I’m a housing provider. How do I continue to manage disrepair during the coronavirus outbreak?
The practicalities and processes regarding disrepair claims will undoubtedly be affected. Housing providers will have to adopt a risk-based approach and consider government guidance to handle claims going forward. Key points to consider are:
- Compliance with the Pre-Action Protocol for Housing Conditions Claims (particularly disclosure)
- The practicalities of inspection
- Non-urgent repairs
Related FAQs
A break or pause in learning can be initiated where the interruption to learning due to Covid-19 is greater than four weeks. This must be reported as a formal break in learning. In such circumstance the funding to the training provider will be suspended for the duration of the break. Previously, the rules only allowed an apprentice to initiate this break in learning but this has been expanded to give employers and training providers the right to initiate this. Training providers should continue with their monthly IRL submissions to the ESFA. During breaks in apprenticeships it is not necessary for the apprentice to comply with the minimum of 20% on the job training requirement but this will resume when the break ends.
The Regulations do not require any prior agreement between an employer and employee that it was not reasonably practicable for holiday to be taken for it to be carried over.
However, if an employee requests holiday then an employer must have ‘good reason’ for refusing it due to coronavirus. The term ‘good reason’ is not defined so the Government will expect employers, employees and (if necessary on any dispute) the Courts to apply common sense.
The Regulations are not confined to key workers so could, in principle, be used by employers for a wider range of employees.
The Government guidance suggests that the following factors should be taken into account when considering whether it was reasonably practicable to take the leave in the relevant year:
- Whether the business has faced a significant increase in demand due to COVID-19 that would reasonably require the worker to continue to be at work and cannot be met through alternative practical measures.
- The extent to which the business’ workforce is disrupted by COVID-19 and the practical options available to the business to provide temporary cover of essential activities.
- The health of the worker and how soon they need to take a period of rest and relaxation.
- The length of time remaining in the worker’s leave year.
- The extent to which the worker taking leave would impact on wider society’s response to, and recovery from, the effects of COVID-19.
- The ability of the remainder of the available workforce to provide cover for the worker going on leave.
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.
Yes: The Cabinet Office has published a number of Procurement Policy Notes to provide instructions to Public Bodies to enable payments to continue to be made to at risk suppliers (and their supply chains) who have been affected by Covid-19. Copies of this guidance can be obtained from the Government website at: https://www.gov.uk/government/publications/procurement-policy-note-0220-supplier-relief-due-to-covid-19
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.