Skip to content

If, after deploying all control measures the risk is still deemed too great for employees to work safely, then what should employers do?

The law says that if after assessing a risk and considering all the control measures available to you, you cannot undertake a task safely – then you should not undertake the task.

If that means taking BAME workers out of higher risk frontline work, that is what will have to be done.

Beware of workers saying “we’ll accept the risk” – it does not protect you against regulatory/enforcement action or civil claims.

Related FAQs

What is the NICE guidance around clinical decision-making?
  • Be alert to the fact that guidance on treating Covid-19 may change with emerging knowledge/scientific data and this may require subsequent modifications to treatment.
  • Critical care staff should support healthcare professionals who do not routinely work in critical care but need to do so.
Can you require an employee to tell their employer whether they have been tested for coronavirus/the results of that test?

Yes, this is very likely to amount to a reasonable management instruction which is put in place for public health reasons. Employers should make it clear to their employees that this is something they are required to do and that if they fail to do so this may lead to disciplinary action.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Alternatives to redundancy toolkit

We have developed a Toolkit to help with these issues. The Toolkit contains:

  • LO1 How to Guide: Lay off and short time working
  • LO2 Letter directing employee to take annual leave
  • LO3 Letter confirming lay off (contractual right)
  • LO4 Letter confirming short time working (contractual right)
  • LO5 Letter proposing lay off (no contractual right)
  • LO6 Letter proposing short time working (no contractual right)
  • LO7 Counter notice disputing entitlement to claim redundancy payment
  • LO8 Script for announcing lay off or short time working (contractual right)
  • LO9 Script for announcing lay off or short time working (no contractual right)
  • LO10 Letter proposing reduction in working hours and pay

The cost of this Toolkit is £500 plus vat. If you would like to find out more about the Toolkit, please speak to your usual Ward Hadaway employment contact, or get in touch one of the contacts at the bottom of this page.