Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Related FAQs

What actions and measures should be avoided?

The CMA is particularly concerned about certain activities, its guidance highlights:

  • Exchange of commercially sensitive information where this is not necessary in response to the crisis
  • Collaboration which unfairly excludes third parties
  • Abuse of a dominant position (including a dominant position held as a result of the crisis) – particularly to charge excessive prices
  • Seeking to maintain prices or prevent reductions in prices
  • Cooperation going beyond what is necessary to respond to the crisis in the interests of consumers
BSA 2022 states that RP’s will have greater powers (to encourage residents to provide access and to fulfill their duties). What are these powers and when are they expected?

Residents will be obliged to:

  • Not act in a way that creates a significant risk of a building safety risk materialising
  • Not interfere with building safety equipment in the common parts
  • Comply with an Accountable Person’s request for information in relation to the assessment and management of building safety risks.

The Accountable Person then has powers in relation to these duties, including:

  • Issuing a contravention notice, requiring a resident to pay for replacement or repair of safety equipment which they have interfered with
  • Applying for court orders in certain situations
  • Requesting access at a reasonable time (in writing with at least 48 hours’ notice) to a resident’s property for the purposes of assessing or managing building safety risks, or checking compliance with the resident’s duties as above.

Secondary legislation is still awaited to bring these provisions into force, so the timing is unknown, but it will likely be within the next 12 months in line with the anticipated timetable for the remainder of the Act.

Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

What are the minimum consultation time limits?

Where an employer is proposing to dismiss:

  • 100 or more employees at one establishment within a 90-day period, consultation must begin at least 45 days before the first dismissal takes effect
  • Between 20 and 99 employees within a 90-day period, consultation must begin at least 30 days before the first dismissal takes effect
  • If you are proposing to dismiss less than 20 employees then there are no minimum time limits but you must adhere to a fair process which will involve individual consultation and providing the employee with a right of an appeal
Alternatives to redundancy toolkit

We have developed a Toolkit to help with these issues. The Toolkit contains:

  • LO1 How to Guide: Lay off and short time working
  • LO2 Letter directing employee to take annual leave
  • LO3 Letter confirming lay off (contractual right)
  • LO4 Letter confirming short time working (contractual right)
  • LO5 Letter proposing lay off (no contractual right)
  • LO6 Letter proposing short time working (no contractual right)
  • LO7 Counter notice disputing entitlement to claim redundancy payment
  • LO8 Script for announcing lay off or short time working (contractual right)
  • LO9 Script for announcing lay off or short time working (no contractual right)
  • LO10 Letter proposing reduction in working hours and pay

The cost of this Toolkit is £500 plus vat. If you would like to find out more about the Toolkit, please speak to your usual Ward Hadaway employment contact, or get in touch one of the contacts at the bottom of this page.