Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
Related FAQs
There are four criteria which must be satisfied if an agreement is to be considered exempt:
- It must improve production or distribution, or promoting technical or economic progress – the guidance suggests that cooperation ensuring essential goods and services can be made available to the public, or an important sub-set of the public such as key workers, will satisfy this criterion.
- It must allow consumers a fair share of the resulting benefit – the guidance suggests this will be the case where the action prevents or reduces shortages.
- It must not impose on the undertakings concerned restrictions which are not indispensable to the attainment of the above benefits – the guidance suggests this will be the case where the cooperation is the only reasonable option due to the urgency of the crisis and where the cooperation is temporary in nature.
- It must not afford the undertakings concerned the possibility of eliminating competition – therefore the parties must endeavour to retain competition in respect of the products (in particular price competition).
Hosted by Advanced Manufacturing Forum, Partner, Matt Cormack discussed in this webinar how to avoid risks associated with your customer and supply chain contracts during this challenging Covid-19 period.
The webinar covers common questions such as:
- Can force majeure excuse me or my suppliers from paying on time?
- What are the risks to my business if I can’t perform on time due to Covid-19?
- What will happen to my contracts if the Government takes steps to require me to close down my facility?
To watch the full recording, please click here. (To note the recording begins at 10 minutes)
If you have any follow up questions, please do not hesitate to contact one of our lawyers detailed below or use our ‘ask us a question‘ feature.
Under their obligations arising from Regulation 36 of the Gas Safety (Installation and Use) Regulations 1998, landlords must service domestic gas appliances on an annual basis and provide tenants with a record of the service within 28 days of that service. Failure to comply can result in prosecution by the Health and Safety Executive (HSE) or downgrading by the Regulator.
We know how important this is. But how can you comply with your obligations during the Covid-19 epidemic?
The latest restrictions on leaving the home, currently allow registered gas engineers to undertake essential work, whilst taking the appropriate precautions advised to avoid spreading or contracting the virus in a new setting.
- Keep in touch. If contact is poor, workers can feel disconnected, isolated or abandoned. This can adversely affect stress levels and mental health – especially in the current crisis when everyone is feeling more anxious.
- Think about the use of laptops/devices (DSE) at home. Provide a basic form of risk assessment for self-completion.
- Remind workers of simple steps to reduce the risks from display screen work:
- take regular breaks (at least 5 minutes every hour) or change activity
- avoid awkward, static postures by regularly changing position
- get up and move or do stretching exercises
- avoid eye fatigue by changing focus or blinking from time to time
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements