How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

Related FAQs

Do I need to obtain consent from a member of staff if we have taken the decision to restrict/alter their duties?

If the duties are so fundamentally different from their contracted role, then yes. For example, if you are asking a frontline clinical member of staff to undertake administrative tasks in another area, then this will be a fundamental change to their terms and conditions for which you need their consent.

If there is a minor alteration to their duties, or the clause within their contract is wide enough to cover their amended duties, then arguably to do not need their consent but best practice would be to obtain their agreement.

What allowances has the Government proposed for company meetings?

The Government’s Corporate Insolvency and Governance Act introduces amendments to the current rules for companies on holding meetings, to address the difficulties companies are facing due to the Covid-19 pandemic.

The new provisions apply to meetings held between 26 March 2020 and 30 September 2020 (referred to as the “Relevant Period”). Subsequent regulations by the Government can be used to shorten this period or extend by up to 3 months but not past 5 April 2021.

The provisions will have retrospective effect, so meetings that were held after 26 March 2020 that may not have met the usual legal requirements due to lockdown, will be validated under these new provisions. These provisions under the Act make amends to relevant legislation and override a company’s articles of association.

For general meetings and certain other meetings of companies, the Act states that:

  • The meeting need not be held in any particular place;
  • The meeting may be held, and any votes may be cast, by electronic means or other means;
  • The meeting may be held without anyone being in the same place
  • Persons attending the meeting no longer have the following rights: the right to attend in person, the right to participate in the meeting other than by voting, or the right to vote by particular means.

The aim of these changes is to facilitate virtual meetings, and remove the need for a physical venue.

Where a company was required to hold its AGM between 26 March and 30 September 2020, it can be held at any time before 30 September 2020.  The Secretary of State has the power to make regulations to further extend the deadline.

What do we need to do?

Privacy policy – You must make sure the relevant privacy policies deal with how you will process Covid-19 data. You should have an employee privacy policy and this may already deal with health data (if it doesn’t, it should). You might also need to look at privacy policies for customers, visitors and suppliers. This ensures that processing is lawful, fair and transparent.

Lawful processing conditions – You will need to consider which processing conditions you are relying on (remembering that you need both an Article 6 condition and an Article 9 condition – this is the part of the GDPR which deals with special category data). As a lot of the data you collect will be about employees, you can’t use consent so you will have to find another lawful reason under GDPR which allows you to process the data.

Appropriate policy document – When you are considering your Article 9 processing conditions, remember you must also have an “appropriate policy document” in place.

Processing record – Finally make sure your processing record is up to date with information on what data you collect and use.

Can I argue that my contract has been frustrated?

It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.

If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.

It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.

Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.

Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.

What facilities are available under CBILS?

Lenders implementing the Scheme can assist in a number of ways, including:

  • Term loans
  • Overdrafts
  • Invoice finance
  • Asset finance facilities

The maximum value available under the scheme is £5m, with repayment terms of up to six years for term loans and asset finance. Overdrafts and invoice finance facilities will be available for up to three years.