How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

Related FAQs

Can I require my staff to inform me should their circumstances be such that they need to self-isolate?

Yes.

Workers (and agency workers) who are aware of the requirement to self-isolate and are due to work during their isolation period at a place other than their designated place (see below) must, as soon as reasonably practicable and in any event before they are next due to start work within the isolation period, tell their employer that they are self-isolating, and set out the start and end dates of their isolation period.

Clear communication to all workers about their obligation to do this is strongly recommended.

Can I wait until April to carry out assessments?

We don’t recommend this. Status determination statements must be issued before 6 April 2021 for current engagements and the appropriate deductions are to be made on payments for services carried out on or after 6 April 2021.

I’m a landlord. How do I comply with Regulation 36 of the Gas Safety Regulations 1998 during the coronavirus outbreak?

Under their obligations arising from Regulation 36 of the Gas Safety (Installation and Use) Regulations 1998, landlords must service domestic gas appliances on an annual basis and provide tenants with a record of the service within 28 days of that service. Failure to comply can result in prosecution by the Health and Safety Executive (HSE) or downgrading by the Regulator.

We know how important this is. But how can you comply with your obligations during the Covid-19 epidemic?

The latest restrictions on leaving the home, currently allow registered gas engineers to undertake essential work, whilst taking the appropriate precautions advised to avoid spreading or contracting the virus in a new setting.

Capability issues

All organisations have underperformers. Capability is a potentially fair reason to dismiss and is separate to any redundancy procedures.

Generally, capability falls into either absences through illness or underperformance in the role. Those who are absent through sickness can be furloughed, but when furlough comes to an end they will need to go back onto sickness. If you are looking to tackle absence then you need to tackle long term and short term absence in a different way.

Long term absence: You need to establish whether the employee is able to return to work (with or without reasonable adjustments) in the medium term. This requires medical opinion and be careful of disability issues. Reasonable adjustments are likely to be important.

Short term absence: You will need to demonstrate that you have fair absence triggers in place and there is normally be a 3 stage procedure: warning and final warning followed by dismissal on notice. Each stage needs a fair procedure, with written information, a fair hearing and the opportunity to appeal. Be careful of disability issues.

As for underperformance: To tackle this, you will need to have clear SMART objectives in place and evidence of the employee failing to meet these. There would then normally be a 3 stage procedure: warning and final warning followed by dismissal on notice. Each stage needs a fair procedure, with written information, a fair hearing and the opportunity to appeal.

What other factors may be considered?
  • Integration:
    • Is the individual held out as being employed by the business by having a company email address, uniform, how would they introduce themselves to customers?
  • Exclusivity:
    • Is the contractor restricted from working for other organisations without the consent of the end user client?
  • Length of engagement:
    • Is the contractor engaged to work on a specific project for a defined period? Or are they engaged for an indefinite period with no reference to a specific task or project?
  • Pay:
    • Are there regular fixed payments or is payment on completion of specific task or commission based? Is the contractor entitled to benefits or bonuses?
  • Facilities:
    • Does the contractor provide their own equipment and materials to provide the services?
  • Financial risk:
    • Is the contractor personally responsible for any loss arising from their work in performing the services? Will they have to rectify unsatisfactory work at their own time and expense? Will they have the opportunity to profit from the success of a project?