How do I apply for CBILS?
CBILS is made available through the British Business Bank’s 40+ accredited lenders and partners, which are listed on their website (https://www.british-business-bank.co.uk/ourpartners/coronavirus-business-interruption-loan-scheme-cbils/accredited-lenders/).
Businesses should initially approach their own lender and only consider other lenders if they are unable to access the finance they need. Note, not every accredited lender can provide every type of finance listed.
Some banks/lenders are not included in the list of accredited lenders which appears to mean that they cannot provide support through the Scheme. We understand from the British Business Bank that further lenders are applying to be accredited but that this may take a little time to process. If the provider of your senior debt is not on the accredited list you should consider approaching the bank which provides your day to day account banking services.
If you wish or need to access the Scheme via an alternative funder the process may take longer as usual on-boarding and KYC processes will need to be undertaken.
Related FAQs
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Failure to comply with the individual consultation obligations could render the dismissal unfair and expose you to a financial penalty of the lower of up to 1 years gross pay or the maximum statutory limit (currently £88,519).
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
You cannot include the following payments in a claim:
- Discretionary bonus or commission payments
- Tips
- Non-cash payments
- Non-monetary benefits including taxable benefits in kind
- Salary sacrifice benefits that reduce an employee’s pay (however HMRC has agreed that such arrangements can be stopped by agreement if due to COVID-19 and the contract is changed)
The updated guidance has confirmed that all of the grant claimed should be paid to the employee in the form of money and that none of the grant is to the used to pay for the provision of benefits or a salary sacrifice scheme.
As their employer, you have an overriding duty to provide a safe system of work. The Trust would not be able to run a defence to say that an employee “waived their rights” and chose to continue to work. Provided the decision around restricting duties has been carefully thought out, a full risk assessment undertaken and the employee has been truly consulted about the impact on them, then the decision taken will be a reasonable management instruction. Failing to follow that reasonable management instruction could amount to a disciplinary offence.