How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

Related FAQs

What steps can we take to avoid sub conscious bias being a factor in our decision making?

There has been a significant amount of press coverage talking about institutional racism within the NHS not only in terms of the treatment of patients but also in terms of the low representation of ethnic minority staff in management positions. Whilst tackling that issue is beyond the brief here, it is important to recognise that sub conscious bias can, regrettably, play a part in decision making processes. An Employment Tribunal will explore a alleged discriminator’s conscious and sub conscious decision making and working in an environment which has not set out sufficient controls to avoid such sub conscious stereotyping places someone at a greater risk of being discriminated against.

In the context of the issues we are addressing here, i.e. risk assessments around BAME staff, as we have stated above, it is essential that BAME staff are represented at all levels in the discussion. Trusts need to be mindful that BAME are underrepresented in management positions.

BAME staff need to be included in the dialogue and need to have a safe place where they can challenge decisions that are being made in relation to them. There needs to be accountability in the processes applied. Meaningful conversations need to happen and concerns should not be dismissed.

Can contractors with public sector engagements and who are in scope (deemed employment) for IR35 purposes be furloughed?

Contractors working for public sector organisations who are deemed employees for IR35 purposes may be eligible to be furloughed provided they are paid via PAYE. In this scenario the agreement to furlough would be made between the contractor’s personal service company (PSC) and the fee payer (usually the agency). The parties would agree that the contractor will carry out no work for the public sector organisation while furloughed and the fee payer would apply for the grant.

At the moment the guidance states that in order to be eligible a claim for furlough must have to have been submitted by 31 July 2020 for a period of 3 weeks between 1 March and 30 June 2020.

Is there a time limit on making an insurance claim?

All policies will impose a stringent obligation, often with time limits, for you to notify insurers of circumstances that may give rise to a potential claim under the policy and non-compliance may well negate your cover. If therefore you have potential cover under your policy you must make a precautionary notification to Insurers as soon as possible.

Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?

The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.

The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.

The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:

  • Amending the contract requirements
  • Varying timings of deliveries
  • Relaxing KPIs or service levels
  • Extending time for performance (e.g. revising a contract delivery plan), and/or
  • Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).

These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.

A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.

If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.

 

 

Preparing for April 2021 – what do you need to do?
  • Audit
    • Identify your off-payroll contractors
    • Determine the status of off-payroll contractors
      • CEST – HMRC employment status checker for tax purposes
  • Communication – liaise with affected workforce
  • Contracts – get them compliant
  • Consider the Ward Hadaway toolkit