Skip to content

Does Force Majeure apply to the leasing of commercial property?

Some commercial tenants have queried whether the current situation is a force majeure which may allow it to terminate the lease. Clauses which allow a party to terminate a lease for a force majeure event or, to put it another way, an “act of God”, are however extremely rare in modern commercial leases. Even if there is such a provision in your lease, it would need to be drafted to apply to an outbreak of disease.

Related FAQs

Flexible working

Many employees require flexible working now more than ever. That could be reduced hours, working from home, reduced days, etc. Be careful to act fairly when considering these requests as they can be a discrimination claim in the waiting.

A flexible working request is a request for a permanent change to the contract of employment however to encourage a greater take up during this difficult time, you can agree this on a temporary basis.

Does the introduction of CLBILS assist private equity-backed businesses?

Under CBILS, for the purposes of calculating the applicant’s annual turnover, approved lenders have been aggregating turnover across the whole of the private equity investor’s portfolio meaning they failed to qualify for the scheme as they were deemed to exceed the £45 million threshold.

For private equity-backed businesses, the removal of the upper limit on annual turnover criteria for CLBILS seemingly avoids the issue of turnover aggregation across investment portfolios seen with the CBILS, potentially enabling more private equity sponsor portfolio companies to be able to access the CLBILS funding.

Do you need to use HMRC's CEST tool?

CEST stands for Check Employment Status for Tax and, although this should do exactly what is says on the tin, there has been criticism of its accuracy and effectiveness. The CEST tool does not test whether there is ‘mutuality of obligation’ in the relationship which is a key factor in determining status.

You are not obliged to use CEST if you are happy with your own assessment process. If you do use CEST keep a record of the certificate given at the end of the assessment and keep this on the contractor’s file. HMRC will stand by the outcome of a CEST assessment provided the information has been honest and accurate. However, you must have entered information honestly to rely on it – you can’t just say what you want to get the right answer, as HMRC may test what you have said.  Also, many people are unhappy with the CEST tool and consider it leans too much towards employed status.

When will these temporary Right To Work measures end?

The Home Office has not stated when it will end these temporary measures, albeit it has stated that it will provide a warning. Where employers have carried out checks using the temporary measures, the Home Office has confirmed that it will require employers to carry out retrospective checks on any of the following:

  • Employees who started working for you when the temporary measures were in place
  • Employees who required a follow up check during the temporary measures (for example because their previous leave was coming to an end).

It is not explicit from the guidance but these retrospective checks must require you to have in your possession the physical ID in its original form. When carrying out the retrospective check, employers must record this using the following wording “the individual’s contract commenced on [insert date]. The prescribed right to work check was undertaken on [insert date] due to Covid-19.”

These further checks must be made within eight weeks of the temporary measures ending, and employers must keep records of both checks undertaken. Where the employer discovers that the employee does not have the right to work during the retrospective check they should stop employing them.

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.