Do leaseholders who have more than three properties in the UK have to pay the full contribution for building safety works and is there a way of finding out how many properties out leaseholders have in the UK?
The first point to note is that it is the position as at 14 February 2022 which is relevant, as whether or not a lease is a ‘qualifying lease’ for the purposes of recovering costs under the Building Safety Act was effectively frozen at that time.
If a leaseholder owned more than three properties in the UK (and the property in question was not their principal home) at that time, then the lease will not be a qualifying lease. The protections under the Act which prevent or restrict the landlord’s ability to recover the cost of remedial works through the service charge will not therefore apply to that lease (save potentially for the provision that costs cannot be recovered where the landlord is responsible for the defects, which does not expressly refer to qualifying leases).
The lack of a searchable database to assess how many properties a leaseholder has in the UK is however one of the difficulties to be resolved in this regard, as there is currently no way of searching the Land Registry to obtain a list of properties owned by one individual. The guidance appears to rely on the leaseholder completing the leaseholder deed of certificate being open and honest in this regard, and that deed of certificate being passed onto subsequent owners. Making false representations or failing to disclose required information in the deed of certificate may be a criminal offence, although reliance on this to discourage mis-reporting is clearly less satisfactory than having a searchable register.
Related FAQs
All policies will impose a stringent obligation, often with time limits, for you to notify insurers of circumstances that may give rise to a potential claim under the policy and non-compliance may well negate your cover. If therefore you have potential cover under your policy you must make a precautionary notification to Insurers as soon as possible.
There have always been ways for public bodies to assist without being required to notify these for approval. These continue to be available during the financial crisis, and are likely to be increasingly useful for measures which need to be introduced quickly. The measures include:
Those where it is possible to conclude that there is no effect on trade between Member States – for example, measures which are likely to have only a limited local effect. The European Commission has concluded, for example, that measures to assist locally-focused cultural activity can be assumed to have no effect on inter-State trade.
Those where it is possible to conclude that the State is acting in a way consistent with a commercial operator (the so-called Market Economy Operator Principle) – particular care will need to be taken in the context of current economic conditions to ensure that it can reasonably be asserted that a commercial operator would act in the same way as the public body.
Measures under the General Block Exemption Regulation – this legislation allows various types of aid, or aid schemes, to be employed.
Examples include aid for SMEs, aid for research and development, aid for local infrastructure and aid to ports and airports.
De Minimis Measures – Member States are permitted to grant small amounts of aid to undertakings over three fiscal years (the current year and the previous two years). This allows undertakings to receive up to €200,000 (or €500,000 where they are providing public services).
All employers have a duty to prevent illegal working, and carrying out proper Right to Work checks are a fundamental part of this. In light of Covid-19, the Home Office has brought in some temporary measures for employers to use to carry out the requisite Right to Work checks. Failure to follow these could lead to enforcement action and penalties.
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.
Solicitors can be authorised to sign contracts for their clients – a signed letter of authority should be scanned and sent to avoid posting potentially contaminated documents.
Solicitors should exchange supplemental agreements on behalf of their clients to agree to postpone exchange and completion dates if it has been agreed to push these back.
The Law Society advises that electronic signatures be used as much as possible for contracts, to avoid possible contamination. However, the Land Registry confirms that the legal transfer document cannot be validly executed with an electronic signature. Solicitors should agree a completion undertaking that the original transfer document will be sent when received and after the restrictions have been lifted.
The Land Registry’s latest guidance https://www.gov.uk/guidance/coronavirus-covid-19-impact-on-hm-land-registrys-services published on 14 May states:
We accept deeds that have been signed using the ‘Mercury signing approach’.
For land registration purposes, a signature page will need to be signed in pen and witnessed in person (not by a video call). The signature will then need to be captured, with a scanner or a camera, to produce a PDF, JPEG or other suitable copy of the signed signature page. Each party sends a single email to their conveyancer to which is attached the final agreed copy of the document and the copy of the signed signature page.
Solicitors should be willing to adopt this procedure for completing transactions to enable them to be registered by the Land Registry.
The execution of a transfer is a deed and must be witnessed. Members of the family can witness signatures so long as they are not also a party to the document. A witness will be more credible if they are 18 or over, but this is not a legal requirement. The legal requirement is for the witness “to be present” when the document is signed. It would be possible for a witness to be on the other side of the room or the other side of a window, and validly witness the execution of a deed. The witness does need to take precautions to avoid possible contamination from the document.
A statutory declaration does not need to be witnessed but must be administered by a solicitor or commissioner for oaths. There is no legally prescribed process for this, and there is nothing to suggest that this could not be validly done via a video telephone call if the signature on the declaration can clearly be seen by the person commissioning the oath when the oath is made.