Skip to content

How do I remain compliant and cover any risk?

Data on properties, and people, has never been more important.

Given that compliance is at risk here, such a decision must be made by the Board to ensure good governance. Board approval should be sought and recorded for the approach the organisation is taking.

It is essential that you continue to record your data on compliance and report to your board at all times, and that there is a clear audit trail for issues with access, and if appropriate to the Regulator. Access issues as a result of self-isolation should be readily identifiable.

Operatives need to be provided with the tools to operate in as safe a way as possible:

  • Checklist of questions to ascertain occupant’s current health
  • Protective equipment (masks, gloves, over clothing)

The Gas Safe website is a useful resource for updates: https://www.gassaferegister.co.uk/help-and-advice/covid-19-advice-and-guidance/

Related FAQs

How do I guard against contractor insolvency in the construction industry?

It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved.   To be in the best possible position, it is worth considering the following at the outset of any project:

  • Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
  • Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
  • Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
  • Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
  • Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
  • Project bank accounts and escrow accounts can also provide some further assurances for the parties involved
Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

I am dealing with an estate where the bank has sent me an indemnity to obtain the funds. Will the bank accept my signature without it being witnessed by my solicitor?

If you have obtained a Grant of Probate or Grant of Letters of Administration there should be no need to complete an indemnity, merely an account closure form. If however you have not yet obtained a Grant but the bank is willing to release funds then they will generally require an indemnity to be executed. Several banks and building societies including Barclays, Lloyds, HSBC and Santander have signed up to the British Banking Association’s voluntary Bereavement Principles, one of which is to support the bereaved according to their personal needs and work with you to resolve everything as quickly as possible.

If the indemnity requires a solicitor to act as a witness, you should contact the bank to see what they are willing to do to get around the problem, given the current situation.

How does a Public Body amend its contracts to enable continued payment to contractors?

The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.

For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf

What are the NICE protocols around a patient’s ongoing treatment whilst in critical care during the pandemic?
  • Start critical care treatment with a clear plan of how the treatment will address the diagnosis and lead to agreed outcomes.
  • Review critical care treatment regularly and when the patient’s clinical condition changes.
  • Stop critical care treatment when it is no longer considered able to achieve the desired outcomes. Record the decision and the discussion with family, carers and the patient (if possible).