I have essential workers who do home visits. How do I assess the risks?
The fundamentals of risk assessment remain the same as for any other foreseeable risk.
Focus on risk controls which reflect Government guidance; social distancing (2 metres) and avoiding contact with occupiers if possible, high-quality PPE – disposable overalls, gloves and fluid repellent surgical face masks, ready access to antibacterial wipes for surfaces, tools and equipment and plentiful hand sanitizer.
Related FAQs
The amount an insurer charges for providing cover is a critical aspect of the underwriting process. The premium must be sufficient to cover expected claims but must also take into account the possibility that the insurer will have to access its capital reserve –it is risk assessment based and the greater the risk, the higher the premium. Historically, insurers of high-rise buildings would have only had to prepare for a loss caused by damage to just a few flats within a building. That is because the design and construction of that building, with the right materials and fire safety provisions in place, should have limited the spread of fire and allowed the damage to be contained –or at least make this an extremely low risk. Now we know that many buildings have been designed, built and signed off in a regulatory system that an independent Government review has found was not fit for purpose. Premiums will reduce overtime but will be dependent upon the perceived level of risk reducing as the regulatory regime, BSA and BSR become more established.
The Act is intended to facilitate the rescue of businesses that are in financial difficulty by preventing suppliers from invoking certain termination clauses under a supply contract, and therefore maintaining supply of goods and services to the business whilst plans to save the business can be considered.
Supply contracts often contain a clause enabling them to terminate the contract, or take other steps such as requiring payment in advance, in the event that the customer enters an insolvency procedure.
This new Act removes any such contractual right by dis-applying any clause that allows the supplier to terminate the contract, or take any other step, due to the customer entering an insolvency process.
Suppliers are also prevented from demanding payment for pre-insolvency debts owed by the customer as a condition of continued supply.
Additionally, where the supplier had a contractual right to terminate the contract due to an event occurring before the customer went into the insolvency process (whether or not linked to payment issues), the supplier loses this right for the duration of the insolvency process.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
Yes. Their contracts can be renewed or extended during the furlough period without breaking the terms of the scheme.
If the employee’s contract has not already expired, the contract can be extended or renewed. The employee may be furloughed provided that they were employed on or before 30 October 2020. You must also have made a RTI submission to HMRC between 20 March 2020 and 30 October 2020.
If the employee’s contract expired on or after 23 September 2020, the employee can be re-employed and furloughed. Please note that the employee must have been employed by you on 23 September 2020 and you must have made a RTI submission to HMRC between 20 March 2020 and 30 October 2020.