Skip to content

Can we require employees who have been shielding to return to work at the end of the 12 week shielding period?

The Government introduced shielding in the peak of the pandemic. Current advice is that shielding is not required. However, those who have been shielding are likely to be the most vulnerable and will likely be nervous about a return to work. They may also be disabled under the Equality Act 2010. You should therefore consider any concerns that are expressed and take action to mitigate any risks. For example, it may be possible to keep these employees on furlough until the scheme runs out or they may be able to work from home. If you would like to discuss any specific scenarios then please contact one of the team.

Related FAQs

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

What should I do if my apprentice is due to finish their fixed-term contract during the pandemic?

Employers who have apprentices on fixed-term contracts due to end during the pandemic should discuss arrangements with the apprentices including whether an extension to the contract can be offered to allow them to complete their apprenticeship.

What routes of challenge are available to an insurer's rejection of my business interruption claim?

Many policies will only provide business interruption cover if it arises from property damage. The FCA has acknowledged that insurers are entitled to reject claims in relation to such policies, notwithstanding the success of the FCA’s test case in the Supreme Court, and which was generally favourable to policyholders [Insert a link here to our update on the test case]. In other cases the policy wording will be less clear and businesses may legitimately feel that their insurer is wrongly withholding payment.

One route of challenge to an insurer’s decision is via one of the well-publicised class actions. Another route of challenge is by a complaint to the Financial Ombudsman Service (FOS). This service is open to consumers and small and medium-sized businesses, ‘micro-enterprises’, charities and trusts. The service will be an attractive option for many businesses, as it is free and relatively quick (although it remains to be seen how the service keeps up with an increase in demand as a result of the pandemic). You will need to have complained to your insurer before bringing a complaint with the FOS.

Further details can be found here.

Are Public Bodies able to continue to pay contractors (and their supply chains) at risk as a result of Covid-19?

Yes: The Cabinet Office has published a number of Procurement Policy Notes to provide instructions to Public Bodies to enable payments to continue to be made to at risk suppliers (and their supply chains) who have been affected by Covid-19. Copies of this guidance can be obtained from the Government website at: https://www.gov.uk/government/publications/procurement-policy-note-0220-supplier-relief-due-to-covid-19