How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

Related FAQs

Who should come back to work and when?

This is critical. The guidance remains clear – IF YOU CAN WORK FROM HOME YOU SHOULD CONTINUE TO DO SO. Bringing people back into work unnecessarily is a big mistake.

Think about how many employees should physically return to the workplace – the fewer the people on site, the lower the risk AND the less pressure on public transport.

Employers will need to be very careful to recognise workers in vulnerable groups or who develop or live in a household with someone who develops symptoms of Covid-19 – again, look at government guidelines. You should understand that this will mean a higher number of staff absences and consider how this might be managed.

Look to keep smaller teams of workers together, minimise physical meetings and if you MUST have them, keep them short and under 15 minutes. Be imaginative – use online platforms like Teams and Zoom wherever you can.

Retraining and redeploying

If the business has areas requiring an increased workforce whilst others require a reduced workforce, staff can be retrained and redeployed across the organisation or even across a wider group of companies. This will not reduce the wage bill but will avoid the need for redundancies. Making fundamental changes to an employee’s role and duties will require their agreement following a fair selection and consultation process.

What do we need to do?

Privacy policy – You must make sure the relevant privacy policies deal with how you will process Covid-19 data. You should have an employee privacy policy and this may already deal with health data (if it doesn’t, it should). You might also need to look at privacy policies for customers, visitors and suppliers. This ensures that processing is lawful, fair and transparent.

Lawful processing conditions – You will need to consider which processing conditions you are relying on (remembering that you need both an Article 6 condition and an Article 9 condition – this is the part of the GDPR which deals with special category data). As a lot of the data you collect will be about employees, you can’t use consent so you will have to find another lawful reason under GDPR which allows you to process the data.

Appropriate policy document – When you are considering your Article 9 processing conditions, remember you must also have an “appropriate policy document” in place.

Processing record – Finally make sure your processing record is up to date with information on what data you collect and use.

How has the law changed?

In part in response to the Covid-19 pandemic, legislation was passed by the government earlier this year which sought to assist companies to trade through the current economic climate. Included within the measures is a degree of protection from compulsory winding up.

The Corporate Insolvency and Governance Act 2020 (The Act), was laid before parliament on 20 May, and became law on 26 June. It is important creditors are aware of what changes have been implemented and the potential and impact which it may have upon debt recovery action you may be considering or have already commenced.

The main part of the Act affecting creditors is the temporary restriction on presentation of winding up petitions and the factors that the Court has to take into account when deciding whether to wind up a company.

On Thursday 24 September 2020 the government passed a further statutory instrument which extended the operation of these restrictions. As a result, the measures which were due to expire on Wednesday 30 September 2020 have now been extended until 31 December 2020.

A key point to note is that the Act has retrospective effect so any pending petitions presented after 27 April will be affected, along with any winding up orders made after that date.

The Act has introduced the following restrictions:

  • A petition cannot be presented by a creditor during the period of 27 April 2020 and 31 December 2020 unless the creditor has reasonable grounds to believe that (a) coronavirus has not had a financial effect on the debtor, or (b) the debtor would have been unable to pay its debts even if coronavirus had not had a financial effect on the debtor;
  • A petition cannot be presented after 27 April 2020 if it is based on a unsatisfied statutory demand served between 1 March 2020 until 31 December 2020;
  • When deciding whether to make a winding up order the Court will need to be satisfied that the grounds giving rise to the petition would have arisen even if Covid-19 did not have a financial effect on the debtor;
  • All winding up orders made between the 27 April and 31 December will automatically be void (that is, of no legal effect) unless the Court would have made the winding up order if the new law was in force at the time the order was made.
Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here