Skip to content

Can I be investigated or prosecuted by HSE if one of my workers contracts Covid-19?

The reality of these unprecedented times is that enforcement of health and safety legislation by the HSE (particularly through the criminal courts) in relation to Covid-19 is an extremely unlikely outcome.

Related FAQs

I'm self-isolating and understand that it takes some time to get a Lasting Power of Attorney registered. What can I do in the meantime to enable someone else to operate my bank account and pay my bills?

The Office of the Public Guardian is continuing to accept applications to register Lasting Powers of Attorney but their usual estimated timescale of eight to ten weeks is likely to be affected by the current situation.

Consequently, an alternative or interim measure if you need something quickly is to execute a General Power of Attorney to authorise someone to act as your Attorney to undertake day to day financial transactions for you. The General Power of Appointment only needs to be executed by you in the presence of a witness (not the Attorney) to be valid and does not need to be registered with the Court of Protection. However, the Power of Attorney would cease to have effect if you become incapable of managing your affairs. It should be seen as a stop-gap only.

When will these temporary Right To Work measures end?

The Home Office has not stated when it will end these temporary measures, albeit it has stated that it will provide a warning. Where employers have carried out checks using the temporary measures, the Home Office has confirmed that it will require employers to carry out retrospective checks on any of the following:

  • Employees who started working for you when the temporary measures were in place
  • Employees who required a follow up check during the temporary measures (for example because their previous leave was coming to an end).

It is not explicit from the guidance but these retrospective checks must require you to have in your possession the physical ID in its original form. When carrying out the retrospective check, employers must record this using the following wording “the individual’s contract commenced on [insert date]. The prescribed right to work check was undertaken on [insert date] due to Covid-19.”

These further checks must be made within eight weeks of the temporary measures ending, and employers must keep records of both checks undertaken. Where the employer discovers that the employee does not have the right to work during the retrospective check they should stop employing them.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

What will my case look like going forward and what are the courts doing?

During the Covid 19 crisis lawyers and the courts have had to adapt with hearings being heard remotely and with more electronic communication. It is clear that going forward, some of these changes will become more permanent.

The Lord Chancellor, Robert Buckland QC MP, has spoken last week regarding changes to the justice system following the COVID-19 pandemic and we know that there is a significant backlog of work that needs to be processed.

Firstly, 10 sites have been identified for ‘Nightingale courts’ which will allow for better social distancing. The authorities have suggested that it is a possibility that courts will need to stay open for a longer time or at weekends, to increase the number of cases that can be heard safely on any given day. This will enable more cases to be heard in a day and therefore a swifter outcome for your case. The standard of video technology will also continue to improve, with plans for new technology being rolled out across all courts form July onwards. The enhanced use of technology may result in matters being heard more efficiently, decreasing the time spent during each hearing.

HMCTS is working to expand access to audio and video technology to support more and new types of hearings. There has been an increase in the use of new and varying equipment over the lock-down period. With the appropriate systems in place, many more hearings could take place on platforms such as the Cloud Video Platform (CVP). Throughout July, the CVP will be more readily available to Country courts. There will be further hardware rolled out to improve the quality of video hearings, and there will be more efficient methods used to organise video lists.

The increased use and training of CVP means that witnesses and advocates may not need to attend court and could attend the hearing remotely. This will give you increased flexibility, enabling you to attend from your office or home. The CVP is efficient and simple to use, with no complex functions; making it user-friendly. This should make litigation more time and cost effective (albeit that there will be the cultural challenge of having less contact with your legal team or the court experience).