How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

Related FAQs

Does this apply to bankruptcy petitions?

No. This bill relates to corporate insolvencies only. Should you require any advice as to personal insolvency situations, please contact our team.

How should contracting authorities work with PFI providers?
  • Working with PFI providers to get contingency plans up to date
  • If a PFI provider is struggling to achieve service delivery requirements due to Covid-19, then local arrangements should be put in place to:
    • maintain unitary charge payments
    • revise contract requirements/standards

moderating payment and performance regimes where appropriate.

  • In any event, you may wish to review and adjust your requirements to reflect the current situation. It is possible that some requirements can be relaxed, whereas others need to be tightened. For example, there may be an increased need for cleaning and maintenance in certain areas of your PFI premises or the layout of the premises and/or room uses may have temporarily changed. With staff illness and shortage likely to be an issue, you may also wish to consider if the resource can be moved from one area to another to help maintain essential services.
  • When putting local bespoke arrangements into place it is vital that:
    •  Contract requirements or performance standards are not relaxed to the point where health and safety are put at risk.
    • It is made clear that the arrangements are temporary and that matters will return to normal as soon as the Covid-19 emergency is over. Indeed the guidance note makes clear that if assets temporarily close they should be kept in such condition that they can be immediately up and running when this emergency is over. In such instances, likely a basic level of maintenance and security will therefore be required as a minimum.
Can you require an employee to tell their employer whether they have been tested for coronavirus/the results of that test?

Yes, this is very likely to amount to a reasonable management instruction which is put in place for public health reasons. Employers should make it clear to their employees that this is something they are required to do and that if they fail to do so this may lead to disciplinary action.

Should I continue to carry out housing inspections during the coronavirus outbreak?

As the pandemic progresses, more and more people will be forced to self-isolate and, inevitably, both tenants and staff will be affected. Put plans in place to mitigate the impact that this may have, particularly regarding staff shortages. The most important focus here should be communication.

The Covid-19 outbreak will affect the pace of everyday life and delays will be expected. Rather than allowing the pandemic to take over completely, it is important to maintain open communication with tenants as much as possible and inform them of any front-facing challenges that you may face.

The Protocol does envisage that delays may occur and allows for some degree of flexibility. Whilst all efforts should be made to conduct inspections where practical and possible, it should be expected by all parties that timescales will be extended during this crisis. It is fundamental, however, that all changes made to standard practice are communicated and explained to tenants to manage expectations.

Similar flexibility should be afforded to tenants. As households are required to isolate it will not always be possible to gain access to properties as would usually be expected and required. Likewise, vulnerable people will wish to protect themselves and their families and may refuse access on this basis. During this period, a degree of understanding must be exercised and concessions made.

Inspections may be delayed if anyone in the household has  symptoms. A questionnaire should be prepared for those visiting properties to assess so far as possible the risk; Personal Protective Equipment should be issued to those visiting, and government guidelines followed.

How does a Public Body amend its contracts to enable continued payment to contractors?

The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.

For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf