible contamination. However, the Land Registry confirms that the legal transfer document cannot be validly executed with an electronic signature. Solicitors should agree a completion undertaking that the original transfer document will be sent when received and after the restrictions have been lifted.

The Land Registry’s latest guidance https://www.gov.uk/guidance/coronavirus-covid-19-impact-on-hm-land-registrys-services published on 14 May states:

We accept deeds that have been signed using the ‘Mercury signing approach’.

For land registration purposes, a signature page will need to be signed in pen and witnessed in person (not by a video call). The signature will then need to be captured, with a scanner or a camera, to produce a PDF, JPEG or other suitable copy of the signed signature page. Each party sends a single email to their conveyancer to which is attached the final agreed copy of the document and the copy of the signed signature page.

Solicitors should be willing to adopt this procedure for completing transactions to enable them to be registered by the Land Registry.

The execution of a transfer is a deed and must be witnessed. Members of the family can witness signatures so long as they are not also a party to the document. A witness will be more credible if they are 18 or over, but this is not a legal requirement. The legal requirement is for the witness “to be present” when the document is signed. It would be possible for a witness to be on the other side of the room or the other side of a window, and validly witness the execution of a deed. The witness does need to take precautions to avoid possible contamination from the document.

A statutory declaration does not need to be witnessed but must be administered by a solicitor or commissioner for oaths. There is no legally prescribed process for this, and there is nothing to suggest that this could not be validly done via a video telephone call if the signature on the declaration can clearly be seen by the person commissioning the oath when the oath is made.