Skip to content

How does a Public Body amend its contracts to enable continued payment to contractors?

The latest Cabinet Office guidance published Monday 6 April 2020 titled ‘Procurement Policy Note PPN 02/20: Additional guidance. FAQs and model terms for construction’ provides model deeds of variation for JCT and NEC3 contracts to provide for such payments to be made. As the Cabinet Office guidance states, legal advice is likely to be required to make sure that the model variations work with your specific contracts. Please contact one of our construction specialists if you need advice and assistance.

For a copy of the guidance note click here: https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/878338/PPN_02_20._Additional_guidance__FAQS_and_model_terms_for_construction.pdf

Related FAQs

How is an establishment defined?

The definition of a relevant establishment is a question of fact for an Employment Tribunal. Guidance from case law says that ‘establishment’ should be interpreted very broadly (so as to avoid employers escaping the need to collectively consult), and may consist of:

  • A distinct entity
  • With a certain degree of permanence and stability
  • Which is assigned to perform one or more tasks
  • Which has a workforce, technical means and a certain organisational structure to allow it to do so

However, there is no need for it to have the following:

  • Legal, economic, financial, administrative or technological autonomy
  • A management which can independently effect collective redundancies
  • Geographical separation from the other units and facilities of the undertaking
What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
What should I do if I have a hearing scheduled in the COP?

Parties are encouraged to review upcoming matters to assess the viability for there to be any agreement which can be reached in relation to the issues in dispute or to consider whether the case needs to proceed to a remote hearing. If directions or issues can be agreed between the parties, reducing the need for remote hearings, then that is the preferred option.

Who is responsible for arranging the remote hearing in COP matters?

Where one or more of the parties is represented, responsibility for making the arrangements for the remote hearing will fall on either the applicant or the first represented party. If no party is legally represented, the court office will contact the parties to explain that the hearing will be held by telephone conference and will send them instructions on how this is to be achieved.

All remote hearings must be recorded. The responsibility for arranging the recording will be addressed on a case by case basis.

What fees will I pay for a loan under CBILS?

Borrowers will not have to pay a guarantee fee. Lenders will pay a fee to access the scheme. The Government will make a Business Interruption Payment to cover the first 12 months of interest payments and any lender-levied fees, allowing smaller businesses to benefit from no upfront cost.

British Business Bank has indicated that following earlier discussions with the banking industry, some lenders indicated that they would not charge arrangement fees or early repayment charges to SMEs borrowing under the scheme. Each business should check the terms of the loans being made to ensure this is the case and what the interest rate and prepayment fees will be following the period in which the Government makes payment of these amounts.