Can I require my staff to inform me should their circumstances be such that they need to self-isolate?
Yes.
Workers (and agency workers) who are aware of the requirement to self-isolate and are due to work during their isolation period at a place other than their designated place (see below) must, as soon as reasonably practicable and in any event before they are next due to start work within the isolation period, tell their employer that they are self-isolating, and set out the start and end dates of their isolation period.
Clear communication to all workers about their obligation to do this is strongly recommended.
Related FAQs
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
If you are eligible you will get a taxable grant of 80% of the average profits from the following tax years (where applicable):
2016-2017
2017-2018
2018-2019
HMRC will add the total profit in each of the three tax years (if applicable). This will then determine the monthly payment, subject to the cap of £2500.
There are two stages:
- Stage 1 – The provision of written information to the representatives.
- Stage 2 – Consultation on the proposed redundancies “with a view to reaching agreement” about certain matters
Stage 1: Provision of information
The first stage in the collective consultation process is to provide the representatives with written information including details of the proposed redundancies (often called a section 188 letter). This information must be given to the appropriate representatives and the time limit before dismissals can take effect does not start to run until they have received it. It is this information which ‘starts the clock’.
It is possible that there will be changes to the proposals during the consultation process: indeed that is part of the reason for the process. The employer’s obligation is not just to provide the appropriate representatives with the relevant information at the start of the process. It is under a continuing obligation to provide them with information in writing about any developments during the consultation process (although later changes do not ‘restart the clock’ before dismissals can take effect).
Stage 2: Consultation on the proposed redundancies “with a view to reaching agreement” about certain matters
The consultation process must include consultation “with a view to reaching agreement with the appropriate representatives” on ways of:
- Avoiding the dismissals
- Reducing the number of employees to be dismissed
- Mitigating the consequences of the dismissals
It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved. To be in the best possible position, it is worth considering the following at the outset of any project:
- Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
- Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
- Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
- Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
- Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
- Project bank accounts and escrow accounts can also provide some further assurances for the parties involved
On 2 April 2020, the Government issued guidance relating to Private Finance Initiatives and PF2 Projects. The guidance, which is to be enforced with immediate effect (currently due to stay in place until 30 June 2020), is one of several guidance notes issued to date.
A link to the guidance is set out below:
Key messages to contracting authorities
- PFI contractors should very much consider themselves as being part of the public sector response to the current pandemic
- Covid-19 is not regarded as, and is not to be classified as a force majeure event
- PFI contractors must ensure that contingency plans are up to date and have been reviewed and discussed with contracting authorities to enable the continuity of full services to respond to the pandemic and maintain vital public services
- Contracting authorities should work closely with PFI contractors to use all available options to maintain public services during the emergency period
- Local arrangements should be made where PFI contractors can’t deliver the agreed requirements and performance standards
- “Best efforts” should be made by all parties for the continuation of service provision