How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
Related FAQs
Mortuaries are a sui generis use, unless ancillary to some other use of land, a hospital for example.
Sui generis uses are not within any Use Class. Consequently planning permission is required for the:
- Change in the use to a sui generis use
- Subsequently for the change in the use to an alternative use, whether that be another sui generis use or a use within a Use Class
Acknowledging the above, if the scale of the use is above de minimis, planning permission is likely to be required to change the use of a warehouse or factory unit into a temporary mortuary.
Should planning control be breached, a local planning authority must decide whether to take enforcement action or not. That enforcement is discretionary was recently reiterated in a Ministerial Statement issued on 13 March 2020 a link to which is below.
Depending on the form of the enforcement action, there could be a right of appeal.
The law says that if after assessing a risk and considering all the control measures available to you, you cannot undertake a task safely – then you should not undertake the task.
If that means taking BAME workers out of higher risk frontline work, that is what will have to be done.
Beware of workers saying “we’ll accept the risk” – it does not protect you against regulatory/enforcement action or civil claims.
There are several options that can be used at this time to try and settle disputes. If it is not possible to settle a dispute via direct discussions between the parties then some form of Alternative Dispute Resolution (“ADR”) might be appropriate. Mediation is the most popular form of ADR. Most people’s perception of mediation is that it needs to be in person but that does not have to be the case.
Mediation can take place online or on the telephone. Most, if not all, ADR providers remain open for business and are quickly changing their business model to ensure that mediations can still take place. Mediation can be arranged at reasonably short notice and certainly so far as the online model is concerned, it mirrors the process that is adopted when parties appear in person. Online mediation allows for joint sessions with the mediator to take place and also for the parties to break out into their respective rooms for private discussions. If a dispute settles at mediation – and the vast majority do – then the agreement reached between the parties is binding and can be enforced.
A group of senior former judges and legal academics have now called for an acceleration in the use of ADR in light of the current circumstances. They have stated that courts should promote “and where appropriate require” the use of ADR. Mediation has particularly seen an increase in growth at this time.
ADR normally results in a quicker outcome than if the matter proceeds in the courts. Due to its conciliatory nature it is a very useful process where parties continue to be in a trading relationship. Contracting parties should also consider building ADR into dispute resolution clauses in their contracts so that in the event there is a dispute the focus is on resolving the dispute as soon as possible before it escalates into litigation.”
There have always been ways for public bodies to assist without being required to notify these for approval. These continue to be available during the financial crisis, and are likely to be increasingly useful for measures which need to be introduced quickly. The measures include:
Those where it is possible to conclude that there is no effect on trade between Member States – for example, measures which are likely to have only a limited local effect. The European Commission has concluded, for example, that measures to assist locally-focused cultural activity can be assumed to have no effect on inter-State trade.
Those where it is possible to conclude that the State is acting in a way consistent with a commercial operator (the so-called Market Economy Operator Principle) – particular care will need to be taken in the context of current economic conditions to ensure that it can reasonably be asserted that a commercial operator would act in the same way as the public body.
Measures under the General Block Exemption Regulation – this legislation allows various types of aid, or aid schemes, to be employed.
Examples include aid for SMEs, aid for research and development, aid for local infrastructure and aid to ports and airports.
De Minimis Measures – Member States are permitted to grant small amounts of aid to undertakings over three fiscal years (the current year and the previous two years). This allows undertakings to receive up to €200,000 (or €500,000 where they are providing public services).
CMA guidance suggests that it will not take enforcement action in respect of agreements which:
- Are appropriate and necessary to avoid a shortage, or ensure security, of supply
- Are clearly in the public interest
- Contribute to the benefit or wellbeing of consumers
- Deal with critical issues that arise as a result of the Covid-19 pandemic
- Last no longer than is necessary to deal with these critical issues