Skip to content

How do I guard against contractor insolvency in the construction industry?

It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved.   To be in the best possible position, it is worth considering the following at the outset of any project:

  • Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
  • Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
  • Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
  • Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
  • Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
  • Project bank accounts and escrow accounts can also provide some further assurances for the parties involved

Related FAQs

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

What happens if I need to sign a new commercial lease in the future?

The outbreak is certainly going to have an impact on new lease negotiations.

Undoubtedly many transactions will be put on hold or indeed stop entirely. Where matters are ongoing, tenants may well look to strengthen rent suspension provision.

It is also possible that tenants and their representatives will also now seek to include termination rights for unseen events. In this regard, the concept of force majeure may start to appear more often in leases.

In both of the examples above, such attempts are not likely to be well received from landlords who will undoubtedly suggest that tenants ensure that their business interruption insurance policies are robust enough to protect the tenant in the event of any future pandemic events.

Another approach tenants might adopt going forwards in negotiations for a new lease (or indeed seeking to vary existing leases), is to move away from the traditional market rent model to a turnover rent arrangement. This will offer some protection going forward if trading conditions deteriorate, but again getting institutional landlords to agree such an approach may prove difficult.

Can employees who are self-isolating or on sick leave be placed on Flexible Furlough?

Employers had the ability to furlough extremely vulnerable employees who needed to shield.

If your employee is on sick leave or self-isolating as a result of Coronavirus, including as a result of track and trace, they’ll be able to get Statutory Sick Pay, subject to other eligibility conditions applying.

There is no special exemption for them, so they would need to meet the usual requirements to be placed on Flexible Furlough after 1 July 2020. i.e. They had to have been placed on furlough for at least 3 weeks before 1 July. Otherwise, they could not be furloughed.

How have competition law rules been relaxed in the light of the coronavirus outbreak?

The Competition and Markets Authority (CMA) has issued a number of guidance documents about the application of competition law rules during the coronavirus outbreak. In general, the competition law rules are being relaxed in very specific circumstances.

What is classed as a good ratio of MHFA to staff numbers?

There is not a magic number. It depends on the nature of the organisation, the work carried out, the organisational structure, the geographical spread, working patterns and conditions. We would give specific advice personalised to the organisation and taking all these and other factors in to consideration. There is no such things as too many MHFAs!