Skip to content

Does Force Majeure apply to the leasing of commercial property?

Some commercial tenants have queried whether the current situation is a force majeure which may allow it to terminate the lease. Clauses which allow a party to terminate a lease for a force majeure event or, to put it another way, an “act of God”, are however extremely rare in modern commercial leases. Even if there is such a provision in your lease, it would need to be drafted to apply to an outbreak of disease.

Related FAQs

What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

What has been the response from the Competition and Markets Authority (CMA)?

The CMA is the government body that is responsible for protecting consumers from unfair trading practices. It has announced programme of work to investigate reports of businesses failing to respect cancellation rights during the Coronavirus pandemic.

Based on the complaints received by them from consumers, the CMA has identified three sectors of particular concern:

  • Weddings and private events
  • Holiday accommodation
  • Nurseries and childcare providers

The CMA has expressed concern about the number of complaints that it has received about businesses seeking to retain deposits for cancelled events, undue restrictions being placed on use of vouchers provided for cancelled bookings, and payments being demanded to hold open nursery places.

The CMA has said it will prioritise investigation of these sectors, and then move on to other sectors.

Do you think MHFA will become a legal requirement for businesses eventually?

This is something which is certainly on the Government’s radar as there is currently a Bill being heard in Parliament about making MHFAs a legal requirement for workplaces. It is still in the very early stages and therefore it is not clear at this stage what the outcome will be. What is clear is that this is an area which is being taken very seriously and it would not be surprising if measures were put in place regarding MHFAs in the workplace.

What should be included in genuinely self-employed contractor terms?

If you consider the factors used to determine status you can include the following terms that are more in line with a self-employed relationship:

  • The right to provide a substitute of the contractor’s choice in the event the individual is not able to perform the services;
  • The ability to work for other businesses as long as doing so will not affect the services to be provided by the contractor;
  • The contractor should have sufficient control over how, when and where (if possible) they provide the services;
  • A degree of financial risk can be included for unsatisfactory work or failing to complete a project or task

We have terms that cover all of these points that can be tailored to your needs. The consultancy agreement is included in our IR35 toolkit.