Skip to content

Can I argue that my contract has been frustrated?

It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.

If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.

It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.

Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.

Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.

Related FAQs

Does Force Majeure apply to the leasing of commercial property?

Some commercial tenants have queried whether the current situation is a force majeure which may allow it to terminate the lease. Clauses which allow a party to terminate a lease for a force majeure event or, to put it another way, an “act of God”, are however extremely rare in modern commercial leases. Even if there is such a provision in your lease, it would need to be drafted to apply to an outbreak of disease.

What criteria will HMRC use to assess applications for furlough from publicly funded organisations?

The government released further clarification on the Coronavirus Job Retention Scheme on 4 April. The wording referred to concerning public sector organisations and organisations receiving public funding remains the same.

The revised guidance does provide a helpful insight into how HMRC will deal with applications made to it for assistance under the scheme. It appears that there won’t be a particularly forensic approach adopted by HMRC. The guidance says you can furlough staff if you cannot maintain your current workforce because your operations have been severely affected by coronavirus.

It goes on to say that all employers are eligible to claim under the scheme and the government recognises different businesses/organisations will face different impacts from coronavirus. The need to demonstrate the impact of coronavirus on your business/organisation is not one of the criteria businesses/organisations are going to need to satisfy, so the government does not appear to intend to set a specific test to determine if a business/organisation is “severely impacted by coronavirus”. It is hoped that this should provide additional comfort to publicly funded organisations facing significant restrictions to their operations during the Covid-19 crisis.

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

How important is social distancing when planning your workplace?

It is absolutely critical to creating a safe workplace and to making workers feel secure.

This could include floor markings every 2m (as we’ve seen in grocery stores), stopping or limiting/staggering access to communal or common areas such as toilets and kitchens, rearranging workstations to maintain a 2 metre distance or, where this is not possible (for example in manufacturing facilities or production lines), erecting physical barriers and avoiding face to face working, encouraging the use of stairs and discouraging lift-use, designing a one-way system for entry and exit and looking at aircon/heating systems to see if any modifications are possible to prevent the spread of airborne particles. If you can increase ventilation in your workplace, it will help reduce risk.

The government has published detailed social distancing guidance for workplaces across sectors including manufacturing, retail, offices, construction and transport; it has also promised to continue to add to this.

What are the NICE protocols around a patient’s ongoing treatment whilst in critical care during the pandemic?
  • Start critical care treatment with a clear plan of how the treatment will address the diagnosis and lead to agreed outcomes.
  • Review critical care treatment regularly and when the patient’s clinical condition changes.
  • Stop critical care treatment when it is no longer considered able to achieve the desired outcomes. Record the decision and the discussion with family, carers and the patient (if possible).