Skip to content

How do I guard against contractor insolvency in the construction industry?

It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved.   To be in the best possible position, it is worth considering the following at the outset of any project:

  • Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
  • Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
  • Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
  • Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
  • Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
  • Project bank accounts and escrow accounts can also provide some further assurances for the parties involved

Related FAQs

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

What is the claim period for Flexible Furlough?

Employers had until 31 July 2020 to make any claims for claim periods up to 30 June 2020. That was the end of the old scheme.

From 1 July 2020, claim periods must start and end within the same calendar month and must be for at least 7 days unless you are claiming for the first few days or the last few days in a month.

You can only claim for a period of fewer than 7 days if the period you are claiming for includes either the first or last day of the calendar month, and you have already claimed for the period ending immediately before it.

For example, if an employee is furloughed for 7 days spanning a month. You can claim the last 3 in one month, and 4 from the next.

The crucial point is that you cannot make claims that cross calendar months.

The first time that you could make a claim for days in July 2020 was 1 July 2020. You could not claim for periods in July 2020 before this point.

Would it be appropriate to suspend someone who refuses to restrict their duties?

Suspension should always be a last resort and not a knee jerk reaction. We would not advise suspension unless a the above steps around the risk assessment have been undertaken. Depending on your local policies, suspension could then be an option on the basis that their health and safety and the health and safety of others are put at risk by their actions.

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

How do I remain compliant and cover any risk?

Data on properties, and people, has never been more important.

Given that compliance is at risk here, such a decision must be made by the Board to ensure good governance. Board approval should be sought and recorded for the approach the organisation is taking.

It is essential that you continue to record your data on compliance and report to your board at all times, and that there is a clear audit trail for issues with access, and if appropriate to the Regulator. Access issues as a result of self-isolation should be readily identifiable.

Operatives need to be provided with the tools to operate in as safe a way as possible:

  • Checklist of questions to ascertain occupant’s current health
  • Protective equipment (masks, gloves, over clothing)

The Gas Safe website is a useful resource for updates: https://www.gassaferegister.co.uk/help-and-advice/covid-19-advice-and-guidance/