Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
Related FAQs
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
It has now changed. Instead of being 3 weeks, it is now technically any period. However, 7 days is the minimum claim period you can now make.
The amount an insurer charges for providing cover is a critical aspect of the underwriting process. The premium must be sufficient to cover expected claims but must also take into account the possibility that the insurer will have to access its capital reserve –it is risk assessment based and the greater the risk, the higher the premium. Historically, insurers of high-rise buildings would have only had to prepare for a loss caused by damage to just a few flats within a building. That is because the design and construction of that building, with the right materials and fire safety provisions in place, should have limited the spread of fire and allowed the damage to be contained –or at least make this an extremely low risk. Now we know that many buildings have been designed, built and signed off in a regulatory system that an independent Government review has found was not fit for purpose. Premiums will reduce overtime but will be dependent upon the perceived level of risk reducing as the regulatory regime, BSA and BSR become more established.
You will need to check the terms of the contract you have with the debtor to make sure you are still entitled to be paid (including checking any force majeure clause).
It is also important to remember that the current exceptional circumstances might also affect your contractual rights in other ways too – please see our commercial & contracts site for more information.
Depending on the type of debt you are owed, there might be some additional restrictions in place that you will need to consider. For example there are certain restrictions on landlords being able to forfeit leases, evict tenants or send High Court Enforcement Officers to collect outstanding rent.
Assuming there are no sector-specific restrictions in place then you should be able to start county or high court proceedings to recover the debt.
As an alternative to starting court proceedings, if the debt is undisputed a creditor can usually opt to issue winding up proceedings against a debtor instead. However, the recently introduced Corporate Insolvency and Governance Act introduces a temporary suspension on the ability of creditors to present winding up petitions to recover money unless the reason why the debtor cannot pay is not related to covid-19. For more information click here.
Often taking firm action is the right thing to do, particularly given that it is a sad reality that it is the creditor who shouts the loudest that will often get paid first. However, one important consideration is the commercial reality that many businesses (and indeed individuals) now find themselves in.
Whether taking legal action is likely to result in payment is always a question any creditor should ask themselves. Some creditors might also want to try to support their customers during these difficult times and/or have concerns about their long term reputation if they pursue the debt too aggressively. However, even if that is the case it is still possible to engage constructively and positively with those who owe you money to try to reach the best possible outcome. This could include:
- Having clear and consistent credit control processes in place
- Obtaining statements of means to help understand what a debtor can afford to pay
- Agreeing realistic payment plans
- Negotiating formal payment holidays
- Putting in place voluntary security to secure the debt
- Identifying those debtors who can’t pay as opposed to won’t pay and targeting resources accordingly
- Looking at what other options might be available, including recovering under parent company guarantees
Many policies will only provide business interruption cover if it arises from property damage. The FCA has acknowledged that insurers are entitled to reject claims in relation to such policies, notwithstanding the success of the FCA’s test case in the Supreme Court, and which was generally favourable to policyholders [Insert a link here to our update on the test case]. In other cases the policy wording will be less clear and businesses may legitimately feel that their insurer is wrongly withholding payment.
One route of challenge to an insurer’s decision is via one of the well-publicised class actions. Another route of challenge is by a complaint to the Financial Ombudsman Service (FOS). This service is open to consumers and small and medium-sized businesses, ‘micro-enterprises’, charities and trusts. The service will be an attractive option for many businesses, as it is free and relatively quick (although it remains to be seen how the service keeps up with an increase in demand as a result of the pandemic). You will need to have complained to your insurer before bringing a complaint with the FOS.
Further details can be found here.