Skip to content

Do I need to give a personal guarantee to access finance under the Coronavirus Business Interruption Loan Scheme (CBILS)?

A number of our clients and networks raised issues in the early stages of the Scheme around the requirement for personal guarantees to access finance under the Scheme. The Scheme has now been updated so that:

  • For facilities under £250,000, personal guarantees cannot be taken to support lending under the Scheme.
  • For facilities above £250,000, personal guarantees may still be required by a lender but the amount which can be recovered under these guarantees is capped at a maximum of 20% of the outstanding balance of the CBILS facility after taking into account any other recoveries from business assets.

Related FAQs

What are the rules?

State aid rules are contained in the Treaty on the Functioning of the European Union (previously referred to as the Treaty of Rome). The State aid rules prohibit the use of state resources, or any public support with an economic value, which given selectively has the capacity to distort trade by favouring certain undertakings, or the production of certain goods, and which has the potential to affect trade between Member States. Where aid is present it must not be granted unless it has been specifically approved in advance by the European Commission or benefits from a general exemption to the rules.

In general, the rules apply to all State actions which might assist businesses including:

  • Grants
  • “Soft” loans
  • Selling to business at an undervalue
  • Buying from business at an overvalue
Are permitted development rights now in existence for the creation of emergency medical facilities?

Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:

  • Preventing an emergency
  • Reducing, controlling or mitigating the effects of an emergency
  • Taking other action in connection with an emergency

It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.

The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.

Further detail of the permitted development right is available at the link below.

http://www.legislation.gov.uk/uksi/2020/412/made

ONLINE EVENT: Contracts, managing supply chain issues and the role of directors

Hosted by NewcastleGateshead Initiative, Partners Damien Charlton and Jane Garvin discussed in this webinar contracts, managing supply chains and the role of directors, with  a particular focus on cancellation of events and businesses in the tourism and hospitality sector.

You can find a recording of the webinar from NGI here.

What are the new rules around holiday entitlement?

Workers who have not taken 20 days holiday entitlement due to Covid-19 can now carry it over into the next 2 leave years. It only applies where it was not reasonably practicable for a worker to take their annual leave due to the coronavirus.

What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.