How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
Related FAQs
Put simply, if it is a requirement of a particular role that PPE is worn, then this should be provided to the employee. If an employer dismissed an employee for refusal to carry out their role due to lack of PPE then this is likely to be an automatically unfair health and safety dismissal.
Furthermore, anyone who is subject to a detriment as a result of raising a health and safety concern, e.g. someone in this situation who refuses to work due to lack of PPE and is sent home without pay, will also have a potentially valid claim in the Employment Tribunal for that detriment, even if they are not dismissed.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
You should speak to your advisors. We do not know presently how existing petitions will be dealt with by the Court. We do know that if any winding up order is made (based on a petition presented after 27 April), it could be found to be void and a creditor may face challenges. Even for petitions presented before 27th April, there is a risk that the Court will not be keen to make a winding up order so it is important that you look at the facts of your debt and weigh up all of the factors before deciding how to proceed.
Yes. For further guidance, please see our FAQs section on Furlough.
Yes. With respect to employees you have an obligation to protect their health so you can gather information to do that. You might gather information from your employees on who has the virus, who has had it and recovered and also who has tested negative. You might also want to know if individuals have been in contact with someone who has it or if they are in a vulnerable group. It is reasonable to want to know where individuals have travelled. In the future it may also be reasonable to know if they are planning to travel to a virus hot spot, as the impact of the virus around the world is likely to continue for some time even after the outbreak has been contained in the UK.
It is reasonable to gather some information about visitors to your site, be they customers or suppliers, as this information will also help protect your staff. However, you should keep what you gather to a minimum. For visitors, it’s unlikely that you need to know anything more than they have Covid-19, are displaying symptoms or have recently been in contact with someone who has the virus.