Do leaseholders who have more than three properties in the UK have to pay the full contribution for building safety works and is there a way of finding out how many properties out leaseholders have in the UK?
The first point to note is that it is the position as at 14 February 2022 which is relevant, as whether or not a lease is a ‘qualifying lease’ for the purposes of recovering costs under the Building Safety Act was effectively frozen at that time.
If a leaseholder owned more than three properties in the UK (and the property in question was not their principal home) at that time, then the lease will not be a qualifying lease. The protections under the Act which prevent or restrict the landlord’s ability to recover the cost of remedial works through the service charge will not therefore apply to that lease (save potentially for the provision that costs cannot be recovered where the landlord is responsible for the defects, which does not expressly refer to qualifying leases).
The lack of a searchable database to assess how many properties a leaseholder has in the UK is however one of the difficulties to be resolved in this regard, as there is currently no way of searching the Land Registry to obtain a list of properties owned by one individual. The guidance appears to rely on the leaseholder completing the leaseholder deed of certificate being open and honest in this regard, and that deed of certificate being passed onto subsequent owners. Making false representations or failing to disclose required information in the deed of certificate may be a criminal offence, although reliance on this to discourage mis-reporting is clearly less satisfactory than having a searchable register.
Related FAQs
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
The current position is that the PSC is responsible for assessing whether IR35 applies. This current regime has been difficult to police by HMRC and HMRC considers there is widespread flouting of the rules by contractors.
From April 2021 the responsibility for assessing whether IR35 applies will shift to the end user/client (with the exception of ‘small’ companies) which will require an assessment to be carried out on a contract by contract basis. HMRC anticipates that this will be easier to monitor and that end user businesses will be more compliant.
The reformed regime will apply to payments made on or after 6 April 2021 for services carried out on or after this date.
The guidance gives numerous examples of the types of performance adjustment which parties should consider. For example this includes:
- Varying deadlines (e.g. for performance or payment)
- Varying compensation (e.g. to recognise increased costs)
- Varying the nature of performance (e.g. allowing substitute goods, allowing pert delivery of services)
The guidance also encourages a reasonable approach to enforcement, which might encourage delaying issuing formal proceedings, increased use of mediation or providing more information to the other party than would be volunteered under normal circumstances.
Where an employer is proposing to dismiss:
- 100 or more employees at one establishment within a 90-day period, consultation must begin at least 45 days before the first dismissal takes effect
- Between 20 and 99 employees within a 90-day period, consultation must begin at least 30 days before the first dismissal takes effect
- If you are proposing to dismiss less than 20 employees then there are no minimum time limits but you must adhere to a fair process which will involve individual consultation and providing the employee with a right of an appeal
Has there ever been a more important time for all staff to feel that they are able to raise concerns about their working environment?
It is a pertinent time to remind all staff that they should be able to raise concerns without the fear of repercussions. It is a good time to be reviewing and re-issuing your Freedom to Speak up/Whistleblowing policy to all. Likewise it is a good time to remind all staff that they should not treat others unfairly or detrimentally for raising health and safety concerns.
Both subjecting someone to a detriment because they have blown the whistle or raised health and safety concerns (and dismissing someone for the same) is unlawful.