Is it possible to proceed with a hearing in person for any COP matters?
Any hearings attended in person will need to be approved by the judge hearing the matter, if necessary, in consultation with the regional lead COP judge. Such requests are highly unlikely to be granted during COVID-19 unless there is a genuine urgency. However, it is deemed to be appropriate matters are likely to be adjourned on the basis that a remote hearing is not possible and a hearing in person is not safe or possible.
Related FAQs
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved. To be in the best possible position, it is worth considering the following at the outset of any project:
- Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
- Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
- Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
- Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
- Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
- Project bank accounts and escrow accounts can also provide some further assurances for the parties involved
The Flexible Furlough Scheme, ‘FFS’ an unfortunate acronym, allows employees to work for some of the week and be furloughed for the rest.
Read more about thisCommercial partner Damien Charlton explains the basic principles of force majeure, and how they are relevant in the current extreme circumstances caused by the Covid-19 pandemic.
Read more about thisA common feature of corporate acquisitions is that part of the consideration is paid on deferred terms or by way of earn out over a period of years following completion. Where deferred consideration is payable, this is either on the basis that outstanding payments will be made on scheduled dates or, less usually, subject to certain agreed (typically financial) objectives being met. These objectives almost always relate to a period before completion of the deal and are dealt with as part of a completion accounts mechanism.
Read more about this