How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
Related FAQs
Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.
New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.
For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.
Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.
For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.
The CMA is the government body that is responsible for protecting consumers from unfair trading practices. It has announced programme of work to investigate reports of businesses failing to respect cancellation rights during the Coronavirus pandemic.
Based on the complaints received by them from consumers, the CMA has identified three sectors of particular concern:
- Weddings and private events
- Holiday accommodation
- Nurseries and childcare providers
The CMA has expressed concern about the number of complaints that it has received about businesses seeking to retain deposits for cancelled events, undue restrictions being placed on use of vouchers provided for cancelled bookings, and payments being demanded to hold open nursery places.
The CMA has said it will prioritise investigation of these sectors, and then move on to other sectors.
If an employee is required under government guidance to wear a face mask during the course of their employment and there is no applicable exemption, any fine issued would be payable by the employee, not the employer.
The Government will provide the lender with a partial guarantee (80%) against the outstanding facility balance, subject to an overall cap per lender. Note, the Government guarantee is to the lender only, the borrower will always remain 100% liable for the debt.
We understand that will make an initial claim for recovery against the borrower and will, once its normal recovery procedures have been completed, claim against the Government guarantee.
Physical bundles may not be regarded as safe for public health and there are obvious difficulties in providing them with the current restrictions in place. Electronic bundles should be provided in PDF format, preferably paginated, indexed and bookmarked. The bundles should only contain documents and authorities that are essential to the issues required to be decided at the remote hearing and should be filed with the court by email.