How do I remain compliant and cover any risk?
Data on properties, and people, has never been more important.
Given that compliance is at risk here, such a decision must be made by the Board to ensure good governance. Board approval should be sought and recorded for the approach the organisation is taking.
It is essential that you continue to record your data on compliance and report to your board at all times, and that there is a clear audit trail for issues with access, and if appropriate to the Regulator. Access issues as a result of self-isolation should be readily identifiable.
Operatives need to be provided with the tools to operate in as safe a way as possible:
- Checklist of questions to ascertain occupant’s current health
- Protective equipment (masks, gloves, over clothing)
The Gas Safe website is a useful resource for updates: https://www.gassaferegister.co.uk/help-and-advice/covid-19-advice-and-guidance/
Related FAQs
Following our webinars on all aspects of furlough and alternatives to redundancy, it is an unfortunate fact that a number of organisations are likely, sooner or later, to be forced to make some employees redundant.
Our employment experts Jamie Gamble and Roisin Patton take you through the key aspects of conducting cost reduction redundancies, but with a focus on aspects that make this exercise different this time. For instance:
- How are you going to conduct sensitive meetings remotely?
- How are you going to ensure that dismissing any furloughed staff will be fair? You may have furloughed at speed, but redundancy selection criteria cannot be defined by such factors.
- Will you use this time to review your selection criteria if you already have some in place?
- How will you deal with individuals who are shielding, have child care issues or are pregnant?
- How do you ensure this is all done sensitively and fairly for those roles that are being made redundant, but also for those who continue to work for you but are still isolated on furlough or working from home?
- And what are the risks for making redundancies in this “new normal”?
Although you may be perfectly familiar with redundancy exercises these are far from normal times and it is therefore worth pausing to think about the impact that Covid-19 might have and what else you need to think about or plan for.
The webinar was recorded on Thursday 2nd July.
The immediate impact is accounting for payroll purposes for the additional cost of 13.8% employers NIC’s and 0.5% apprenticeship levy on top of the payment to the contactor’s PSC.
Secondary NIC’s cannot be recovered from payments due to employees and the same applies under the new IR35 regime. However, new terms can be agreed with reduced level of fees to reflect this additional cost.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
If a tenant continues to refuse to take heed of the government’s social-distancing guidelines, for example by inviting large groups of people who do not reside there to their property, it can constitute a nuisance. One housing association successfully applied for an injunction. The injunction ordered by the Court stipulated that no persons, other than the children of the tenant, are to attend the property until the current social-distancing restrictions are lifted by the government.
A representative of the housing association highlighted the need for the current guidelines to be followed and the need for housing providers to ensure that all residents living in their communities are kept safe during this time of ‘unprecedented risk’.
This case demonstrates that flouting of the current restrictions is likely to be considered anti-social in the eyes of the courts – a point which all housing providers should bear in mind during this period. Further, it highlights the availability of an alternative remedy to the issuing of possession proceedings (in light of the government’s moratorium on evictions) to deal with anti-social behaviour during the next three months, Covid-19 related or not.