Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

Related FAQs

Do I need to treat everyone the same and bring them all back at the same time?

No. You should always treat employees consistently and fairly, but this doesn’t mean treating them all the same, or applying the same requirements. For those employees who have been homeworking and doing so without any problems, then they should be allowed to continue to do so.

We would anticipate that the vast majority, if not all, businesses will be approaching the return on a phased basis, which inevitably means some employees returning to work sooner than others. In reality then, you aren’t treating everyone the same, but try to be fair and consistent; you need to do what works best from a business perspective, but can you rotate people, require them to come in at different times etc. Where people perceive that the planned return is being worked out fairly they are far more likely to buy into this, which will help avoid resentments building up between colleagues.

Who do the Procurement Policy Notes (PPN) apply to?

All three of the PPNs are effective immediately and apply to the following Contracting Authorities:

  • Central Government Departments
  • Executive agencies
  • Non-departmental public bodies
  • Local authorities
  • NHS bodies
  • The wider public sector

In regards to PPN03/20, those in scope organisations that do not currently use procurement cards are advised to immediately put in place arrangements using the relevant Crown Commercial Service Agreement (Lot 2 of RM3828 Payment Solutions).

How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

My business has a contract with a public sector body – what guidance has the Government issued about payment under contracts between public and private sector bodies?

The Cabinet Office has published a helpful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). This can include making advance payments to suppliers, if necessary. The PPN sets out actions that public sector bodies should take (until at least 30 June 2020) to ensure continuity of service and to ensure that its suppliers can resume normal contract activity once able to.

The actions public sector bodies should be taking include:

  • Informing its suppliers (that they believe are at risk) that they will continue to be paid as normal until the end of June 2020 (even if service delivery is currently interrupted). Risk might include supply chains collapsing and/or significant financial implications for a supplier
  • If a contract involves a payment by results mechanism, basing payments on previous months (e.g. the average monthly payment over the previous 3 months), and
  • Ensuring that invoices submitted by suppliers are paid immediately to maintain cash flow in the supply chain and help to protect jobs.

If you are a supplier to a public sector body, you must act transparently and on an open-book basis, making cost data available to your public sector clients. You must also continue to pay your employees and subcontractors / suppliers. Suppliers to the public sector must not expect to make profits on any undelivered elements of a contract. The PPN makes clear that, should suppliers be found to be taking undue advantage, or failing to act transparently, a public sector body can take action to recover payments made to that supplier.

The PPN requires public sector bodies to urgently review their contract portfolios and take steps to support suppliers who they believe are “at risk”. However, no definition of “at risk” is given in the document.  We would suggest that if you are a supplier and you have yet to hear from a public sector client, you should seek to get in touch with them as soon as possible, particularly if you have concerns about your supply chain, staff retention and/or are experiencing financial difficulties currently. Given the requirement for transparency, you may be required to provide evidence, so it may be helpful to have any relevant documentation ready to send, if necessary, as this may help ensure a decision is made by the public sector client more promptly, particularly as the public sector body may have a number of contracts to consider.

 

Do you think MHFA will become a legal requirement for businesses eventually?

This is something which is certainly on the Government’s radar as there is currently a Bill being heard in Parliament about making MHFAs a legal requirement for workplaces. It is still in the very early stages and therefore it is not clear at this stage what the outcome will be. What is clear is that this is an area which is being taken very seriously and it would not be surprising if measures were put in place regarding MHFAs in the workplace.