Skip to content

Court proceedings haven’t yet been issued – what should I do?

Parties still need to comply with the various Protocols that apply and will be expected to exchange information in the usual way. Court proceedings can be issued electronically.

Related FAQs

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Can we rely upon the 'reasonable grounds' point to proceed with a petition?

If the debts owed to you pre-date Covid-19 and your debtor seemed unable to pay well before the Covid-19 pandemic took place, it is entirely possible that you will be able to present a petition on the grounds that the debtor would have been unable to pay its debts even if the Covid-19 had no effect on its financial position. We do not yet have any reliable precedent as to how the Courts are likely to deal with such cases.  Whether you are likely to succeed will depend on the exact circumstances of the debt and your debtor. There has been one case decided in August 2020 where the Court concluded that Covid-19 did not have a financial effect upon the debtor and that the circumstances which gave rise to the petition had arisen long before Covid and would have occurred in any event.  A winding up order was made in that case.  What we do know about the court’s approach is that the purpose of the Act is to allow viable companies to trade through the current times and the Court is likely to set the bar high.

Please contact us if there a debt you would like to discuss. Even if presenting a winding up petition is not available for now, there may still be other forms of legal proceedings that you can use to collect money owed to you, like county court proceedings.

How do I implement temporary contractual arrangements?

The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.

With time and resource precious commodities, focus should be given to documenting:

  • The key changes to your PFI requirements
  • The temporary nature of the measures
  • The requirement for best efforts on behalf of the PFI Contractor
  • The importance of continued health and safety measures at all times
Do you have to collectively consult for the minimum period of time before you can issue notice?

These periods are often mistakenly referred to as minimum lengths of consultation (especially by Trade Unions). That is not correct. Consultation can commence, conclude and notices of dismissal be issued within the 30 and 45 day periods. The expiry of the notice would just have to be outside of those restricted periods.

How much will I get under the scheme?

If you are eligible you will get a taxable grant of 80% of the average profits from the following tax years (where applicable):

2016-2017

2017-2018

2018-2019

HMRC will add the total profit in each of the three tax years (if applicable). This will then determine the monthly payment, subject to the cap of £2500.