Skip to content

How is an establishment defined?

The definition of a relevant establishment is a question of fact for an Employment Tribunal. Guidance from case law says that ‘establishment’ should be interpreted very broadly (so as to avoid employers escaping the need to collectively consult), and may consist of:

  • A distinct entity
  • With a certain degree of permanence and stability
  • Which is assigned to perform one or more tasks
  • Which has a workforce, technical means and a certain organisational structure to allow it to do so

However, there is no need for it to have the following:

  • Legal, economic, financial, administrative or technological autonomy
  • A management which can independently effect collective redundancies
  • Geographical separation from the other units and facilities of the undertaking

Related FAQs

Do all contractors have to be assessed?

Individual contractors who are not operating via an intermediary (eg sole traders) do not need to be assessed under IR35. However, you will always have the risk with those individuals that there is no intermediary – therefore if their tax status is wrong, HMRC are very likely to consider that responsibility for this would fall on the hiring company in any event.

What challenges to planning permission does the current lockdown situation present?
  • Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
  • Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
  • Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
  • The ability to get people on site to undertake material operations

In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.

If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.

What does this mean for my business?

The guidance is helpful and is likely to be useful to businesses as they seek to respond to the crisis and to restart their business activities as lockdown is eased. However, there remain outstanding questions. For example, can collaboration to prevent widespread insolvencies be viewed as in the interest of consumers? Businesses need to remain aware of the extremely high stakes involved in relation to competition law. Businesses contemplating collaboration with competitors should take legal advice before doing so.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

What does the new Chief Coroner guidance cover?

This guidance from the Chief Coroner applies to reports of death and coroner investigations in England and Wales. It is to assist coroners in continuing to exercise their judicial decisions independently, in accordance with the law, and during the extraordinarily pressured events being faced at present.