Skip to content

How does a Public Body amend its contracts to enable continued payment to contractors?

The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.

For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf

Related FAQs

Which agreements will qualify for exemption?

There are four criteria which must be satisfied if an agreement is to be considered exempt:

  • It must improve production or distribution, or promoting technical or economic progress – the guidance suggests that cooperation ensuring essential goods and services can be made available to the public, or an important sub-set of the public such as key workers, will satisfy this criterion.
  • It must allow consumers a fair share of the resulting benefit – the guidance suggests this will be the case where the action prevents or reduces shortages.
  • It must not impose on the undertakings concerned restrictions which are not indispensable to the attainment of the above benefits – the guidance suggests this will be the case where the cooperation is the only reasonable option due to the urgency of the crisis and where the cooperation is temporary in nature.
  • It must not afford the undertakings concerned the possibility of eliminating competition – therefore the parties must endeavour to retain competition in respect of the products (in particular price competition).
How do I make arrangements for end point assessments for apprentices?

Arrangements for end point assessments can be modified or rescheduled. End point assessment organisations should engage with External Quality Assurance Providers to agree arrangements for the end point assessments where face-to-face assessments are being modified. Where rescheduling is required due to Covid-19 issues and there is a specified time limit for the ESA post gateway, a further pause of 12 weeks is allowable. This should be recorded by the training provider in the ILR.

How often do MHFA qualifications need updating?

The recommendation is every 3 years, however it is recommended that MHFAs receive regular ongoing training and support.

Is it possible to proceed with a hearing in person for any COP matters?

Any hearings attended in person will need to be approved by the judge hearing the matter, if necessary, in consultation with the regional lead COP judge. Such requests are highly unlikely to be granted during COVID-19 unless there is a genuine urgency. However, it is deemed to be appropriate matters are likely to be adjourned on the basis that a remote hearing is not possible and a hearing in person is not safe or possible.

What actions and measures should be avoided?

The CMA is particularly concerned about certain activities, its guidance highlights:

  • Exchange of commercially sensitive information where this is not necessary in response to the crisis
  • Collaboration which unfairly excludes third parties
  • Abuse of a dominant position (including a dominant position held as a result of the crisis) – particularly to charge excessive prices
  • Seeking to maintain prices or prevent reductions in prices
  • Cooperation going beyond what is necessary to respond to the crisis in the interests of consumers