Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.
Related FAQs
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
The Chief Coroner supports the position, communicated by NHS England and the Chief Medical Officer that Covid-19 is an acceptable direct or underlying cause of death for the purposes of completing the Medical Certificate of Cause of Death (MCCD) and is considered a naturally occurring disease. This cause of death alone is not a reason to refer a death to a coroner under CJA 2009.
If the cause of death is believed to be due to confirmed Covid-19 infection, there is unlikely to be any need for a post mortem to be conducted and the MCCD should be issued, and guidance is given on how this is delivered to the Registrar in the event of the next of kin/informant being in self-isolation.
In a hospital setting the MCCD process should be straightforward because of diagnosis and treatment in life. This may be more complex in a community setting. The Coronavirus Act 2020 however expanded the window for last medical review from 14 to 28 days. Outside of this, the death will need to be reported to the coroner.
Although Covid-19 is a naturally occurring disease, there may be additional factors around the death which mean it should be reported to the coroner; for example, the cause of death is unclear, or where there are other relevant factors. Guidance is given to coroners on how to manage such reported deaths, particularly where post mortem examinations may not be readily availability.
Following our webinars on all aspects of furlough and alternatives to redundancy, it is an unfortunate fact that a number of organisations are likely, sooner or later, to be forced to make some employees redundant.
Our employment experts Jamie Gamble and Roisin Patton take you through the key aspects of conducting cost reduction redundancies, but with a focus on aspects that make this exercise different this time. For instance:
- How are you going to conduct sensitive meetings remotely?
- How are you going to ensure that dismissing any furloughed staff will be fair? You may have furloughed at speed, but redundancy selection criteria cannot be defined by such factors.
- Will you use this time to review your selection criteria if you already have some in place?
- How will you deal with individuals who are shielding, have child care issues or are pregnant?
- How do you ensure this is all done sensitively and fairly for those roles that are being made redundant, but also for those who continue to work for you but are still isolated on furlough or working from home?
- And what are the risks for making redundancies in this “new normal”?
Although you may be perfectly familiar with redundancy exercises these are far from normal times and it is therefore worth pausing to think about the impact that Covid-19 might have and what else you need to think about or plan for.
The webinar was recorded on Thursday 2nd July.
It is absolutely critical to creating a safe workplace and to making workers feel secure.
This could include floor markings every 2m (as we’ve seen in grocery stores), stopping or limiting/staggering access to communal or common areas such as toilets and kitchens, rearranging workstations to maintain a 2 metre distance or, where this is not possible (for example in manufacturing facilities or production lines), erecting physical barriers and avoiding face to face working, encouraging the use of stairs and discouraging lift-use, designing a one-way system for entry and exit and looking at aircon/heating systems to see if any modifications are possible to prevent the spread of airborne particles. If you can increase ventilation in your workplace, it will help reduce risk.
The government has published detailed social distancing guidance for workplaces across sectors including manufacturing, retail, offices, construction and transport; it has also promised to continue to add to this.
It has now changed. Instead of being 3 weeks, it is now technically any period. However, 7 days is the minimum claim period you can now make.