Skip to content

Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

Related FAQs

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
What is the current guidance relating to Private Finance Initiatives and PF2 Projects in light of coronavirus?

On 2 April 2020, the Government issued guidance relating to Private Finance Initiatives and PF2 Projects. The guidance, which is to be enforced with immediate effect (currently due to stay in place until 30 June 2020), is one of several guidance notes issued to date.

A link to the guidance is set out below:

https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/877804/2020_04_01_PFI_and_COVID19_final.docx.pdf

Key messages to contracting authorities

  • PFI contractors should very much consider themselves as being part of the public sector response to the current pandemic
  • Covid-19 is not regarded as, and is not to be classified as a force majeure event
  • PFI contractors must ensure that contingency plans are up to date and have been reviewed and discussed with contracting authorities to enable the continuity of full services to respond to the pandemic and maintain vital public services
  • Contracting authorities should work closely with PFI contractors to use all available options to maintain public services during the emergency period
  • Local arrangements should be made where PFI contractors can’t deliver the agreed requirements and performance standards
  • “Best efforts” should be made by all parties for the continuation of service provision
What is the minimum period for Flexible Furlough?

It has now changed. Instead of being 3 weeks, it is now technically any period. However, 7 days is the minimum claim period you can now make.

What is the NHS coronavirus Test and Trace scheme and how does it work?

The NHS Test and Trace service is operated by the NHS in England to track and help prevent the spread of COVID-19. Where an individual displays symptoms of coronavirus they can be tested to determine whether or not they have the disease. Those with the disease will then be contacted by NHS contact tracers and asked who they have come into close contract with.
Close contact is defined as:

  • Face to face (within 1 metre)
  • Spent more than 15 minutes within 2 metres of another person
  • Travelled in a car or on a plane with another person

The contact tracer will then contact those people with whom the individual has come into close contact and tell them to self-isolate for 14 days.

Can I collect health data in relation to Covid-19?

Yes. With respect to employees you have an obligation to protect their health so you can gather information to do that. You might gather information from your employees on who has the virus, who has had it and recovered and also who has tested negative. You might also want to know if individuals have been in contact with someone who has it or if they are in a vulnerable group. It is reasonable to want to know where individuals have travelled. In the future it may also be reasonable to know if they are planning to travel to a virus hot spot, as the impact of the virus around the world is likely to continue for some time even after the outbreak has been contained in the UK.

It is reasonable to gather some information about visitors to your site, be they customers or suppliers, as this information will also help protect your staff. However, you should keep what you gather to a minimum. For visitors, it’s unlikely that you need to know anything more than they have Covid-19, are displaying symptoms or have recently been in contact with someone who has the virus.