Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.
The CMA is the government body that is responsible for protecting consumers from unfair trading practices. It has announced programme of work to investigate reports of businesses failing to respect cancellation rights during the Coronavirus pandemic.
Based on the complaints received by them from consumers, the CMA has identified three sectors of particular concern:
- Weddings and private events
- Holiday accommodation
- Nurseries and childcare providers
The CMA has expressed concern about the number of complaints that it has received about businesses seeking to retain deposits for cancelled events, undue restrictions being placed on use of vouchers provided for cancelled bookings, and payments being demanded to hold open nursery places.
The CMA has said it will prioritise investigation of these sectors, and then move on to other sectors.
Partner at Ward Hadaway Adrian Ballam catches up with corporate finance expert and CBILS specialist Chris Silverwood (CorpFin and cashflow.co.uk) a month after their initial conversation to talk about what the last couple of months have taught us about access to finance.
Sections of the video and their timings are as follows:
(01.06) – example of continuing appetite for certain businesses (e.g. tech sector)
(02.06) – conflict between incumbent bank and different CBILS lenders, plus brief discussion of CBILS II
(05.36) – bounce back loans have been a distraction
(06.27) – muted impact of fintech CBILS lenders
(07.52) – discussion about invoice discounting
(11.59) – looming insolvency environment
(12:52) – emerging themes
If a business has been provided with a loan from 23 March on commercial terms, providing the borrower meets the CBILS eligibility criteria, lenders have been asked to bring these facilities onto CBILS wherever possible (e.g. where the lender is accredited to offer the same facility through CBILS) and changes retrospectively applied as necessary. Please contact us if this applies to you and we can review facilities and advise upon the potential changes that may be made retrospectively to the benefit of the business.
Ultimately closing a service will be a decision that is taken at the highest level and that decision will depend on risk appetite. Often these types of higher risk are mitigated by way of insurance but that still depends on an insurer being willing to accept that risk. This decision will depend on accepting a known risk and its consequences.