Skip to content

Do I need to obtain consent from a member of staff if we have taken the decision to restrict/alter their duties?

If the duties are so fundamentally different from their contracted role, then yes. For example, if you are asking a frontline clinical member of staff to undertake administrative tasks in another area, then this will be a fundamental change to their terms and conditions for which you need their consent.

If there is a minor alteration to their duties, or the clause within their contract is wide enough to cover their amended duties, then arguably to do not need their consent but best practice would be to obtain their agreement.

Related FAQs

What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases

The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:

  • The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
  • How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
  • Whether the definition of higher risk buildings is correct, or will require some refinement.

The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.

Can employees on fixed-term contracts be furloughed?

Yes. Their contracts can be renewed or extended during the furlough period without breaking the terms of the scheme.

If the employee’s contract has not already expired, the contract can be extended or renewed. The employee may be furloughed provided that they were employed on or before 30 October 2020. You must also have made a RTI submission to HMRC between 20 March 2020 and 30 October 2020.

If the employee’s contract expired on or after 23 September 2020, the employee can be re-employed and furloughed. Please note that the employee must have been employed by you on 23 September 2020 and you must have made a RTI submission to HMRC between 20 March 2020 and 30 October 2020.

 

What happens if someone is asked to restrict their duties but, despite acknowledging the risks to their health involved, they say that they want to continue to work on the front line?

As their employer, you have an overriding duty to provide a safe system of work. The Trust would not be able to run a defence to say that an employee “waived their rights” and chose to continue to work. Provided the decision around restricting duties has been carefully thought out, a full risk assessment undertaken and the employee has been truly consulted about the impact on them, then the decision taken will be a reasonable management instruction. Failing to follow that reasonable management instruction could amount to a disciplinary offence.

What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

What are the new Procurement Policy Notes (PPN)?

The Government has produced and published three new Procurement Policy Notes as a direct result of the ever changing Covid-19 environment.

PPN 01/20: Responding to COVID-19

The purpose of PPN 01/20 is to ensure that contracting authorities are able to procure goods, services and works with extreme urgency, to allow them to respond to the pandemic efficiently.

This PPN provides guidance for the following circumstances:

  • Direct award due to extreme urgency (regulations 32(2)(c)) (click here to read our article regarding regulation 32)
  • Direct award due to an absence of competition or protection of exclusive rights
  • Call off from an existing framework agreement or dynamic purchasing system
  • Call for competition using a standard procedure with accelerated timescales
  • Extending or modifying a contract during its term

PPN 02/20: Supplier relief due to COVID-19

PPN 02/20 focuses predominantly on the supplier to assist in keeping supply chains open and ensuring that suppliers are kept financially sound during these unpredictable times.

This PPN provides guidance for the following circumstances:

  • Urgent reviews of contract portfolios and to update suppliers if they believe they are at risk
  • Put in place appropriate payment measure to support supplier cash flow
  • Where contract payments are based on ‘payment by results’ make payments based on previous invoices
  • Ask suppliers to act on a ‘open book’ basis and make cost data available to the contracting authority during this period
  • Ensure invoices submitted by suppliers are paid immediately on receipt

PPN 03/20: Use of Procurement Cards

The third guidance note PPN 03/20 relates to the use of procurement cards to increase efficiency and accelerate payment to suppliers.

This PPN provides the following advice and urges organisations to arrange with their procurement card provider to:

  • Increase a single transaction limit to £20,000 for key card holders
  • Raise monthly limits on spending with procurement cards to £100,000 for key card holders
  • Spend on procurement cards each month in excess of £100,000 should be permissible to meet business needs

Although the above advice has been provided, should these limits not be necessary, organisations should seek an appropriate transaction limit or monthly limit.

The PPN also advises that by 30 April 2020, in scope organisations should:

  • Ensure that a number of appropriate staff have the authority to use these cards
  • Open all relevant categories of spend to enable these cards to be used more widely