Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.
Related FAQs
For the purposes of collective consultation, making someone redundant and/or changing terms and conditions of employment, by termination and re-engagement, is also classed as a dismissal by reason of redundancy and so has the exact same consultation requirements.
You should have in place a dispute resolution procedure that sets out the appeal process or contractors or the agency as appropriate. You must respond to an appeal within 45 days.
If the status determination is disputed you should consider the contractor or agency’s reasons objections. You must consider if the original determination is to be maintained and give reasons for this. Or a new determination with reasons can be provided if appropriate.
Records of disputed determinations and the outcome of any appeal should be kept.
Yes. You should be able to furlough a suspended employee subject to all other eligibility requirements however we recommend that you take advice on this before doing so.
The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.
For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf
The workplace will not revert to its pre-Covid-19 state overnight, with social distancing in the work place likely to remain in place for quite some time to come.
This could mean that businesses will need to think carefully about how their capacity will be impacted, and how this will affect their ability to perform contractual obligations.
For example, if a business has an outsourcing contract under which it has to perform a business process, or produce a particular output, will it be able to comply with contractual performance standards whilst social distancing is still in place? In the context of a manufacturing business, what will be the impact on production schedules and delivery dates? There might also be an impact on operating costs, for example if processes are changed and additional shifts are introduced – can these additional costs be sustained?
Businesses need to plan a safe system of work for their employees to ensure they comply with Health and Safety legislation, but they also need to consider how this will impact on their ability to perform pre-existing contractual obligations. Ultimately, contractual arrangements with customers might need to remain on a revised footing for a number of months.
Getting to a point where agreement is reached on allocation of additional costs and/or changes to key elements of a contract such as scope of work, performance standards and delivery date will require co-operation between contracting parties. Again, it is important that any variations that are agreed are recorded properly and follow the required contractual procedures.