Skip to content

If an employer identifies that higher PPE spec is required for BAME employees undertaking a particular task, is it necessary to increase the spec for all employees working in that area?

It is. If you assess a risk and identify a control measure then fail to deploy it, then you are breaching your legal duties under HASWA and potentially committing a criminal offence. So if you decide for example that N95 respirators have to be used by everyone, you have a duty to provide them.

So the short answer is yes.

Related FAQs

What are the early warning signs that a contractor may be in financial difficulty?

As the project progresses, it is important to continually monitor the contractor’s performance.  Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:

  • Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
  • Slowdown in progress on site
  • Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
  • An increasing number of defects and reduction in the quality of the contractor’s work
  • The contractor seeking changes in the payment arrangements, and in particular early payments
  • The contractor making spurious claims or contra charges
  • The contractor seeking assignment of its benefit of the building contract
  • Late filing of accounts by the contractor at Companies House
  • Unsatisfied court judgements against the contractor
  • Subcontractors and suppliers not being paid or being paid late
  • Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
  • Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
  • Increasingly aggressive behaviour by the contractor
  • The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
What is the Bounce Back Loan Scheme (BBLS)?

On 4 May 2020, the Government launched the Bounce Back Loan Scheme (BBLS), which is intended to cut red tape to enable smaller businesses to access finance quickly during the coronavirus outbreak.

The scheme helps small and medium-sized businesses to borrow between £2,000 and up to 25% of their turnover. The maximum loan available is £50,000.

The government guarantees 100% of the loan and there are no any fees or interest to pay for the first 12 months. After 12 months the interest rate will be 2.5% a year.

The length of the loan is 6 years, but it can be repaid early without penalty. No repayments will be due during the first 12 months.

Under the scheme, lenders are not permitted to take any form of personal guarantee or take recovery action over a borrower’s personal assets (such as their main home or personal vehicle).

Businesses can apply for a BBLS loan if it:

  • is based in the UK
  • was established before 1 March 2020, and
  • has been adversely impacted by the coronavirus.

Any business regarded as being a business in difficulty on 31 December 2019 will need to confirm that it is complying with additional state aid restrictions.

Businesses from any sector can apply, except the following:

  • banks, insurers and reinsurers (but not insurance brokers)
  • public-sector bodies, and
  • state-funded primary and secondary schools.

Businesses already claiming under the following schemes cannot apply although it is possible to convert an existing loan under such schemes into BBLS:

  • Coronavirus Business Interruption Loan Scheme (CBILS)
  • Coronavirus Large Business Interruption Loan Scheme (CLBILS)
  • COVID-19 Corporate Financing Facility.

There are 11 lenders participating in the scheme including many of the main retail banks, which are listed on the British Business Bank’s website (www.british-business-bank.co.uk/ourpartners/coronavirus-business-interruption-loan-schemes/bounce-back-loans/for-businesses-and-advisors/). Applicants are directed to approach a suitable lender via the lender’s website. If an applicant is declined by a lender, they can apply to other lenders in the scheme.

The lender will ask applicants to fill in a short online application form and self-declare that they are eligible. All lending decisions remain fully delegated to the accredited lenders.

Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?

The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.

The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.

The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:

  • Amending the contract requirements
  • Varying timings of deliveries
  • Relaxing KPIs or service levels
  • Extending time for performance (e.g. revising a contract delivery plan), and/or
  • Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).

These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.

A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.

If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.

 

 

Should Covid-19 be recorded as a cause of death?

The Chief Coroner supports the position, communicated by NHS England and the Chief Medical Officer that Covid-19 is an acceptable direct or underlying cause of death for the purposes of completing the Medical Certificate of Cause of Death (MCCD) and is considered a naturally occurring disease. This cause of death alone is not a reason to refer a death to a coroner under CJA 2009.

If the cause of death is believed to be due to confirmed Covid-19 infection, there is unlikely to be any need for a post mortem to be conducted and the MCCD should be issued, and guidance is given on how this is delivered to the Registrar in the event of the next of kin/informant being in self-isolation. 

In a hospital setting the MCCD process should be straightforward because of diagnosis and treatment in life. This may be more complex in a community setting. The Coronavirus Act 2020 however expanded the window for last medical review from 14 to 28 days. Outside of this, the death will need to be reported to the coroner.

Although Covid-19 is a naturally occurring disease, there may be additional factors around the death which mean it should be reported to the coroner; for example, the cause of death is unclear, or where there are other relevant factors. Guidance is given to coroners on how to manage such reported deaths, particularly where post mortem examinations may not be readily availability.

I have to pay my ex-spouse monthly spousal maintenance pursuant to a Court Order and I can no longer afford to pay. Can I stop paying?

Maintenance Orders embodied in a Court Order are variable. If you have lost a very large part of your income, then the Courts ought to take that into consideration when looking at a Court Application to reduce or end spousal maintenance payments. The outcome of any Court Application will, however, depend on a number of factors.

Technically, you should not just stop paying or reduce the maintenance payments, as your ex-spouse could then make an Application to Court for enforcement and payment of the arrears. You could ask the Court to forego you having to pay those arrears if you had evidence to prove that you could not make the payments, however, the Court will need to take a fair approach and you should not assume this request will be agreed.

You should first try to negotiate a reduction or termination of the maintenance with your ex-spouse, either directly or through a Solicitor. If this is possible, you should obtain a Court Order reflecting that agreement. Where a sensible compromise cannot be reached, a Court Application may be necessary.