Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

Related FAQs

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

Can apprentices be furloughed?

The government has stated that the scheme will apply to apprentices and that they can continue to train whilst they are furloughed. However you must pay at least the Apprenticeship Minimum Wage, National Living Wage or National Minimum Wage for all periods of training during furlough leave, taking into account the rate increases from 1 April 2020 and the increases which will take effect from 1 April 2021. This means that you will be responsible for any shortfall in the amount claimed under the scheme and the appropriate minimum wage.

We recommend that you get in touch to discuss any queries on furloughing apprentices.

Which properties should I prioritise?

Some organisations are prioritising properties, known to be higher risk, such as properties with open flues, or near to the certificate expiry date.

Vulnerable staff and tenants need protection, safe working practices need to be established, and communicated. Organisations should bring forward servicing for people known to be vulnerable – but bearing in mind the guidance as to preserving the annual test date.

What do we need to do?

Privacy policy – You must make sure the relevant privacy policies deal with how you will process Covid-19 data. You should have an employee privacy policy and this may already deal with health data (if it doesn’t, it should). You might also need to look at privacy policies for customers, visitors and suppliers. This ensures that processing is lawful, fair and transparent.

Lawful processing conditions – You will need to consider which processing conditions you are relying on (remembering that you need both an Article 6 condition and an Article 9 condition – this is the part of the GDPR which deals with special category data). As a lot of the data you collect will be about employees, you can’t use consent so you will have to find another lawful reason under GDPR which allows you to process the data.

Appropriate policy document – When you are considering your Article 9 processing conditions, remember you must also have an “appropriate policy document” in place.

Processing record – Finally make sure your processing record is up to date with information on what data you collect and use.

I have trespassers occupying my land. Can I evict them?

On 18 April 2020, it was announced that an exception to the current stay in possession proceedings and ban on all evictions has been made to allow possession orders to be made against trespassers.

This means land owners can take action to remove unauthorised persons occupying their land. Trespassers include: squatters; travellers; failed successors of secure tenancies; and licensees whose licences have been terminated.

Further, the automatic stay to possession proceedings currently imposed no longer applies to applications for interim possession orders meaning any persons found to be “squatting” on land without permission may again be subject to an order requiring them to leave your premises within 24 hours of service of that order.