Court proceedings have been issued. What happens to the court timetable?
The parties to litigation should still take the steps they have been ordered to take and comply with any Orders made by the court. If for any reason it looks as if a direction cannot be complied with because of the Covid-19 virus then an extension of time can be agreed with the other party (up to 28 days) or through the court. We are aware that Orders have been made extending the time for certain steps to be taken by 56 days.
Related FAQs
Hopefully, further guidance will provide additional clarification on this, but it is difficult to see how a charity whose operations have been significantly curtailed because of the Covid-19 restrictions, cannot furlough employees and access the scheme, in particular where they have several different income streams. For example if a charity’s retail or fundraising operations have been significantly curtailed due to the restrictions, then it would appear unfair for it not to able to rely on the furlough scheme to assist in the funding of the employment costs associated with this part of the charity.
However, it might be prudent, where there are services that are publicly funded and employees working within those services cannot undertake their normal work, to consider if they can do different roles to work on Covid-19 activities. If there is no such work available then the guidance does appear to allow the furloughing of employees and such organisations to access the scheme.
In our experience, the funding streams and work undertaken by the organisations that could fall into the third category identified above can be exceptionally diverse and we would strongly recommend that you take advice before making such decisions about furloughing employees.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
CMA guidance suggests that it will not take enforcement action in respect of agreements which:
- Are appropriate and necessary to avoid a shortage, or ensure security, of supply
- Are clearly in the public interest
- Contribute to the benefit or wellbeing of consumers
- Deal with critical issues that arise as a result of the Covid-19 pandemic
- Last no longer than is necessary to deal with these critical issues
Although there is no formal selection process that must be followed in order to furlough staff, the basis for selecting who will be furloughed should be explained to all relevant staff. Basing this on work levels, required skills or whether work can in fact be carried out efficiently from home will help this process. Staff can be invited to volunteer to be furloughed or re-furloughed. Any requests can be considered on a case by case basis. It may be that a particular skill set is required which may result in an employee’s request being refused.
Residents will be obliged to:
- Not act in a way that creates a significant risk of a building safety risk materialising
- Not interfere with building safety equipment in the common parts
- Comply with an Accountable Person’s request for information in relation to the assessment and management of building safety risks.
The Accountable Person then has powers in relation to these duties, including:
- Issuing a contravention notice, requiring a resident to pay for replacement or repair of safety equipment which they have interfered with
- Applying for court orders in certain situations
- Requesting access at a reasonable time (in writing with at least 48 hours’ notice) to a resident’s property for the purposes of assessing or managing building safety risks, or checking compliance with the resident’s duties as above.
Secondary legislation is still awaited to bring these provisions into force, so the timing is unknown, but it will likely be within the next 12 months in line with the anticipated timetable for the remainder of the Act.