Skip to content

Can I progress an application for EIA development?

Where a development is considered to be “EIA development” (being development where an Environmental Impact Assessment or Environmental Statement is required to be submitted) there are additional statutory publicity and notice requirements over and above the requirements for a standard planning application. Regulations usually require that the environmental statement is to be made available for inspection by the public at all reasonable hours at an address in the locality for a period of at least 30 days. Copies of the environmental statement are also to be made available for people to take away from that address. This clearly requires physical copies to be available at a specified location for a prolonged period of time, which may prove problematic during the current health crisis.

New regulations came into effect on 14 May 2020 which will temporarily suspend the above requirements and will instead require the Environmental Statement to be available for inspection online. The applicant must however provide a certificate to the Local Planning Authority stating what steps have been undertaken to bring the application (and the Environmental Statement) to the attention of people who are likely to have an interest and why it considers that such steps were reasonable.

Related FAQs

What is Coronavirus Business Interruption Loan Scheme (CBILS)?

The Coronavirus Business Interruption Loan Scheme (“CBILS“) is open for applications to provide small businesses with a loan of up to £5m to assist with the Covid-19 outbreak. The Scheme is aimed at businesses who are experiencing lost or deferred revenues, and who otherwise would be denied support from lenders, to be supported by a Government backed guarantee. The Scheme will initially run for six months with the possibility to be extended where required, so businesses should only approach a lender under the Scheme as and when they require assistance.

What is classed as a good ratio of MHFA to staff numbers?

There is not a magic number. It depends on the nature of the organisation, the work carried out, the organisational structure, the geographical spread, working patterns and conditions. We would give specific advice personalised to the organisation and taking all these and other factors in to consideration. There is no such things as too many MHFAs!

What if the contractor is supplied by an agency?

As mentioned earlier, if an agency is involved you must send them a copy of the status determination statement for each contractor, and they will also have the right to dispute the outcome.

If the agency pays the contractor, they will be responsible for the operation of PAYE and NIC’s deductions and any apprenticeship levy. The agency may try to recover these costs from the end user client.

If workers are supplied by an agency or umbrella company and are already treated as employees by the agency, they will remain unaffected by IR35.

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

How do I reduce employment costs? Are we talking about redundancy?

The obvious option to reduce the cost of your workforce is redundancy. However, that also reduces the number of employees and therefore your capacity.