How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
Related FAQs
Some examples of the key questions to ask include:
- Is there still a viable underlying business that is likely to continue beyond the current crisis?
- What does the revised short to medium cash flow look like and will the company continue to be able to pay its liabilities?
- Does the company have the support of all of its stakeholders – lenders, shareholders, customers, suppliers and banks – even though the business might be in breach of its own obligations?
- What measures could (and should) the board put in place to protect creditors, including making sure that exposure to creditors (both collectively and individually) is not increased, assets are not sold at less than value and no creditor is treated more favourably than another?
- Is there still a reasonable prospect of the business avoiding liquidation or administration?
The key question is always whether accepting the money is in the best interests of creditors as a whole bearing in mind that accepting Government support and continuing to trade might increase the company’s overall liabilities. Directors should be mindful that if the business fails, their decisions during this critical time may be scrutinised and it is therefore important that directors have up-to-date financial information and projections to form the basis of any decisions, take stock, get the right advice and document the decisions that are taken.
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.
There is not a magic number. It depends on the nature of the organisation, the work carried out, the organisational structure, the geographical spread, working patterns and conditions. We would give specific advice personalised to the organisation and taking all these and other factors in to consideration. There is no such things as too many MHFAs!
Some employers falling into the third group of organisations described above could understandably feel aggrieved that on the first reading of the guidance they are not able to furlough employees and rely on the Government scheme. Many publicly funded organisations that are not public sector employers, receive a package of public funding with little expectation on how that funding is used or applied, other than broadly for it to be used in providing the services it is contracted to deliver. Also, several publicly funded organisations have many different income streams and the element of funding that is received from the public purse can be only an element of their operating costs.
Unfortunately there is still no clear guidance on when employers falling into the third category identified above can use the scheme. The only reference in the guidance on this states that where organisations are not “primarily funded” from the public purse and whose staff cannot be redeployed to assist with the coronavirus response, the scheme might be appropriate to be used for some staff. This seems to suggest that where an employing organisation is not wholly or mainly funded by public funding and staff cannot be redeployed to work in areas in the effort to combat coronavirus, then it would be appropriate for the employer to access the scheme.
If considering applying for grants under the scheme a sensible approach would be to look at the combined total of your public funding and payments under the scheme and make sure it will not represent more than 100% of the level of total income you would have expected to receive during this period in a non-Covid scenario.
Local Authorities are expected to maintain support to suppliers and this should be considered:
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.