How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
Related FAQs
Hopefully, further guidance will provide additional clarification on this, but it is difficult to see how a charity whose operations have been significantly curtailed because of the Covid-19 restrictions, cannot furlough employees and access the scheme, in particular where they have several different income streams. For example if a charity’s retail or fundraising operations have been significantly curtailed due to the restrictions, then it would appear unfair for it not to able to rely on the furlough scheme to assist in the funding of the employment costs associated with this part of the charity.
However, it might be prudent, where there are services that are publicly funded and employees working within those services cannot undertake their normal work, to consider if they can do different roles to work on Covid-19 activities. If there is no such work available then the guidance does appear to allow the furloughing of employees and such organisations to access the scheme.
In our experience, the funding streams and work undertaken by the organisations that could fall into the third category identified above can be exceptionally diverse and we would strongly recommend that you take advice before making such decisions about furloughing employees.
Employers had the ability to furlough extremely vulnerable employees who needed to shield.
If your employee is on sick leave or self-isolating as a result of Coronavirus, including as a result of track and trace, they’ll be able to get Statutory Sick Pay, subject to other eligibility conditions applying.
There is no special exemption for them, so they would need to meet the usual requirements to be placed on Flexible Furlough after 1 July 2020. i.e. They had to have been placed on furlough for at least 3 weeks before 1 July. Otherwise, they could not be furloughed.
If you do not have a justifiable reason for insisting that your employees have the vaccine (see FAQ above) your employee could resign and bring a claim of constructive unfair dismissal if they have more than 2 years’ continuous employment. This would be on the basis that you have breached trust and confidence.
If the vaccine includes pig gelatine (as many do), and the employee refuses on religious or because they are vegan, you may face a claim for discrimination under the Equality Act 2010.
Yes, but the Courts have been temporarily restructured into three categories:
- Open courts (open for business including vital in person hearings)
- Staffed courts (for video and telephone hearings)
- Suspended courts (no hearings of any kind)
These changes have been effective from Monday 30 March 2020.
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.