I’m getting married but have had to postpone the wedding. Should I delay putting a prenuptial agreement in place until a later date?
No. The greater the gap between the completion of a Prenuptial Agreement and the Wedding the more likely it will be upheld by the Court. If such an Agreement is made shortly before the wedding takes place one of the parties to it could claim that they felt under pressure to sign and the Court may decline to follow it.
Related FAQs
At the discretion of the lender, the Scheme may be used for unsecured lending for facilities of £250,000 and under.
Lenders were required to demonstrate lending additionality (i.e. lending that without the Scheme, wouldn’t have otherwise taken place). The Scheme has been extended to those businesses who would have previously met requirements for a commercial facility and would not have been eligible for CBILS. As a result it is suggested that all viable small businesses affected by Covid-19, and not just those unable to secure regular commercial financing, will now be eligible should they need finance to keep operating.
Primary Residential Property cannot be taken as Security under the Scheme. If the lender can offer finance on normal commercial terms without the need to make use of the Scheme, they will do so.
The government released further clarification on the Coronavirus Job Retention Scheme on 4 April. The wording referred to concerning public sector organisations and organisations receiving public funding remains the same.
The revised guidance does provide a helpful insight into how HMRC will deal with applications made to it for assistance under the scheme. It appears that there won’t be a particularly forensic approach adopted by HMRC. The guidance says you can furlough staff if you cannot maintain your current workforce because your operations have been severely affected by coronavirus.
It goes on to say that all employers are eligible to claim under the scheme and the government recognises different businesses/organisations will face different impacts from coronavirus. The need to demonstrate the impact of coronavirus on your business/organisation is not one of the criteria businesses/organisations are going to need to satisfy, so the government does not appear to intend to set a specific test to determine if a business/organisation is “severely impacted by coronavirus”. It is hoped that this should provide additional comfort to publicly funded organisations facing significant restrictions to their operations during the Covid-19 crisis.
The application has to be made before the date on which the accounts should have been filed, so this process can’t be used if you are already late. If you don’t make the application before your filing deadline, then a fine will automatically be generated if your accounts are filed late. Whilst you could appeal against such a fine on the grounds that the delay was caused by coronavirus issues, this is likely to be a much more time consuming and uncertain process that applying in advance.
It does not appear that the process applies to Confirmation Statements or other returns.
If you consider the factors used to determine status you can include the following terms that are more in line with a self-employed relationship:
- The right to provide a substitute of the contractor’s choice in the event the individual is not able to perform the services;
- The ability to work for other businesses as long as doing so will not affect the services to be provided by the contractor;
- The contractor should have sufficient control over how, when and where (if possible) they provide the services;
- A degree of financial risk can be included for unsatisfactory work or failing to complete a project or task
We have terms that cover all of these points that can be tailored to your needs. The consultancy agreement is included in our IR35 toolkit.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.