How do EWS1 form requirements apply to leasehold flats sold to secure tenants exercising their Right to Buy under the Housing Act 1985 whether in low, medium or high rise blocks?
Where a lender requires a EWS1 as part of the mortgage requirements for a flat this will apply regardless of its tenure and will therefore apply to applicable RTB properties. It may also be required in order to obtain a valuation for the disposal notices and issues in obtaining it could cause problems in serving this within relevant deadlines required by legislation.
Related FAQs
It is. If you assess a risk and identify a control measure then fail to deploy it, then you are breaching your legal duties under HASWA and potentially committing a criminal offence. So if you decide for example that N95 respirators have to be used by everyone, you have a duty to provide them.
So the short answer is yes.
Some of these can be implemented by you, some need agreement or consultation and some depend on the wording of contracts. We’ll explain more in relation to each option.
CMA guidance suggests that it will not take enforcement action in respect of agreements which:
- Are appropriate and necessary to avoid a shortage, or ensure security, of supply
- Are clearly in the public interest
- Contribute to the benefit or wellbeing of consumers
- Deal with critical issues that arise as a result of the Covid-19 pandemic
- Last no longer than is necessary to deal with these critical issues
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
To facilitate social distancing the Home Office has stated that as of 30 March 2020, the following are permitted:
- The RTW check can now take place over video call.
- Job applicants no longer have to send original documents but can send scanned copies or photos to the employer.
- Where the job applicant cannot provide these documents, employers can use the Employer Checking Service and if they have the right to work, then the employer will receive a Positive Verification Notice which will provide the employer with a statutory excuse for 6 months.
These adjustments remain in place until the Home Office confirms otherwise.