Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
Many businesses that supply directly to consumers have been concerned to understand their legal position in relation to services that have been cancelled, or that they have been unable to perform, because of the Covid-19 pandemic, and in particular how to deal with deposits paid by consumers for such services. With some degree of restriction on the hospitality and tourism sectors likely to remain in place for some time, such questions will remain important for the foreseeable future.
- It is important to have a clear paper trail for any agreed reduction in salary, and hence any reduction in the amount of contributions. However, the contribution rates (as opposed to the amounts) should be the same as normal, and hence all processes and software should function as per normal and, amongst other things, remain compliant with auto-enrolment employer duties.
- However, if the period of affected contributions does not overlap precisely with the period of reduced salary, for example because of different cut-off dates, there may well be instances of non-compliance with auto-enrolment employer duties at the beginning as well as at the end of the period covered by the Coronavirus Job Retention Scheme.
- Accordingly, where an employer takes advantage of the Coronavirus Job Retention Scheme, good communication with the persons responsible for pensions administration and detailed record-keeping are essential to prevent non-compliances in the short-term and confusion in the long term.
There is not a magic number. It depends on the nature of the organisation, the work carried out, the organisational structure, the geographical spread, working patterns and conditions. We would give specific advice personalised to the organisation and taking all these and other factors in to consideration. There is no such things as too many MHFAs!
The fee payer that pays the fee to the contractor’s PSC for the services (end user client or agency) will be responsible for operating PAYE and deducting NIC’s. The fee payer must also pay employer NIC’s and where applicable the apprenticeship levy so there will be additional costs involved in the event of a change to employed status for tax purposes.
If the assessment concludes that the contractor is self-employed, the PSC can continue to be paid gross.
If the business has areas requiring an increased workforce whilst others require a reduced workforce, staff can be retrained and redeployed across the organisation or even across a wider group of companies. This will not reduce the wage bill but will avoid the need for redundancies. Making fundamental changes to an employee’s role and duties will require their agreement following a fair selection and consultation process.