Skip to content

Do I need to obtain consent from a member of staff if we have taken the decision to restrict/alter their duties?

If the duties are so fundamentally different from their contracted role, then yes. For example, if you are asking a frontline clinical member of staff to undertake administrative tasks in another area, then this will be a fundamental change to their terms and conditions for which you need their consent.

If there is a minor alteration to their duties, or the clause within their contract is wide enough to cover their amended duties, then arguably to do not need their consent but best practice would be to obtain their agreement.

Related FAQs

What other financial support is there for businesses?

 Aside from the CBILS Scheme, the Government have, or are in the process of, implementing several different schemes to support businesses financially through the Covid-19 outbreak.

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

Can a sponsor cut the salary or hours of a Tier 2 visa holder?

Yes but the sponsor must report this on the Sponsor Management System within 10 working days and must follow normal employment law principles.

If this results in the sponsored worker’s falling below the minimum required salary the usual position is that they cannot continued to be sponsored. However the government has implemented a concession for sponsors who have ceased trading or temporarily reduced trading which allows the salary to be reduced to 80% of the figure stated on the Certificate of Sponsorship or £2,500 per month, whichever is lower.

Flexible working

Many employees require flexible working now more than ever. That could be reduced hours, working from home, reduced days, etc. Be careful to act fairly when considering these requests as they can be a discrimination claim in the waiting.

A flexible working request is a request for a permanent change to the contract of employment however to encourage a greater take up during this difficult time, you can agree this on a temporary basis.

I’m a housing provider. How do I continue to manage disrepair during the coronavirus outbreak?

The practicalities and processes regarding disrepair claims will undoubtedly be affected. Housing providers will have to adopt a risk-based approach and consider government guidance to handle claims going forward. Key points to consider are:

  • Compliance with the Pre-Action Protocol for Housing Conditions Claims (particularly disclosure)
  • The practicalities of inspection
  • Non-urgent repairs