Does Force Majeure apply to the leasing of commercial property?
Some commercial tenants have queried whether the current situation is a force majeure which may allow it to terminate the lease. Clauses which allow a party to terminate a lease for a force majeure event or, to put it another way, an “act of God”, are however extremely rare in modern commercial leases. Even if there is such a provision in your lease, it would need to be drafted to apply to an outbreak of disease.
Related FAQs
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
The guidance from the Government concerning private sector organisations is very different from the guidance for public sector and organisations that receive public funding. The guidance states:
“The government expects that the scheme will not be used by many public sector organisations, as the majority of public sector employees are continuing to provide essential public services or contribute to the response to the coronavirus outbreak.
Where employers receive public funding for staff costs, and that funding is continuing, we expect employers to use that money to continue to pay staff in the usual fashion – and correspondingly not furlough them. This also applies to non-public sector employers who receive public funding for staff costs. Organisations who are receiving public funding specifically to provide services necessary to respond to Covid-19 are not expected to furlough staff.”
This guidance isn’t particularly clear but it appears that there is a recognition that there are different types of organisations which could be caught by this:
- Organisations who will be required to provide frontline services during the Covid-19 response. It is interpreted that NHS organisations such as NHS Trusts will fall firmly into this category. Employees of such organisations are expected not to be furloughed and to continue to work and be paid their normal salary in the usual way.
- Organisations who receive public funding to provide services to respond to the Covid-19 crisis. These organisations are not expected to furlough their staff. The type of organisation that would fit into this category are those that have been commissioned to developing breathing apparatus or testing kits to meet the needs of the healthcare sector during the peak of the pandemic.
- Organisations who receive public funds for staff costs to operate services. Employers are expected to continue to pay staff if the money to pay them is publicly funded. It is strongly inferred that this is irrespective of whether such staff have any work to perform. The type of organisation that is likely to fall into this category are GP practices, charities and private sector companies that have won contracts with the public sector.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
The fee payer that pays the fee to the contractor’s PSC for the services (end user client or agency) will be responsible for operating PAYE and deducting NIC’s. The fee payer must also pay employer NIC’s and where applicable the apprenticeship levy so there will be additional costs involved in the event of a change to employed status for tax purposes.
If the assessment concludes that the contractor is self-employed, the PSC can continue to be paid gross.
Every company has to file accounts at Companies House every year. If they are filed late, a fine is automatically levied. If there is a long delay in filing them, the directors are at risk of prosecution and the Registrar of Companies might start a process which could ultimately lead to the company being struck from the register.
However, Companies House has recognised that businesses might currently face exceptional problems in preparing and filing their accounts on time and so have posted a notice on their website which says that if immediately before the filing deadline, it becomes apparent that accounts will not be filed on time due to coronavirus, you can make an application to extend the period allowed for filing.