I’m self-isolating and understand that it takes some time to get a Lasting Power of Attorney registered. What can I do in the meantime to enable someone else to operate my bank account and pay my bills?
The Office of the Public Guardian is continuing to accept applications to register Lasting Powers of Attorney but their usual estimated timescale of eight to ten weeks is likely to be affected by the current situation.
Consequently, an alternative or interim measure if you need something quickly is to execute a General Power of Attorney to authorise someone to act as your Attorney to undertake day to day financial transactions for you. The General Power of Appointment only needs to be executed by you in the presence of a witness (not the Attorney) to be valid and does not need to be registered with the Court of Protection. However, the Power of Attorney would cease to have effect if you become incapable of managing your affairs. It should be seen as a stop-gap only.
Related FAQs
- Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
- Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
- Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
- The ability to get people on site to undertake material operations
In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.
If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.
The duty is to inform and consult appropriate representatives of the “affected employees”.
Note that the term “affected employees” means those who may be “affected by the proposed dismissals or who may be affected by measures taken in connection with those dismissals”. The term extends beyond those immediately at risk of dismissal to include those affected by measures associated with the redundancies.
“Appropriate representatives” can be:
- The Trade Union (if recognised)
- (For any roles not covered by collective recognition) any existing standing body of elected or appointed employee representatives (if already in place)
- Employee representatives, who are elected specifically for redundancy consultation
“Switching” is where you can transfer from one visa category to another without leaving the UK. However, in many instances where an individual wants to change from one visa category to another, they have to leave the UK and apply from the country they normally reside in.
There are currently limited concessions in place due to the pandemic where you are able to switch visas from within the UK instead of applying from overseas. These are regularly updated and so please contact us for further information.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Lenders implementing the Scheme can assist in a number of ways, including:
- Term loans
- Overdrafts
- Invoice finance
- Asset finance facilities
The maximum value available under the scheme is £5m, with repayment terms of up to six years for term loans and asset finance. Overdrafts and invoice finance facilities will be available for up to three years.