I’m getting married but have had to postpone the wedding. Should I delay putting a prenuptial agreement in place until a later date?
No. The greater the gap between the completion of a Prenuptial Agreement and the Wedding the more likely it will be upheld by the Court. If such an Agreement is made shortly before the wedding takes place one of the parties to it could claim that they felt under pressure to sign and the Court may decline to follow it.
Related FAQs
CBILS is made available through the British Business Bank’s 40+ accredited lenders and partners, which are listed on their website (https://www.british-business-bank.co.uk/ourpartners/coronavirus-business-interruption-loan-scheme-cbils/accredited-lenders/).
Businesses should initially approach their own lender and only consider other lenders if they are unable to access the finance they need. Note, not every accredited lender can provide every type of finance listed.
Some banks/lenders are not included in the list of accredited lenders which appears to mean that they cannot provide support through the Scheme. We understand from the British Business Bank that further lenders are applying to be accredited but that this may take a little time to process. If the provider of your senior debt is not on the accredited list you should consider approaching the bank which provides your day to day account banking services.
If you wish or need to access the Scheme via an alternative funder the process may take longer as usual on-boarding and KYC processes will need to be undertaken.
It is envisaged that employees of organisations falling into the first two categories set out above and won’t be eligible for the job retention scheme in relation to the majority of their employees. It is envisaged that NHS Trusts for example are going to require their staff to be working at full capacity where possible. However, the guidance doesn’t definitely exclude public sector organisations from furloughing employees and notably the government expects such organisations to use public money to continue to pay staff and not furlough them, rather than say requires. In reality, it is difficult to see how such an organisation will be able to rely on the scheme, but the guidance doesn’t completely rule it out.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
The fee payer that pays the fee to the contractor’s PSC for the services (end user client or agency) will be responsible for operating PAYE and deducting NIC’s. The fee payer must also pay employer NIC’s and where applicable the apprenticeship levy so there will be additional costs involved in the event of a change to employed status for tax purposes.
If the assessment concludes that the contractor is self-employed, the PSC can continue to be paid gross.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements