Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
Related FAQs
Employers will be collecting and sharing health information. Health information is sensitive and higher data protection standards apply. Here are a few key pointers.
- Update privacy notices to cover the new collection and sharing of employees’ information and provide these to the workforce. Be transparent and fair.
- Identify the legal basis and condition for use of this information and put any required paperwork in place. The ICO guidance will help. For some conditions such as the employment condition, an Appropriate Policy Document (APD) will be required. The ICO has an APD template.
- Only use the information for the purpose of managing the workforce during the pandemic.
- Only collect or share information if it’s necessary – if it’s a targeted and proportionate way of achieving your purpose.
- Make sure any health information collected and shared is accurate – there may be serious consequences if it’s not.
- Work out how long the information must be kept for. Keep a record of that period and act on it at the appropriate time.
- Security is very important – there may be malicious actors trying to trick employers and employees. Make sure employees know how to identify a genuine NHS Test and Trace contact. Keep the information secure. Use the ICO’s data sharing checklists** and keep a record of the disclosures made and why. Control external disclosures – only certain authorised members of staff should make them.
- Make sure individuals can still exercise their data protection rights – that’s also very important. Keep data protection records up-to-date and ensure any exports of personal information outside the UK are compliant.
- Before introducing employer-led testing like taking temperatures, thermal imaging or other potentially intrusive tests, work out if a data protection impact assessment (DPIA) is required. It will be if the intended processing is ‘high risk’. If it is, then carry out a full DPIA. It will help address the issues systematically and mitigate risks.
- All this demonstrates ‘accountability’ – it shows affected individuals and the ICO that the employer is complying with data protection requirements.
If you need further help, please visit the ICO’s data protection and coronavirus information hub or ask our data protection team.
** Please note that this link is to the ICO’s existing checklists and data sharing code of practice. We will update the link to the ICO’s new checklists after they are published.
Hosted by Advanced Manufacturing Forum, Partner, Matt Cormack discussed in this webinar how to avoid risks associated with your customer and supply chain contracts during this challenging Covid-19 period.
The webinar covers common questions such as:
- Can force majeure excuse me or my suppliers from paying on time?
- What are the risks to my business if I can’t perform on time due to Covid-19?
- What will happen to my contracts if the Government takes steps to require me to close down my facility?
To watch the full recording, please click here. (To note the recording begins at 10 minutes)
If you have any follow up questions, please do not hesitate to contact one of our lawyers detailed below or use our ‘ask us a question‘ feature.
Similar to the position for claims between 1 August 2020 and 31 October 2020, for claims between 1 July 2021 and 30 September 2021 there will be a cost to businesses of furloughing staff, which will gradually increase until the scheme closes at the end of September as follows.
- From 1 July 2021 employers will be required to contribute 10% of wages, with the Government contributing 70%.
- From 1 August 2021, the employer contribution increases to 20% and the Government will contribute 60%.
- 30 September 2021: scheme closes.
Employees will continue to receive 80% of their current wages, up to £2,500 a month.
Initially, the relaxation applied to supermarkets and food suppliers. This was subsequently widened to apply to other businesses, permitting them to collaborate where necessary to respond to the crisis in the interests of consumers.
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.