How long does a claim take?
There is no hard and fast rule as to how long a claim under the 1975 Act can take. If a dispute is settled early into the process then resolution can be reached in a matter of weeks or months. If, on the other hand, matters have to proceed all the way to trial then it is not unheard of for disputes under the 1975 Act to last anywhere between 12-18 months
Related FAQs
The Government has introduced new regulations, which took effect on 14 May 2020, to relax the publicity requirements in respect of planning applications.
Planning applications are usually required to be publicised by way of site notices and local newspaper notices and applications are to be made available for public inspection. The Government has recognised that these actions may not always be possible in accordance with social distancing guidelines and in order that Councils do not delay applications as a result of an inability to comply with the publicity requirements, the Government has relaxed the requirements.
A Local Planning Authority is now required to “take reasonable steps” to publicise a planning application, which may be through use of online newspapers, social media, or other electronic measures. What is considered reasonable will depend upon the circumstances of an individual application and will be proportionate to the scale and impact of the development. A large development that has previously generated significant interest will require more steps to bring the application to the attention of all of those with an interest than a householder application. The guidance emphasises the role of the publicity requirements, namely to enable those with an interest to make representations and to effectively participate in the decision making process and therefore community engagement remains key. It is recommended that the officer’s report refers to the steps taken where a Council has relied upon the temporary publicity arrangements.
The requirement to make planning applications available for public inspection has also been temporarily suspended providing that the applications are available for online inspection. In reality most LPAs already provide such an online facility. Where individuals are unable to access an application online LPAs should make alternative arrangements, for example providing information over the phone or providing a hard copy set of documents by post.
The regulations however only amend the statutory publicity requirements. In addition to these, all LPAs are required to have a Statement of Community Involvement which may provide for additional publicity requirements and the LPA will be bound by these regardless of the temporary relaxation of any statutory requirements. Where a Statement of Community Involvement does go beyond the statutory requirements, the Government guidance suggests that LPAs update these to ensure that local communities can continue to be consulted in the current climate.
The regulations are currently due to expire on 31 December 2020.
The guidance gives numerous examples of the types of performance adjustment which parties should consider. For example this includes:
- Varying deadlines (e.g. for performance or payment)
- Varying compensation (e.g. to recognise increased costs)
- Varying the nature of performance (e.g. allowing substitute goods, allowing pert delivery of services)
The guidance also encourages a reasonable approach to enforcement, which might encourage delaying issuing formal proceedings, increased use of mediation or providing more information to the other party than would be volunteered under normal circumstances.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
With another lock-down in force in England, it has been confirmed that the courts will remain open. This is different to the first lockdown in March 2020, in which the majority of courts were closed and most face to face hearings did not take place. Hopefully, this new lock-down measure will ensure that cases are still being heard at a steady rate, and there should not be a backlog for your case to be dealt with.
Lord Chancellor Robert Buckland QC MP emphasised the importance of maintaining safety during the new measures: “Our courts & tribunals continue to be an essential public service, served by essential workers and meeting Covid-secure standards endorsed by public health officials. With the use of remote hearings wherever appropriate, this vital work can and should continue.”
A large sum of £110m has been spent in recent months to make courts safe and to ensure that trials should go ahead where necessary. As a result of the expenditure, hearings can now still take place both in person, whilst adhering to the rules, as well as remotely. Your case may be heard in court if it is deemed as being “necessary in the interest of justice”.
Precautionary measures, such as social distancing, will still be in place, with Judges and magistrates ensuring that this happens.
Lord Chief Justice, Lord Burnett of Maldon commented: “The next few weeks will present difficulties in all jurisdictions. But as before judges, magistrates, staff, the legal profession and others involved in the system will meet them and ensure that the administration of justice continues to function in the public interest.”
It is absolutely critical to creating a safe workplace and to making workers feel secure.
This could include floor markings every 2m (as we’ve seen in grocery stores), stopping or limiting/staggering access to communal or common areas such as toilets and kitchens, rearranging workstations to maintain a 2 metre distance or, where this is not possible (for example in manufacturing facilities or production lines), erecting physical barriers and avoiding face to face working, encouraging the use of stairs and discouraging lift-use, designing a one-way system for entry and exit and looking at aircon/heating systems to see if any modifications are possible to prevent the spread of airborne particles. If you can increase ventilation in your workplace, it will help reduce risk.
The government has published detailed social distancing guidance for workplaces across sectors including manufacturing, retail, offices, construction and transport; it has also promised to continue to add to this.