Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
Related FAQs
- On admission to critical care, the risks, benefits and likely outcomes of the different treatment options should be discussed with patients, families and carers so they can make informed decisions about their treatment wherever possible.
- A member of the critical care team should be involved in these discussions whenever the patient or team needs advice about critical care to make decisions about treatment.
A new Permitted Development Right has been introduced by The Town and Country Planning (Permitted Development and Miscellaneous Amendments) (England) (Coronovirus) Regulations 2020 providing for the construction of new dwellinghouses on detached blocks of flats.
The new Right comes into force on 1 August 2020 and from this date development consisting of works for the construction of up to two additional storeys of new dwellinghouses immediately above the existing topmost residential storey which is a purpose-built, detached block of flats is permitted development. The Right additionally covers specified associated works, the construction of fire escapes and ancillary structures, bin stores for example.
The Right is subject to detailed criteria being met and to a prior approval process to the Local Planning Authority who can consider the acceptability of the proposed development in a range of respects. A link to the Regulations is here.
The Regulations additionally include a number of further amendments including additional rights for the holding of markets and for additional temporary uses of land for a time limited period. They additionally include amendments to existing permitted development rights for the change of use of buildings to dwellinghouses through a requirement that there be adequate natural light in all habitable rooms.
The Act is intended to facilitate the rescue of businesses that are in financial difficulty by preventing suppliers from invoking certain termination clauses under a supply contract, and therefore maintaining supply of goods and services to the business whilst plans to save the business can be considered.
Supply contracts often contain a clause enabling them to terminate the contract, or take other steps such as requiring payment in advance, in the event that the customer enters an insolvency procedure.
This new Act removes any such contractual right by dis-applying any clause that allows the supplier to terminate the contract, or take any other step, due to the customer entering an insolvency process.
Suppliers are also prevented from demanding payment for pre-insolvency debts owed by the customer as a condition of continued supply.
Additionally, where the supplier had a contractual right to terminate the contract due to an event occurring before the customer went into the insolvency process (whether or not linked to payment issues), the supplier loses this right for the duration of the insolvency process.
Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.
New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.
For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.
Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.
For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.
In recognition of the problems that the current situation is causing, the UK IPO classed the 24th March and all subsequent days as “interrupted days” which means that deadlines that fall within this period will be extended until the UK IPO declares that the interrupted days have ceased. As lockdown has begun to be eased, the IPO has now reviewed its position and has confirmed that the “interrupted days” period will come to an end on the 29 July 2020. This means that Thursday 30 July 2020 will be the first normal day of operation, therefore all “interrupted days” deadlines will expire on this day. Similarly, if your deadline falls after the period of interruption ends, this deadline will not be automatically extended.
The IPO is conscious that many businesses may still be in challenging positions when the period of “interrupted days” end. They will endeavour to continue to provide flexibility and support to assist businesses with their applications. They hope to temporarily remove fees for requests for extensions of deadlines, and will give further updates when this fee exemption is in place.
The IPO continues to encourage applicants to meet original deadlines where they are able. As their offices are closed, the UK IPO is not currently processing paper forms (i.e. hard copy) and faxes. However, they are processing forms which have been submitted electronically, or via email and have made a new email address available for the submission of forms.
Intellectual Property Offices covering other territories have made their own announcements about the extension of deadlines. The EUIPO’s period of extension of deadlines came to an end on the 18th May. However, they have published a Guidance Note and accompanying webinar on the EUIPO website, detailing options for parties who may struggle to meet deadlines and remedies for those who may have missed deadlines.