Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
Related FAQs
The reaction from NCVO is that this is an important first step. However, it will not stop well run charities from closing and others will look very different in a few months’ time.
Employers had until 31 July 2020 to make any claims for claim periods up to 30 June 2020. That was the end of the old scheme.
From 1 July 2020, claim periods must start and end within the same calendar month and must be for at least 7 days unless you are claiming for the first few days or the last few days in a month.
You can only claim for a period of fewer than 7 days if the period you are claiming for includes either the first or last day of the calendar month, and you have already claimed for the period ending immediately before it.
For example, if an employee is furloughed for 7 days spanning a month. You can claim the last 3 in one month, and 4 from the next.
The crucial point is that you cannot make claims that cross calendar months.
The first time that you could make a claim for days in July 2020 was 1 July 2020. You could not claim for periods in July 2020 before this point.
Arrangements for end point assessments can be modified or rescheduled. End point assessment organisations should engage with External Quality Assurance Providers to agree arrangements for the end point assessments where face-to-face assessments are being modified. Where rescheduling is required due to Covid-19 issues and there is a specified time limit for the ESA post gateway, a further pause of 12 weeks is allowable. This should be recorded by the training provider in the ILR.
Contractors working for public sector organisations who are deemed employees for IR35 purposes may be eligible to be furloughed provided they are paid via PAYE. In this scenario the agreement to furlough would be made between the contractor’s personal service company (PSC) and the fee payer (usually the agency). The parties would agree that the contractor will carry out no work for the public sector organisation while furloughed and the fee payer would apply for the grant.
At the moment the guidance states that in order to be eligible a claim for furlough must have to have been submitted by 31 July 2020 for a period of 3 weeks between 1 March and 30 June 2020.
Employees who are unable to work because they are shielding in line with public health guidance (or need to stay home with someone who is shielding) can be furloughed after 1 July 2020, as long as you have previously submitted a claim for them in relation to a furlough period of at least 3 consecutive weeks taking place any time between 1 March 2020 and 30 June.