How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

Related FAQs

Can I use flexible furlough to utilise an employee's holiday entitlement?

Employees are generally permitted to take holidays during furlough. However, Government guidance has been updated to state that “Employees should not be placed on furlough for a period simply because they are on holiday for that period.” If a period of furlough happens to coincide with an employee’s holiday then you should ensure that there are business grounds to support furlough being used in that instance so that it isn’t just being used as a means to fund holiday utilisation.

What are the responsibilities of employers under the coronavirus Test and Trace scheme?

The Government has produced workplace guidance for employers, setting out 2 key messages for employers:

  • Continue to make workplaces as safe as possible; and
  • Encourage workers to heed any notifications to self-isolate and to support them while they are require to isolate

Government guidance can be accessed here: How it works (an overview) and Workplace guidance for employers.

Flexible working

Many employees require flexible working now more than ever. That could be reduced hours, working from home, reduced days, etc. Be careful to act fairly when considering these requests as they can be a discrimination claim in the waiting.

A flexible working request is a request for a permanent change to the contract of employment however to encourage a greater take up during this difficult time, you can agree this on a temporary basis.

Who is eligible for CBILS?

To be eligible for CBILS, the British Business Bank has confirmed that businesses should be able to answer YES to the following points:

  • Your application must be for business purposes
  • You must be a UK-based SME with an annual turnover of up to £45m. This includes sole traders, freelances, body corporates, limited partnerships and limited liability partnerships. For sole traders to be eligible it is expected that sole traders will need to have a business account with its funders and not be operating via a personal account
  • Your business must generate more than 50% of its turnover from trading activity
  • Your CBILS-backed facility will be used to support primarily trading in the UK
  • You wish to borrow up to a maximum of £5m.

Businesses meeting these criteria from all sectors can apply save for Banks, Building Societies, Insurers and Reinsurers (but not insurance brokers), the public sector including state-funded primary and secondary schools, employer, professional, religious or political membership organisation or trade unions which are not eligible.

Your borrowing proposals must be considered viable by the relevant lender under normal circumstances aside from the Covid-19 outbreak, and the lender believes the provision of finance will enable the business to trade out of any short-to-medium term difficulty. Lending decisions are delegated to the accredited lenders and lenders will need further information to confirm eligibility.

The eligibility criteria for CBILS does not require lenders to take into account other forms of Government support that SME’s may already be benefiting from, most notably business rate relief.

We understand that ownership structure is not taken into account when confirming eligibility and that businesses back by a PE funder or a subsidiary of an overseas entity can be eligible if it meets the other criteria.

An update on eligibility – 3 April 2020

Previously, for facilities above £250,000, the lender must establish a lack or absence of security prior to businesses using the Scheme. The requirement for insufficient collateral has been removed allowing those SMEs who are considered to have sufficient collateral to access the Scheme. We would expect that where security is available, a lender will seek to take security over the relevant assets.

What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases

The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:

  • The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
  • How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
  • Whether the definition of higher risk buildings is correct, or will require some refinement.

The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.