How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

Related FAQs

Can I switch an existing loan facility onto the CBILS scheme?

If a business has been provided with a loan from 23 March on commercial terms, providing the borrower meets the CBILS eligibility criteria, lenders have been asked to bring these facilities onto CBILS wherever possible (e.g. where the lender is accredited to offer the same facility through CBILS) and changes retrospectively applied as necessary. Please contact us if this applies to you and we can review facilities and advise upon the potential changes that may be made retrospectively to the benefit of the business.

What do I do if I have been endorsed for a Global Talent, Start-up or Innovator visa but my endorsement is due to expire?

Endorsing bodies are still processing applications for these visa types and endorsements are still being issued. You usually have to apply for your visa within 3 months of receipt of your endorsement. In most cases you will still be able to submit your application online within this timeframe however it will not be completed as visa application centres across the world are closed. If you cannot apply because you haven’t been able to travel and your endorsement has expired, you may still be eligible for a visa. You should make your application as planned and UKVI will consider all applications on a case by case basis.

Who is responsible for arranging the remote hearing in COP matters?

Where one or more of the parties is represented, responsibility for making the arrangements for the remote hearing will fall on either the applicant or the first represented party. If no party is legally represented, the court office will contact the parties to explain that the hearing will be held by telephone conference and will send them instructions on how this is to be achieved.

All remote hearings must be recorded. The responsibility for arranging the recording will be addressed on a case by case basis.

I have trespassers occupying my land. Can I evict them?

On 18 April 2020, it was announced that an exception to the current stay in possession proceedings and ban on all evictions has been made to allow possession orders to be made against trespassers.

This means land owners can take action to remove unauthorised persons occupying their land. Trespassers include: squatters; travellers; failed successors of secure tenancies; and licensees whose licences have been terminated.

Further, the automatic stay to possession proceedings currently imposed no longer applies to applications for interim possession orders meaning any persons found to be “squatting” on land without permission may again be subject to an order requiring them to leave your premises within 24 hours of service of that order.

Given the recent decline in financial performance, the business is now in breach of its covenants with the bank. Should we be concerned?

That will depend on the terms of your facility and the stance taken by your bank.

Banking facilities often place obligations on businesses to stick to certain financial criteria. For example, an obligation to keep turnover or profit above certain levels or a commitment to keep the bank’s exposure within an agreed percentage of the value of the company’s assets (known as loan to value ratio).

The consequences of breaching those covenants will depend on the terms of your facility, but normally this amounts to an event of default. Events of default can result in the loan (or whatever form the facility takes) becoming repayable and could give the bank certain powers to take action to recover the money that they are owed.

Whether the bank will take action during these unprecedented times is another matter, particularly given the extent of support being offered to businesses via mainstream lenders and the political desire to keep viable businesses up and running. Lenders themselves will no doubt wish to remain supportive where possible. The underlying performance of the business (and whether but for the effects of Covid-19 it would have been in a healthy financial position), the relationship you have with the bank and your history with them will no doubt be relevant to the approach taken by the bank. However, early engagement with your bank (as well as other key stakeholders in the business) will be important.