Do leaseholders who have more than three properties in the UK have to pay the full contribution for building safety works and is there a way of finding out how many properties out leaseholders have in the UK?
The first point to note is that it is the position as at 14 February 2022 which is relevant, as whether or not a lease is a ‘qualifying lease’ for the purposes of recovering costs under the Building Safety Act was effectively frozen at that time.
If a leaseholder owned more than three properties in the UK (and the property in question was not their principal home) at that time, then the lease will not be a qualifying lease. The protections under the Act which prevent or restrict the landlord’s ability to recover the cost of remedial works through the service charge will not therefore apply to that lease (save potentially for the provision that costs cannot be recovered where the landlord is responsible for the defects, which does not expressly refer to qualifying leases).
The lack of a searchable database to assess how many properties a leaseholder has in the UK is however one of the difficulties to be resolved in this regard, as there is currently no way of searching the Land Registry to obtain a list of properties owned by one individual. The guidance appears to rely on the leaseholder completing the leaseholder deed of certificate being open and honest in this regard, and that deed of certificate being passed onto subsequent owners. Making false representations or failing to disclose required information in the deed of certificate may be a criminal offence, although reliance on this to discourage mis-reporting is clearly less satisfactory than having a searchable register.
Related FAQs
The BBC
The national broadcaster’s collated content surrounding the Covid-19 pandemic:
https://www.bbc.co.uk/news/coronavirus
and with regards to business:
https://www.bbc.co.uk/news/business
The Chancellor confirmed that payments under the scheme would not be available immediately.
As mentioned earlier, if an agency is involved you must send them a copy of the status determination statement for each contractor, and they will also have the right to dispute the outcome.
If the agency pays the contractor, they will be responsible for the operation of PAYE and NIC’s deductions and any apprenticeship levy. The agency may try to recover these costs from the end user client.
If workers are supplied by an agency or umbrella company and are already treated as employees by the agency, they will remain unaffected by IR35.
Where an employer is proposing to dismiss:
- 100 or more employees at one establishment within a 90-day period, consultation must begin at least 45 days before the first dismissal takes effect
- Between 20 and 99 employees within a 90-day period, consultation must begin at least 30 days before the first dismissal takes effect
- If you are proposing to dismiss less than 20 employees then there are no minimum time limits but you must adhere to a fair process which will involve individual consultation and providing the employee with a right of an appeal
On 2 April 2020, the Government issued guidance relating to Private Finance Initiatives and PF2 Projects. The guidance, which is to be enforced with immediate effect (currently due to stay in place until 30 June 2020), is one of several guidance notes issued to date.
A link to the guidance is set out below:
Key messages to contracting authorities
- PFI contractors should very much consider themselves as being part of the public sector response to the current pandemic
- Covid-19 is not regarded as, and is not to be classified as a force majeure event
- PFI contractors must ensure that contingency plans are up to date and have been reviewed and discussed with contracting authorities to enable the continuity of full services to respond to the pandemic and maintain vital public services
- Contracting authorities should work closely with PFI contractors to use all available options to maintain public services during the emergency period
- Local arrangements should be made where PFI contractors can’t deliver the agreed requirements and performance standards
- “Best efforts” should be made by all parties for the continuation of service provision