Can I progress an application for EIA development?
Where a development is considered to be “EIA development” (being development where an Environmental Impact Assessment or Environmental Statement is required to be submitted) there are additional statutory publicity and notice requirements over and above the requirements for a standard planning application. Regulations usually require that the environmental statement is to be made available for inspection by the public at all reasonable hours at an address in the locality for a period of at least 30 days. Copies of the environmental statement are also to be made available for people to take away from that address. This clearly requires physical copies to be available at a specified location for a prolonged period of time, which may prove problematic during the current health crisis.
New regulations came into effect on 14 May 2020 which will temporarily suspend the above requirements and will instead require the Environmental Statement to be available for inspection online. The applicant must however provide a certificate to the Local Planning Authority stating what steps have been undertaken to bring the application (and the Environmental Statement) to the attention of people who are likely to have an interest and why it considers that such steps were reasonable.
Related FAQs
Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.
New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.
For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.
Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.
For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
On 7 May the Government published guidance on how contracting parties can act responsibly in order to assist the effort to deal with Covid-19. The guidance seeks to persuade contracting parties to act reasonably and recognise the impact of Covid-19 on contractual counterparties. This will continue to be relevant as business begins to emerge from lockdown.
Yes, but as a last resort. In summary, the law requires employers:
- to assess the workplace risks posed to new or expectant mothers or their babies;
- to alter the employee’s working conditions or hours of work to avoid any significant risk to them;
- where it is not reasonable to alter working conditions or hours, or would not avoid the risk, to offer suitable alternative work on terms that are not “substantially less favourable”;
- where suitable alternative work is not available, or the employee reasonably refuses it, the employer should consider whether it is appropriate to suspend the employee on full pay.