Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
It has also been proposed in the Corporate Insolvency and Governance Bill that public companies who were due to file their accounts in the period from 26 March 2020 to 30 September 2020 will have until the earlier of the 30 September 2020 and the date which is 12 months after the end of their relevant accounting period to do this.
This is separate from the pre-existing scheme, announced on 25 March 2020, whereby companies can apply to Companies House for a 3 month extension for filing their accounts.
The duty is to inform and consult appropriate representatives of the “affected employees”.
Note that the term “affected employees” means those who may be “affected by the proposed dismissals or who may be affected by measures taken in connection with those dismissals”. The term extends beyond those immediately at risk of dismissal to include those affected by measures associated with the redundancies.
“Appropriate representatives” can be:
- The Trade Union (if recognised)
- (For any roles not covered by collective recognition) any existing standing body of elected or appointed employee representatives (if already in place)
- Employee representatives, who are elected specifically for redundancy consultation
The workplace will not revert to its pre-Covid-19 state overnight, with social distancing in the work place likely to remain in place for quite some time to come.
This could mean that businesses will need to think carefully about how their capacity will be impacted, and how this will affect their ability to perform contractual obligations.
For example, if a business has an outsourcing contract under which it has to perform a business process, or produce a particular output, will it be able to comply with contractual performance standards whilst social distancing is still in place? In the context of a manufacturing business, what will be the impact on production schedules and delivery dates? There might also be an impact on operating costs, for example if processes are changed and additional shifts are introduced – can these additional costs be sustained?
Businesses need to plan a safe system of work for their employees to ensure they comply with Health and Safety legislation, but they also need to consider how this will impact on their ability to perform pre-existing contractual obligations. Ultimately, contractual arrangements with customers might need to remain on a revised footing for a number of months.
Getting to a point where agreement is reached on allocation of additional costs and/or changes to key elements of a contract such as scope of work, performance standards and delivery date will require co-operation between contracting parties. Again, it is important that any variations that are agreed are recorded properly and follow the required contractual procedures.
At the discretion of the lender, the Scheme may be used for unsecured lending for facilities of £250,000 and under.
Lenders were required to demonstrate lending additionality (i.e. lending that without the Scheme, wouldn’t have otherwise taken place). The Scheme has been extended to those businesses who would have previously met requirements for a commercial facility and would not have been eligible for CBILS. As a result it is suggested that all viable small businesses affected by Covid-19, and not just those unable to secure regular commercial financing, will now be eligible should they need finance to keep operating.
Primary Residential Property cannot be taken as Security under the Scheme. If the lender can offer finance on normal commercial terms without the need to make use of the Scheme, they will do so.
During the Covid 19 crisis lawyers and the courts have had to adapt with hearings being heard remotely and with more electronic communication. It is clear that going forward, some of these changes will become more permanent.
The Lord Chancellor, Robert Buckland QC MP, has spoken last week regarding changes to the justice system following the COVID-19 pandemic and we know that there is a significant backlog of work that needs to be processed.
Firstly, 10 sites have been identified for ‘Nightingale courts’ which will allow for better social distancing. The authorities have suggested that it is a possibility that courts will need to stay open for a longer time or at weekends, to increase the number of cases that can be heard safely on any given day. This will enable more cases to be heard in a day and therefore a swifter outcome for your case. The standard of video technology will also continue to improve, with plans for new technology being rolled out across all courts form July onwards. The enhanced use of technology may result in matters being heard more efficiently, decreasing the time spent during each hearing.
HMCTS is working to expand access to audio and video technology to support more and new types of hearings. There has been an increase in the use of new and varying equipment over the lock-down period. With the appropriate systems in place, many more hearings could take place on platforms such as the Cloud Video Platform (CVP). Throughout July, the CVP will be more readily available to Country courts. There will be further hardware rolled out to improve the quality of video hearings, and there will be more efficient methods used to organise video lists.
The increased use and training of CVP means that witnesses and advocates may not need to attend court and could attend the hearing remotely. This will give you increased flexibility, enabling you to attend from your office or home. The CVP is efficient and simple to use, with no complex functions; making it user-friendly. This should make litigation more time and cost effective (albeit that there will be the cultural challenge of having less contact with your legal team or the court experience).