Skip to content

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

Should Covid-19 be recorded as a cause of death?

The Chief Coroner supports the position, communicated by NHS England and the Chief Medical Officer that Covid-19 is an acceptable direct or underlying cause of death for the purposes of completing the Medical Certificate of Cause of Death (MCCD) and is considered a naturally occurring disease. This cause of death alone is not a reason to refer a death to a coroner under CJA 2009.

If the cause of death is believed to be due to confirmed Covid-19 infection, there is unlikely to be any need for a post mortem to be conducted and the MCCD should be issued, and guidance is given on how this is delivered to the Registrar in the event of the next of kin/informant being in self-isolation. 

In a hospital setting the MCCD process should be straightforward because of diagnosis and treatment in life. This may be more complex in a community setting. The Coronavirus Act 2020 however expanded the window for last medical review from 14 to 28 days. Outside of this, the death will need to be reported to the coroner.

Although Covid-19 is a naturally occurring disease, there may be additional factors around the death which mean it should be reported to the coroner; for example, the cause of death is unclear, or where there are other relevant factors. Guidance is given to coroners on how to manage such reported deaths, particularly where post mortem examinations may not be readily availability.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
What will be the added cost to business of furloughing staff from 1 July 2021?

Similar to the position for claims between 1 August 2020 and 31 October 2020, for claims between 1 July 2021 and 30 September 2021 there will be a cost to businesses of furloughing staff, which will gradually increase until the scheme closes at the end of September as follows.

  • From 1 July 2021 employers will be required to contribute 10% of wages, with the Government contributing 70%.
  • From 1 August 2021, the employer contribution increases to 20% and the Government will contribute 60%.
  • 30 September 2021: scheme closes.

Employees will continue to receive 80% of their current wages, up to £2,500 a month.

 

What are the temporary adjustments to Right To Work checks?

To facilitate social distancing the Home Office has stated that as of 30 March 2020, the following are permitted:

  • The RTW check can now take place over video call.
  • Job applicants no longer have to send original documents but can send scanned copies or photos to the employer.
  • Where the job applicant cannot provide these documents, employers can use the Employer Checking Service and if they have the right to work, then the employer will receive a Positive Verification Notice which will provide the employer with a statutory excuse for 6 months.

These adjustments remain in place until the Home Office confirms otherwise.

 

Can I wait until April to carry out assessments?

We don’t recommend this. Status determination statements must be issued before 6 April 2021 for current engagements and the appropriate deductions are to be made on payments for services carried out on or after 6 April 2021.