Can I be investigated or prosecuted by HSE if one of my workers contracts Covid-19?
The reality of these unprecedented times is that enforcement of health and safety legislation by the HSE (particularly through the criminal courts) in relation to Covid-19 is an extremely unlikely outcome.
Related FAQs
All of the measures announced above are aimed at all employers in the UK and are not sector specific. However, over and above these measures the Chancellor also announced a number of financial measures that he hopes will save jobs in the hospitality industry such as the reduction of VAT on food and drink and the “eat out to help out” scheme which has already taken place. The Job Support Scheme is designed to support businesses who face lower demand due to the pandemic, and so is designed to have an impact on those sectors most badly hit.
The Chief Coroner supports the position, communicated by NHS England and the Chief Medical Officer that Covid-19 is an acceptable direct or underlying cause of death for the purposes of completing the Medical Certificate of Cause of Death (MCCD) and is considered a naturally occurring disease. This cause of death alone is not a reason to refer a death to a coroner under CJA 2009.
If the cause of death is believed to be due to confirmed Covid-19 infection, there is unlikely to be any need for a post mortem to be conducted and the MCCD should be issued, and guidance is given on how this is delivered to the Registrar in the event of the next of kin/informant being in self-isolation.
In a hospital setting the MCCD process should be straightforward because of diagnosis and treatment in life. This may be more complex in a community setting. The Coronavirus Act 2020 however expanded the window for last medical review from 14 to 28 days. Outside of this, the death will need to be reported to the coroner.
Although Covid-19 is a naturally occurring disease, there may be additional factors around the death which mean it should be reported to the coroner; for example, the cause of death is unclear, or where there are other relevant factors. Guidance is given to coroners on how to manage such reported deaths, particularly where post mortem examinations may not be readily availability.
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
Yes. Their contracts can be renewed or extended during the furlough period without breaking the terms of the scheme.
If the employee’s contract has not already expired, the contract can be extended or renewed. The employee may be furloughed provided that they were employed on or before 30 October 2020. You must also have made a RTI submission to HMRC between 20 March 2020 and 30 October 2020.
If the employee’s contract expired on or after 23 September 2020, the employee can be re-employed and furloughed. Please note that the employee must have been employed by you on 23 September 2020 and you must have made a RTI submission to HMRC between 20 March 2020 and 30 October 2020.