Skip to content

Can I switch an existing loan facility onto the CBILS scheme?

If a business has been provided with a loan from 23 March on commercial terms, providing the borrower meets the CBILS eligibility criteria, lenders have been asked to bring these facilities onto CBILS wherever possible (e.g. where the lender is accredited to offer the same facility through CBILS) and changes retrospectively applied as necessary. Please contact us if this applies to you and we can review facilities and advise upon the potential changes that may be made retrospectively to the benefit of the business.

Related FAQs

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

Were any measures sector specific?

All of the measures announced above are aimed at all employers in the UK and are not sector specific. However, over and above these measures the Chancellor also announced a number of financial measures that he hopes will save jobs in the hospitality industry such as the reduction of VAT on food and drink and the “eat out to help out” scheme which has already taken place. The Job Support Scheme is designed to support businesses who face lower demand due to the pandemic, and so is designed to have an impact on those sectors most badly hit.

Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?

The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.

The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.

The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:

  • Amending the contract requirements
  • Varying timings of deliveries
  • Relaxing KPIs or service levels
  • Extending time for performance (e.g. revising a contract delivery plan), and/or
  • Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).

These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.

A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.

If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.

 

 

What should be included in genuinely self-employed contractor terms?

If you consider the factors used to determine status you can include the following terms that are more in line with a self-employed relationship:

  • The right to provide a substitute of the contractor’s choice in the event the individual is not able to perform the services;
  • The ability to work for other businesses as long as doing so will not affect the services to be provided by the contractor;
  • The contractor should have sufficient control over how, when and where (if possible) they provide the services;
  • A degree of financial risk can be included for unsatisfactory work or failing to complete a project or task

We have terms that cover all of these points that can be tailored to your needs. The consultancy agreement is included in our IR35 toolkit.

Do I need Planning Permission to change the use of a warehouse or factory unit to a temporary mortuary?

Mortuaries are a sui generis use, unless ancillary to some other use of land, a hospital for example.

Sui generis uses are not within any Use Class. Consequently planning permission is required for the:

  • Change in the use to a sui generis use
  • Subsequently for the change in the use to an alternative use, whether that be another sui generis use or a use within a Use Class

Acknowledging the above, if the scale of the use is above de minimis, planning permission is likely to be required to change the use of a warehouse or factory unit into a temporary mortuary.

Should planning control be breached, a local planning authority must decide whether to take enforcement action or not. That enforcement is discretionary was recently reiterated in a Ministerial Statement issued on 13 March 2020 a link to which is below.

https://www.parliament.uk/business/publications/written-questions-answers-statements/written-statement/Commons/2020-03-13/HCWS159/

Depending on the form of the enforcement action, there could be a right of appeal.