Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.
Related FAQs
During the Covid 19 crisis lawyers and the courts have had to adapt with hearings being heard remotely and with more electronic communication. It is clear that going forward, some of these changes will become more permanent.
The Lord Chancellor, Robert Buckland QC MP, has spoken last week regarding changes to the justice system following the COVID-19 pandemic and we know that there is a significant backlog of work that needs to be processed.
Firstly, 10 sites have been identified for ‘Nightingale courts’ which will allow for better social distancing. The authorities have suggested that it is a possibility that courts will need to stay open for a longer time or at weekends, to increase the number of cases that can be heard safely on any given day. This will enable more cases to be heard in a day and therefore a swifter outcome for your case. The standard of video technology will also continue to improve, with plans for new technology being rolled out across all courts form July onwards. The enhanced use of technology may result in matters being heard more efficiently, decreasing the time spent during each hearing.
HMCTS is working to expand access to audio and video technology to support more and new types of hearings. There has been an increase in the use of new and varying equipment over the lock-down period. With the appropriate systems in place, many more hearings could take place on platforms such as the Cloud Video Platform (CVP). Throughout July, the CVP will be more readily available to Country courts. There will be further hardware rolled out to improve the quality of video hearings, and there will be more efficient methods used to organise video lists.
The increased use and training of CVP means that witnesses and advocates may not need to attend court and could attend the hearing remotely. This will give you increased flexibility, enabling you to attend from your office or home. The CVP is efficient and simple to use, with no complex functions; making it user-friendly. This should make litigation more time and cost effective (albeit that there will be the cultural challenge of having less contact with your legal team or the court experience).
Unfortunately, losses caused by pandemics are not often covered expressly under standard policies, as the risk has been difficult for insurers to price and understand.
Even where additional cover in respect of notifiable diseases has been purchased, it typically will not include Covid-19 within the range of diseases covered by the policy. If the policy includes a list of notifiable diseases, and which does not include Covid-19, it is very unlikely that cover will be available for pandemic-relates losses.
The most common types of covers that could be afforded by insurance policies for coronavirus-related losses and liabilities are traditional business interruption insurance, contingent business interruption insurance, liability insurance, as well as cancellation and abandonment insurance.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
This will be dependent upon the how the leasehold structure is set up for each relevant building, but it may be the local authority. We would be happy to provide further advice in relation to specific buildings if you contact us separately with the relevant details and documents.
In recognition of the problems that the current situation is causing, the UK IPO classed the 24th March and all subsequent days as “interrupted days” which means that deadlines that fall within this period will be extended until the UK IPO declares that the interrupted days have ceased. As lockdown has begun to be eased, the IPO has now reviewed its position and has confirmed that the “interrupted days” period will come to an end on the 29 July 2020. This means that Thursday 30 July 2020 will be the first normal day of operation, therefore all “interrupted days” deadlines will expire on this day. Similarly, if your deadline falls after the period of interruption ends, this deadline will not be automatically extended.
The IPO is conscious that many businesses may still be in challenging positions when the period of “interrupted days” end. They will endeavour to continue to provide flexibility and support to assist businesses with their applications. They hope to temporarily remove fees for requests for extensions of deadlines, and will give further updates when this fee exemption is in place.
The IPO continues to encourage applicants to meet original deadlines where they are able. As their offices are closed, the UK IPO is not currently processing paper forms (i.e. hard copy) and faxes. However, they are processing forms which have been submitted electronically, or via email and have made a new email address available for the submission of forms.
Intellectual Property Offices covering other territories have made their own announcements about the extension of deadlines. The EUIPO’s period of extension of deadlines came to an end on the 18th May. However, they have published a Guidance Note and accompanying webinar on the EUIPO website, detailing options for parties who may struggle to meet deadlines and remedies for those who may have missed deadlines.