How should contracting authorities work with PFI providers?
- Working with PFI providers to get contingency plans up to date
- If a PFI provider is struggling to achieve service delivery requirements due to Covid-19, then local arrangements should be put in place to:
- maintain unitary charge payments
- revise contract requirements/standards
moderating payment and performance regimes where appropriate.
- In any event, you may wish to review and adjust your requirements to reflect the current situation. It is possible that some requirements can be relaxed, whereas others need to be tightened. For example, there may be an increased need for cleaning and maintenance in certain areas of your PFI premises or the layout of the premises and/or room uses may have temporarily changed. With staff illness and shortage likely to be an issue, you may also wish to consider if the resource can be moved from one area to another to help maintain essential services.
- When putting local bespoke arrangements into place it is vital that:
- Contract requirements or performance standards are not relaxed to the point where health and safety are put at risk.
- It is made clear that the arrangements are temporary and that matters will return to normal as soon as the Covid-19 emergency is over. Indeed the guidance note makes clear that if assets temporarily close they should be kept in such condition that they can be immediately up and running when this emergency is over. In such instances, likely a basic level of maintenance and security will therefore be required as a minimum.
Related FAQs
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
The Government will allocate £360 million to charities providing key services and supporting vulnerable people during the crisis. £200 million of this amount will be paid to Hospices UK to be distributed to hospices to help increase capacity and give stability to the sector. The remaining amount is to be allocated to:
- St Johns Ambulance to support the NHS
- victims charities, including domestic abuse, to help with potential increase in demand for charities providing these services
- charities supporting vulnerable children, so they can continue delivering services on behalf of local authorities;
- disabled people
- Citizens Advice Bureau to increase the number of staff providing advice during this difficult time
The Government Departments will identify priority recipients, with the aim that these charities will receive money in the form of a cash grant over the next few weeks and by the end of April to assist in paying amongst other costs April’s wage bill.
The Act is intended to facilitate the rescue of businesses that are in financial difficulty by preventing suppliers from invoking certain termination clauses under a supply contract, and therefore maintaining supply of goods and services to the business whilst plans to save the business can be considered.
Supply contracts often contain a clause enabling them to terminate the contract, or take other steps such as requiring payment in advance, in the event that the customer enters an insolvency procedure.
This new Act removes any such contractual right by dis-applying any clause that allows the supplier to terminate the contract, or take any other step, due to the customer entering an insolvency process.
Suppliers are also prevented from demanding payment for pre-insolvency debts owed by the customer as a condition of continued supply.
Additionally, where the supplier had a contractual right to terminate the contract due to an event occurring before the customer went into the insolvency process (whether or not linked to payment issues), the supplier loses this right for the duration of the insolvency process.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
If it is not possible to find work for the employee to do at home, you do have the option of putting the employee on furlough.