Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

Does the introduction of CLBILS assist private equity-backed businesses?

Under CBILS, for the purposes of calculating the applicant’s annual turnover, approved lenders have been aggregating turnover across the whole of the private equity investor’s portfolio meaning they failed to qualify for the scheme as they were deemed to exceed the £45 million threshold.

For private equity-backed businesses, the removal of the upper limit on annual turnover criteria for CLBILS seemingly avoids the issue of turnover aggregation across investment portfolios seen with the CBILS, potentially enabling more private equity sponsor portfolio companies to be able to access the CLBILS funding.

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

Capability issues

All organisations have underperformers. Capability is a potentially fair reason to dismiss and is separate to any redundancy procedures.

Generally, capability falls into either absences through illness or underperformance in the role. Those who are absent through sickness can be furloughed, but when furlough comes to an end they will need to go back onto sickness. If you are looking to tackle absence then you need to tackle long term and short term absence in a different way.

Long term absence: You need to establish whether the employee is able to return to work (with or without reasonable adjustments) in the medium term. This requires medical opinion and be careful of disability issues. Reasonable adjustments are likely to be important.

Short term absence: You will need to demonstrate that you have fair absence triggers in place and there is normally be a 3 stage procedure: warning and final warning followed by dismissal on notice. Each stage needs a fair procedure, with written information, a fair hearing and the opportunity to appeal. Be careful of disability issues.

As for underperformance: To tackle this, you will need to have clear SMART objectives in place and evidence of the employee failing to meet these. There would then normally be a 3 stage procedure: warning and final warning followed by dismissal on notice. Each stage needs a fair procedure, with written information, a fair hearing and the opportunity to appeal.

Can an employee still do training when on Flexible Furlough?

Employees on Flexible Furlough can engage in training during hours which you record your employee as being on furlough, as long as in undertaking the training the employee does not provide services to, or generate revenue for, or on behalf of their organisation or a linked or associated organisation.

Where training is undertaken by furloughed employees during hours which you record your employee as being on furlough, at the request of their employer, they are entitled to be paid at least their appropriate national minimum wage for this time.

How do you support your Mental health first aider (MHFA) team?

We recommend that ongoing support is provided to all MHFA’s beyond completion of the MHFA training. It is necessary to do refresher training (approx. every 3 years) and ideally ongoing ‘continued professional development’ should be provided as well as regular opportunities for debriefing / seeking support. One way of supporting your MHFAs in the workplace is by creating a buddy system amongst the MHFAs. That way the individuals carrying out the role of MHFAs have a support structure in place amongst themselves. All trained MHFAs can also reach out to management to discuss any concerns they have or to seek any further support they need.