Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

Related FAQs

Does a sponsor need to report a change in workplace if a Tier 2 visa holder is working from home as a result of Covid-19?

No. The Home Office has confirmed that sponsors do not need to report sponsored workers as working from home, where this is directly related to the coronavirus outbreak.

However any UK employers who sponsor overseas workers, should also ensure that they remain compliant with their other sponsor licence duties, which includes reporting any change to an employee’s salary and duties.

Can we require employees to have their temperatures taken on the way in to work, and is this something we should be doing?

If such testing is regarded as a “reasonably practicable step” which has been identified as an appropriate control following a risk assessment then it is something you can do.

Although you can’t physically force someone to have something intrusive done, this is very likely to be a reasonable management instruction and therefore if someone refuses to have this done as a condition of entry into the work place then disciplinary action may follow.

Where this is something that is required of employees, employers should be letting their staff know that this is one of a number of measures that are being introduced into the workplace for their own safety. If the employer can explain, in advance of the return, why temperature checks need to be taken, what the consequences of the results will be- i.e. will they be sent home if over a certain temperature, whether this data will be stored (and if the sole purpose is to determine whether or not they are fit to attend work on a particular day then why are they being stored), and the fact that temperature checks are a requirement of entry to company premises for everyone, then there shouldn’t be significant resistance to this measure.

Large scale temperature checks have in some businesses become part of the “new normal” working environment.

I’m getting married but have had to postpone the wedding. Should I delay putting a prenuptial agreement in place until a later date?

No. The greater the gap between the completion of a Prenuptial Agreement and the Wedding the more likely it will be upheld by the Court. If such an Agreement is made shortly before the wedding takes place one of the parties to it could claim that they felt under pressure to sign and the Court may decline to follow it.

What if you want to terminate the contract completely?

If changed circumstances mean that a business wants to exit from a contractual arrangement, then before trying to terminate it, a careful review should be carried out to see whether a right to terminate actually exists. For example:

  • Not every contract for the sale of goods contains the right for the buyer to terminate in circumstances where the supplier hasn’t done anything wrong. If a business has entered into a contract on the supplier’s standard terms, it is unlikely to contain any such provision
  • A contract for the provision of services is unlikely, if drafted by the customer, to contain a provision that allows the supplier to walk away from the arrangement at short notice, or perhaps at all

If a party tries to terminate a contract when it doesn’t have the right to do so, the other party will likely claim breach of contract and could sue for damages. In the case of a long term or high-value contract, this could amount to a very significant liability.

Even if the right to terminate the contract does exist, there might be particular rules about the following:

  • How much notice has to be given
  • How such notice has to be served (for example, it might have to be in writing to a particular address)
  • When the notice can be served (perhaps on an anniversary of the start of the contract)
  • How much a party has to pay if it cancels (for example, for raw materials, for work done to date, or even the whole contract price)

All of these factors must be taken into account, and any contractual processes for termination are followed.

Can I argue that my contract has been frustrated?

It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.

If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.

It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.

Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.

Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.