How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
Related FAQs
The recommendation is every 3 years, however it is recommended that MHFAs receive regular ongoing training and support.
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
At the discretion of the lender, the Scheme may be used for unsecured lending for facilities of £250,000 and under.
Lenders were required to demonstrate lending additionality (i.e. lending that without the Scheme, wouldn’t have otherwise taken place). The Scheme has been extended to those businesses who would have previously met requirements for a commercial facility and would not have been eligible for CBILS. As a result it is suggested that all viable small businesses affected by Covid-19, and not just those unable to secure regular commercial financing, will now be eligible should they need finance to keep operating.
Primary Residential Property cannot be taken as Security under the Scheme. If the lender can offer finance on normal commercial terms without the need to make use of the Scheme, they will do so.
An employer has a duty of care to its workforce and must take reasonable precautions to protect the health and safety of employees. Employers also have a duty of care towards anyone entering or using their place of business, such as visiting clients or customers.
This means that if an employer reasonably believes that wearing face masks at work is appropriate and necessary, it can issue an instruction to employees to this effect and employees should abide by this as far as possible.
However employers should be cautious about introducing and enforcing a policy across its business which requires its staff to wear face masks as there is the risk of unlawfully discriminating against people who are exempt from wearing face coverings or have legitimate reasons for not doing so. An employer should also consider the duty to make reasonable adjustments for disabled employees and discuss any concerns raised by employees who do not want to or feel unable to wear a mask.
The change in the law has the potential to place much greater financial risks on suppliers, making it more difficult to exit a contract with a customer of doubtful solvency. This will place increased emphasis on appropriate financial due diligence and credit checking before entering into supply contracts.
In addition to the obvious issues around financial risk, suppliers will also need to think carefully about how their contracts are drafted. For example, any form of right that is drafted so as to be triggered on customer insolvency will clearly be problematic. These could include:
- Retention of Title provisions, which are commonly drafted so that the right to enter premises and retake possession of the goods is triggered on insolvency;
- Provisions for brand protection, which seek to control how goods are dealt with on termination of the contract.
This is potentially a very significant development for many businesses. We would strongly recommend specialist advice be obtained so that:
- businesses understand the potential increased risks faced; and
- where possible, contracts are updated so that appropriate protections are maintained.