Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
Related FAQs
No. You should always treat employees consistently and fairly, but this doesn’t mean treating them all the same, or applying the same requirements. For those employees who have been homeworking and doing so without any problems, then they should be allowed to continue to do so.
We would anticipate that the vast majority, if not all, businesses will be approaching the return on a phased basis, which inevitably means some employees returning to work sooner than others. In reality then, you aren’t treating everyone the same, but try to be fair and consistent; you need to do what works best from a business perspective, but can you rotate people, require them to come in at different times etc. Where people perceive that the planned return is being worked out fairly they are far more likely to buy into this, which will help avoid resentments building up between colleagues.
Yes. You can continue to fully furlough employees until 30 September 2021 (but from between 1 August 2020 and 31 December 2020 and from 1 July 2021 you need to contribute to the cost). If on full-time furlough, employees continue not to be able to undertake any work for you. As before, they can undertake training, or volunteer or work for another employer or organisation (if contractually allowed).
The amount an insurer charges for providing cover is a critical aspect of the underwriting process. The premium must be sufficient to cover expected claims but must also take into account the possibility that the insurer will have to access its capital reserve –it is risk assessment based and the greater the risk, the higher the premium. Historically, insurers of high-rise buildings would have only had to prepare for a loss caused by damage to just a few flats within a building. That is because the design and construction of that building, with the right materials and fire safety provisions in place, should have limited the spread of fire and allowed the damage to be contained –or at least make this an extremely low risk. Now we know that many buildings have been designed, built and signed off in a regulatory system that an independent Government review has found was not fit for purpose. Premiums will reduce overtime but will be dependent upon the perceived level of risk reducing as the regulatory regime, BSA and BSR become more established.
Due to the new guidance on social distancing and remote working, the Planning Inspectorate initially stated that site visits, hearings and inquiries would be cancelled. However, there is very much a push from the Secretary of State to keep the planning system moving notwithstanding the requirements to adapt to new ways of working. The Government now expects all hearings to be conducted virtually and where a virtual hearing is not possible, the expectation is that alternative arrangements will be put “speedily” in place and in accordance with social distancing requirements.
The Planning Inspectorate have been exploring ways of conducting hearings and inquiries remotely using technological means and conducted their first “digital” hearing on 11 May .
The Business and Planning Act 2020, which entered the statute books on 22 July 2020, includes provisions which allow more flexibility in relation to how appeals are determined including an ability for the Secretary of State to decide to adopt a procedure which is a combination of written representations, a hearing and/or an inquiry.
Site visits have re-commenced where it is safe to do so. The Inspectorate is looking at whether a site visit is necessary and has conducted a trial of “virtual site visits” where sites are assessed by means of photographs or video evidence.
The Planning Inspectorate have subsequently been scaling up conducting digital hearings, which also includes holding virtual local plan examination hearings.
No. No action need be taken in relation to the demand but we would advise against presentation of a petition based upon any Statutory Demand issued between 1 March 2020 and the end of the restrictions. As you may be aware, with Winding Up there is no requirement to issue a Statutory Demand notice before proceeding so this is unlikely to create too many issues – click here to see whether you should issue petitions on other grounds.
There is nothing to prevent statutory demands being served at this time. However, there may be limited benefit as it cannot form the basis of a future winding up petition.