Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
Related FAQs
Normally, once you have submitted the online visa application and paid the fee, you have to attend an appointment to enrol your biometrics and verify your passport within 45 days. This requirement has been relaxed due to the visa application centres being closed.
Now that application centres have mostly reopened, you must book and attend an appointment to complete the application process. However, the Home Office has recently introduced the IDV app which allows applicants who previously gave their fingerprints as part of a previous application since July 2015, to upload a photo electronically. There will then be no need to attend a Visa Application Centre to submit their biometrics. Applicants who are eligible to use this electronic option will be contacted by UKVI.
- Trusts should allow for telephone advice rather than face-to-face review from critical care when clinically appropriate.
- Hospitals should discuss the sharing of resources and the transfer of patients between units, including units in other hospitals, to ensure the best use of critical care within the NHS.
Please note, the above is intended to provide a summary of the key recommendations which emerge from this guidance. Access to the full guidance can be found here.
The BBC
The national broadcaster’s collated content surrounding the Covid-19 pandemic:
https://www.bbc.co.uk/news/coronavirus
and with regards to business:
https://www.bbc.co.uk/news/business
In appropriate cases, disciplinary action and then dismissal may be fair if an employee refuses to wear a face covering in the workplace. For example, if this is in breach of the government guidance or if employer has issued a reasonable management instruction to this effect due to an identified health and safety risk.
It is important that employers use a fair and reasonable procedure when deciding whether to discipline and/or dismiss an employee and that its actions does not unlawfully discriminate against employees who have legitimate reasons for not wearing masks, such as those individuals who have health conditions like asthma.
- Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
- Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
- Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
- The ability to get people on site to undertake material operations
In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.
If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.