Skip to content

Can I still progress with stopping up applications?

We are working with many of our clients to progress with stopping up applications in order to divert/stop up highways and public rights of way affecting development sites. Due to lockdown restrictions the Department for Transport stalled the progress of applications because they were unable to comply with the statutory publicity requirements. We have very recently been contacted by the Department for Transport casework team who have confirmed that the stopping up/diversion applications can now be progressed. We are aware that Councils across the country are also now progressing with applications. Please contact us if you require any advice/assistance in respect of your application.

Related FAQs

What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

What if we are a charity in Scotland Wales or Northern Ireland?

Because they all have devolved governments, when there are changes to spending levels in England, the Government makes adjustments to the amount of public expenditure allotted to Scotland, Wales and Northern Ireland.  In this case £60 million will be made available for all of the devolved administrations as a result of the £370 million funding allocated to charities in England. This is broken down as follows:

  • £30 million for the Scottish Government
  • £20 million for Welsh Government
  • £10 million for the Northern Ireland Executive

There may be further allocations, dependent on the final projects funded, through the £360 million direct grant pot.

What will be the impact of the proposals on suppliers?

The change in the law has the potential to place much greater financial risks on suppliers, making it more difficult to exit a contract with a customer of doubtful solvency.  This will place increased emphasis on appropriate financial due diligence and credit checking before entering into supply contracts.

In addition to the obvious issues around financial risk, suppliers will also need to think carefully about how their contracts are drafted.  For example, any form of right that is drafted so as to be triggered on customer insolvency will clearly be problematic.  These could include:

  • Retention of Title provisions, which are commonly drafted so that the right to enter premises and retake possession of the goods is triggered on insolvency;
  • Provisions for brand protection, which seek to control how goods are dealt with on termination of the contract.

This is potentially a very significant development for many businesses.  We would strongly recommend specialist advice be obtained so that:

  • businesses understand the potential increased risks faced; and
  • where possible, contracts are updated so that appropriate protections are maintained.
Can colleagues meet outside of work during the national lockdown?

Yes, but only for work purposes and where it is unreasonable to do so from home. Work colleagues cannot meet to socialise.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements