Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.
If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.
It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.
Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.
Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.
a. You should first try and discuss this with your ex-partner, either directly or through a Solicitor, to see whether an amicable agreement can be reached.
If you contribute to private school fees voluntarily, it is a matter for you and your ex-partner to resolve the issue with the school, depending whose name is on the bills. You may need to speak to the children’s school to see whether they can offer any reductions or remedies in relation to those payments. If you contribute to the school fees as part of a Court Order, you will need to ensure you do not breach the Order and you may need to consider applying for a variation of the Order if you can no longer afford the payments or reach a compromise agreement with your ex-partner.
You can use the Child Maintenance Service (CMS) calculator (https://www.gov.uk/calculate-child-maintenance) to recalculate your child maintenance obligations using your amended income. This recalculation can then be used in your discussions and you can formally instruct the CMS to verify that calculation if you and your ex-partner cannot reach an agreement about it. If you have already formally involved the CMS, they do carry out an annual review of child maintenance payments, however, they will also recalculate payments outside of the review period where there has been a change in income of 25% or more. We expect the CMS will be experiencing a high volume of enquiries at the present time so anticipate there may be delays in them assisting.
The position on child maintenance payments included in a Court Order are slightly more complicated and how you approach this will depend on how much time has passed since the date of the Order.
Most rent suspension clauses in commercial property leases are unlikely to come to the assistance of the tenant. These clauses normally apply only where the premises has suffered substantial physical damage and are, as a consequence, incapable of being occupied, used or accessed. The coronavirus pandemic does not involve any physical damage to a property, loss from the crisis will be purely financial. Such losses then will not be covered by the landlord’s buildings insurance policy in a way that will allow a tenant to claim rent suspension.
You should have in place a dispute resolution procedure that sets out the appeal process or contractors or the agency as appropriate. You must respond to an appeal within 45 days.
If the status determination is disputed you should consider the contractor or agency’s reasons objections. You must consider if the original determination is to be maintained and give reasons for this. Or a new determination with reasons can be provided if appropriate.
Records of disputed determinations and the outcome of any appeal should be kept.
If it is not possible to find work for the employee to do at home, you do have the option of putting the employee on furlough.