How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
Related FAQs
We have teamed up with Scaleup North East to help companies impacted by the coronavirus outbreak plan how to get back to business.
Our specialist lawyers will provide a free “diagnostic” call with eligible businesses across the NE, exploring challenges they are facing in the aftermath of the lockdown, and identify specific steps to survive, and then thrive, in these challenging times and beyond.
Through the collaboration with Scaleup North East, eligible North East-based SMEs are then able to apply for up to 40% funding towards up to £4,000 of legal advice.
These might include:
- Employment issues, such as dealing with a phased return to work
- Measures to support cash-flow, such as amendment to terms of trading and debt collection procedures
- Renegotiations and amendments to contracts, and other advice about contracts with suppliers and customers to deal with consequences of Covid-19
- Managing property costs – review of leases, advice on break clauses and formalisation of any revised arrangements recently put in place with landlords/tenants
- Health and safety implications of return to work and social distancing
Find out more on our website or contact partner Damien Charlton. If you are not eligible because of location but are interested in the free “diagnostic”, please contact us.
- Keep in touch. If contact is poor, workers can feel disconnected, isolated or abandoned. This can adversely affect stress levels and mental health – especially in the current crisis when everyone is feeling more anxious.
- Think about the use of laptops/devices (DSE) at home. Provide a basic form of risk assessment for self-completion.
- Remind workers of simple steps to reduce the risks from display screen work:
- take regular breaks (at least 5 minutes every hour) or change activity
- avoid awkward, static postures by regularly changing position
- get up and move or do stretching exercises
- avoid eye fatigue by changing focus or blinking from time to time
The reality of these unprecedented times is that enforcement of health and safety legislation by the HSE (particularly through the criminal courts) in relation to Covid-19 is an extremely unlikely outcome.
On Wednesday 8 July 2020 as part of a summer ‘mini-budget’, Rishi Sunak delivered the Government’s response to the threat to millions of jobs due to the existing furlough arrangements being wound down from August 2020 until it planned to close at the end of October 2020. In a wide-ranging speech to Parliament, the Chancellor announced a number of schemes to look to protect jobs beyond October 2020, in particular in certain sectors and for those aged 18-24. As the Government releases further information over the coming days and weeks, we will add to these FAQs.
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.