Can construction work be undertaken outside of any permitted hours to make up for site closures?
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Related FAQs
An extension to the traditional business interruption insurance, “contingent business interruption insurance” often covers areas such as business interruption due to damage to property of a customer or suppliers. Nonetheless, proving loss can be problematic.
Claims for loss of use of the property may be possible as a result of forced business closure due to lockdown. Accordingly policies should be carefully reviewed to see if cover is available.
Maintenance Orders embodied in a Court Order are variable. If you have lost a very large part of your income, then the Courts ought to take that into consideration when looking at a Court Application to reduce or end spousal maintenance payments. The outcome of any Court Application will, however, depend on a number of factors.
Technically, you should not just stop paying or reduce the maintenance payments, as your ex-spouse could then make an Application to Court for enforcement and payment of the arrears. You could ask the Court to forego you having to pay those arrears if you had evidence to prove that you could not make the payments, however, the Court will need to take a fair approach and you should not assume this request will be agreed.
You should first try to negotiate a reduction or termination of the maintenance with your ex-spouse, either directly or through a Solicitor. If this is possible, you should obtain a Court Order reflecting that agreement. Where a sensible compromise cannot be reached, a Court Application may be necessary.
Some of these can be implemented by you, some need agreement or consultation and some depend on the wording of contracts. We’ll explain more in relation to each option.
It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.
If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.
It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.
Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.
Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.
Another obvious cost cutting measure is to reduce working hours, either temporarily or permanently. Again, it should be done fairly, either across the board or by selecting teams/individuals based on objective business reasons. Imposing without agreement would create significant risk, therefore would require fair selection and consultation.