Is it possible to proceed with a hearing in person for any COP matters?
Any hearings attended in person will need to be approved by the judge hearing the matter, if necessary, in consultation with the regional lead COP judge. Such requests are highly unlikely to be granted during COVID-19 unless there is a genuine urgency. However, it is deemed to be appropriate matters are likely to be adjourned on the basis that a remote hearing is not possible and a hearing in person is not safe or possible.
Related FAQs
All three of the PPNs are effective immediately and apply to the following Contracting Authorities:
- Central Government Departments
- Executive agencies
- Non-departmental public bodies
- Local authorities
- NHS bodies
- The wider public sector
In regards to PPN03/20, those in scope organisations that do not currently use procurement cards are advised to immediately put in place arrangements using the relevant Crown Commercial Service Agreement (Lot 2 of RM3828 Payment Solutions).
The Competition and Markets Authority (CMA) has issued a number of guidance documents about the application of competition law rules during the coronavirus outbreak. In general, the competition law rules are being relaxed in very specific circumstances.
A common feature of corporate acquisitions is that part of the consideration is paid on deferred terms or by way of earn out over a period of years following completion. Where deferred consideration is payable, this is either on the basis that outstanding payments will be made on scheduled dates or, less usually, subject to certain agreed (typically financial) objectives being met. These objectives almost always relate to a period before completion of the deal and are dealt with as part of a completion accounts mechanism.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
The outbreak is certainly going to have an impact on new lease negotiations.
Undoubtedly many transactions will be put on hold or indeed stop entirely. Where matters are ongoing, tenants may well look to strengthen rent suspension provision.
It is also possible that tenants and their representatives will also now seek to include termination rights for unseen events. In this regard, the concept of force majeure may start to appear more often in leases.
In both of the examples above, such attempts are not likely to be well received from landlords who will undoubtedly suggest that tenants ensure that their business interruption insurance policies are robust enough to protect the tenant in the event of any future pandemic events.
Another approach tenants might adopt going forwards in negotiations for a new lease (or indeed seeking to vary existing leases), is to move away from the traditional market rent model to a turnover rent arrangement. This will offer some protection going forward if trading conditions deteriorate, but again getting institutional landlords to agree such an approach may prove difficult.