Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

Forcing annual leave

Employers have a statutory right to require employees to take annual leave at their direction, subject to providing staff with notice equal to at least double the length of the leave that you are directing them to take (e.g. 10 days’ notice for five days leave). However, this measure is not likely to achieve any urgent cost savings or alleviate immediate cash-flow pressure as holidays would need to be paid.

Clearly, annual leave can be taken on furlough so you could have staff on furlough and annual leave.

Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?

The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.

The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.

The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:

  • Amending the contract requirements
  • Varying timings of deliveries
  • Relaxing KPIs or service levels
  • Extending time for performance (e.g. revising a contract delivery plan), and/or
  • Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).

These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.

A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.

If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.

 

 

What fees will I pay for a loan under CBILS?

Borrowers will not have to pay a guarantee fee. Lenders will pay a fee to access the scheme. The Government will make a Business Interruption Payment to cover the first 12 months of interest payments and any lender-levied fees, allowing smaller businesses to benefit from no upfront cost.

British Business Bank has indicated that following earlier discussions with the banking industry, some lenders indicated that they would not charge arrangement fees or early repayment charges to SMEs borrowing under the scheme. Each business should check the terms of the loans being made to ensure this is the case and what the interest rate and prepayment fees will be following the period in which the Government makes payment of these amounts.  

Are benefits to be included in the claim for a grant?

You cannot include the following payments in a claim:

  • Discretionary bonus or commission payments
  • Tips
  • Non-cash payments
  • Non-monetary benefits including taxable benefits in kind
  • Salary sacrifice benefits that reduce an employee’s pay (however HMRC has agreed that such arrangements can be stopped by agreement if due to COVID-19 and the contract is changed)

The updated guidance has confirmed that all of the grant claimed should be paid to the employee in the form of money and that none of the grant is to the used to pay for the provision of benefits or a salary sacrifice scheme.

Which properties should I prioritise?

Some organisations are prioritising properties, known to be higher risk, such as properties with open flues, or near to the certificate expiry date.

Vulnerable staff and tenants need protection, safe working practices need to be established, and communicated. Organisations should bring forward servicing for people known to be vulnerable – but bearing in mind the guidance as to preserving the annual test date.