Skip to content

How can I tell if the correct procedure was followed when the Will was executed?

There are a number of technical formalities which any testator must follow in order to execute a valid Will.  These include:

  • The Will must be signed by the testator, in the presence of two other witnesses and then be signed by those witnesses, in the presence of the person making the Will after the testator themselves has signed the document.
  • The person making the Will must be over 18 years of age and have mental capacity.
  • The person must make the Will voluntarily without undue influence and must know and understand what the Will says; and
  • The Will must be in writing

Related FAQs

What should I do if I think this is relevant to my contracts?

It would be prudent to take legal advice early in relation to any issue you foresee in performing a contract. This will allow you to:

  • Ensure that initial contact with your counterparty is framed in the correct way
  • Ensure that any variations are fully documented so that both parties are fully protected
What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases

The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:

  • The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
  • How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
  • Whether the definition of higher risk buildings is correct, or will require some refinement.

The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.

What challenges to planning permission does the current lockdown situation present?
  • Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
  • Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
  • Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
  • The ability to get people on site to undertake material operations

In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.

If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.

What is a small company?

The changes will not apply to end users who are a small company. If you meet two out the following 3 conditions, you will meet the small company definition and are therefore exempt from the changes to IR35:

  1. Annual turnover is no more than £10.2 million
  2. Balance sheet total is no more than £5.1 million
  3. No more than 50 employees

Companies will always be classified as small in their first financial year. Public companies will always be considered to be medium or large businesses and cannot fall under this exemption.

For a group company to be a small company its parent company must also meet the small company definition.

Can contractors with public sector engagements and who are in scope (deemed employment) for IR35 purposes be furloughed?

Contractors working for public sector organisations who are deemed employees for IR35 purposes may be eligible to be furloughed provided they are paid via PAYE. In this scenario the agreement to furlough would be made between the contractor’s personal service company (PSC) and the fee payer (usually the agency). The parties would agree that the contractor will carry out no work for the public sector organisation while furloughed and the fee payer would apply for the grant.

At the moment the guidance states that in order to be eligible a claim for furlough must have to have been submitted by 31 July 2020 for a period of 3 weeks between 1 March and 30 June 2020.