How do EWS1 form requirements apply to leasehold flats sold to secure tenants exercising their Right to Buy under the Housing Act 1985 whether in low, medium or high rise blocks?
Where a lender requires a EWS1 as part of the mortgage requirements for a flat this will apply regardless of its tenure and will therefore apply to applicable RTB properties. It may also be required in order to obtain a valuation for the disposal notices and issues in obtaining it could cause problems in serving this within relevant deadlines required by legislation.
Related FAQs
- On admission to critical care, the risks, benefits and likely outcomes of the different treatment options should be discussed with patients, families and carers so they can make informed decisions about their treatment wherever possible.
- A member of the critical care team should be involved in these discussions whenever the patient or team needs advice about critical care to make decisions about treatment.
The amount an insurer charges for providing cover is a critical aspect of the underwriting process. The premium must be sufficient to cover expected claims but must also take into account the possibility that the insurer will have to access its capital reserve –it is risk assessment based and the greater the risk, the higher the premium. Historically, insurers of high-rise buildings would have only had to prepare for a loss caused by damage to just a few flats within a building. That is because the design and construction of that building, with the right materials and fire safety provisions in place, should have limited the spread of fire and allowed the damage to be contained –or at least make this an extremely low risk. Now we know that many buildings have been designed, built and signed off in a regulatory system that an independent Government review has found was not fit for purpose. Premiums will reduce overtime but will be dependent upon the perceived level of risk reducing as the regulatory regime, BSA and BSR become more established.
As part of the Coronavirus Bill there is some good news for tenants in so far as it included the following:
- All commercial tenants in England, Wales and Northern Ireland missing rent payments are to benefit from a government ban on forfeiture of their lease.
- Landlords then will be prevented from terminating leases and “evicting” commercial tenants.
- The above provisions rules will apply not only to principal rent, but to “any sum a tenant is required to pay”, leaving the burden of supplying services and insuring the premises on landlords. The bill will last until 30 June 2020, with an option for the government to extend this deadline.
Whist this is helpful to any Tenant planning not to pay rent or other payments due under their lease insofar as they will not suffer forfeiture and be evicted, it should be noted that the contractual obligation to continue paying rent and all other costs due under the lease remains and Landlords will still be able to take action to recover any payments due under the lease that are in arrears.
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
Civil Court listing priorities, last updated by HMCTS on 24 April 2020, categorise the Court’s work into the following:
Priority 1 – work that must be done: this includes any applications in cases listed for trial in the next 3 months, any applications where there is a substantial hearing listed in the next month, all multi-track hearings where parties agree that it is urgent (subject to triage).
Priority 2 – work that could be done: Infant and Protected Party approvals, Applications for interim payments in multi-track / personal injury / clinical negligence cases, Applications to set aside Judgment in default, Preliminary Assessment of costs.
The full guidance can be found at: