Can I still progress with stopping up applications?
We are working with many of our clients to progress with stopping up applications in order to divert/stop up highways and public rights of way affecting development sites. Due to lockdown restrictions the Department for Transport stalled the progress of applications because they were unable to comply with the statutory publicity requirements. We have very recently been contacted by the Department for Transport casework team who have confirmed that the stopping up/diversion applications can now be progressed. We are aware that Councils across the country are also now progressing with applications. Please contact us if you require any advice/assistance in respect of your application.
Related FAQs
Workers who have not taken 20 days holiday entitlement due to Covid-19 can now carry it over into the next 2 leave years. It only applies where it was not reasonably practicable for a worker to take their annual leave due to the coronavirus.
Interestingly, there is currently no ‘single’ technology to be used by the judiciary within the protocol. The court and parties must choose from a selection of possible IT platforms or audio/telephone hearing (further details available in the guidance e.g. Skype for Business, Microsoft Teams, Zoom etc.) The particular platform must be agreed at the outset of each case and then specified in the case management order. The guidance issued also sets out the basic principles which apply when conducting remote hearings.
Head of Commercial, Colin Hewitt, speaks with the team at NewcastleGateshead Initiative about the complexities of event cancellations and the associated legal implications.
Click here to listen to the full podcast.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
Where an apprentice is made redundant the training provider should support the apprentice in seeking alternative employment within a 12 week period. ESFA will support this process. Where an apprentice is placed on unpaid leave or the nature of their employment no longer supports their apprenticeship, it should be considered whether a break in learning would be appropriate.
An employer who wishes to make an apprentice redundant should seek advice on the process to be followed for this.