How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

Related FAQs

What has been the response from the Competition and Markets Authority (CMA)?

The CMA is the government body that is responsible for protecting consumers from unfair trading practices. It has announced programme of work to investigate reports of businesses failing to respect cancellation rights during the Coronavirus pandemic.

Based on the complaints received by them from consumers, the CMA has identified three sectors of particular concern:

  • Weddings and private events
  • Holiday accommodation
  • Nurseries and childcare providers

The CMA has expressed concern about the number of complaints that it has received about businesses seeking to retain deposits for cancelled events, undue restrictions being placed on use of vouchers provided for cancelled bookings, and payments being demanded to hold open nursery places.

The CMA has said it will prioritise investigation of these sectors, and then move on to other sectors.

I don’t live in the same home as my child’s other parent. Can my child move between each house?

If you are separated from your child’s other parent, government guidance about self-isolation and social distancing may have an impact on the contact arrangements that are in place and give rise to disagreements about spending time with the other parent, travelling arrangements and whether the child should continue to go to school, where one of the parents is a key worker and a school place is available.

The government has issued guidance which makes it clear that where parents do not live in the same household, children under the age of 18 can be moved between their parents’ homes.

Cafcass has also issued guidance which states that, “unless there are justified medical/self-isolation issues – or some future nationally issued guidance or expectation associated with leaving the house in your area – children should maintain their usual routine of spending time with each of their parents. If there is a Child Arrangements Order in place this should be complied with unless to do so would put your child, or others, at risk”.  The guidance from Cafcass be accessed here.  https://mcusercontent.com/2750134472ba930f1bc0fddcd/files/987e77d6-0827-470c-9447-acc61404f465/CAFCASS_Covid19_advice_for_familes_20.pdf

Can I switch an existing loan facility onto the CBILS scheme?

If a business has been provided with a loan from 23 March on commercial terms, providing the borrower meets the CBILS eligibility criteria, lenders have been asked to bring these facilities onto CBILS wherever possible (e.g. where the lender is accredited to offer the same facility through CBILS) and changes retrospectively applied as necessary. Please contact us if this applies to you and we can review facilities and advise upon the potential changes that may be made retrospectively to the benefit of the business.

What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

Can agency workers be furloughed?

Yes, if they are paid via PAYE. This includes agency workers engaged under umbrella companies.

The furlough should be agreed between the agency (the employer) and the worker and documented in accordance with the guidance. It is recommended that the decision to furlough is discussed with end user clients. Just like other employees, agency workers cannot perform work through or on behalf of the agency while furloughed. This includes work for the client.

For agency staff working under umbrella companies, it is for the umbrella company and the agency worker to agree on furloughing the worker.