Skip to content

I work in construction. Can I still travel to work?

The CLC has also prepared a template letter that firms may adopt and issue to their workforce regarding travel to work. This can be accessed at download document.

The CLC’s current advice to those carrying out works on site is to carry out your own risk assessment on each site and determine whether or not it is safe to continue to work in accordance with the Public Health England instructions and the CLC Site Operating Procedures.  If it is not possible to work in accordance with the above they should not work.

Related FAQs

Who do the Procurement Policy Notes (PPN) apply to?

All three of the PPNs are effective immediately and apply to the following Contracting Authorities:

  • Central Government Departments
  • Executive agencies
  • Non-departmental public bodies
  • Local authorities
  • NHS bodies
  • The wider public sector

In regards to PPN03/20, those in scope organisations that do not currently use procurement cards are advised to immediately put in place arrangements using the relevant Crown Commercial Service Agreement (Lot 2 of RM3828 Payment Solutions).

What if we are a charity in Scotland Wales or Northern Ireland?

Because they all have devolved governments, when there are changes to spending levels in England, the Government makes adjustments to the amount of public expenditure allotted to Scotland, Wales and Northern Ireland.  In this case £60 million will be made available for all of the devolved administrations as a result of the £370 million funding allocated to charities in England. This is broken down as follows:

  • £30 million for the Scottish Government
  • £20 million for Welsh Government
  • £10 million for the Northern Ireland Executive

There may be further allocations, dependent on the final projects funded, through the £360 million direct grant pot.

How do I implement temporary contractual arrangements?

The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.

With time and resource precious commodities, focus should be given to documenting:

  • The key changes to your PFI requirements
  • The temporary nature of the measures
  • The requirement for best efforts on behalf of the PFI Contractor
  • The importance of continued health and safety measures at all times
What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here