Skip to content

Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

Related FAQs

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
How do you support your Mental health first aider (MHFA) team?

We recommend that ongoing support is provided to all MHFA’s beyond completion of the MHFA training. It is necessary to do refresher training (approx. every 3 years) and ideally ongoing ‘continued professional development’ should be provided as well as regular opportunities for debriefing / seeking support. One way of supporting your MHFAs in the workplace is by creating a buddy system amongst the MHFAs. That way the individuals carrying out the role of MHFAs have a support structure in place amongst themselves. All trained MHFAs can also reach out to management to discuss any concerns they have or to seek any further support they need.

What are the changes to the law?

On 25th June 2020, the Corporate Insolvency and Governance Act, among other things, introduced new restrictions on suppliers of goods and services to terminate the contract in the event that the customer enters an insolvency process.  This has very important consequences for many businesses as it could expose them to greater financial risks.

Can you place employees who TUPE transfer to you on Flexible Furlough?

A new employer may claim under the scheme in respect of the employees of a previous business transferred after 10 June 2020 as long as:

  • the TUPE or PAYE business succession rules apply to the change in ownership
  • the employees being claimed have previously had a claim submitted for them by their prior employer in relation to a furlough period of at least 3 consecutive weeks taking place any time between 1 March 2020 and 30 June

In these circumstances, the maximum number of employees that the new employer can claim for will be the total of both:

  • the maximum number of employees the new employer claimed for in any one claim ending on or before 30 June
  • the number of employees that are being transferred to the new employer which have had a claim submitted for them in relation to a furlough period of at least 3 consecutive weeks taking place any time between 1 March 2020 and 30 June. This is subject the maximum cap the previous employer was subject to.

A new employer is also eligible to claim under scheme in respect of the employees associated with a transfer of a business after 10 June 2020 from the liquidator of a company in compulsory liquidation where:

  • TUPE would have applied were it not for the company being in compulsory liquidation
  • the employees being claimed for have been furloughed and a had a claim submitted for them by their prior employer in relation to a period of at least 3 consecutive weeks taking place any time between 1 March 2020 and 30 June

In these circumstances, the maximum number of employees that the new employer can claim for will be the total of both:

  • the maximum number of employees the new employer claimed for in any one claim ending on or before 30 June and
  • the number of employees that are being transferred to the new employer which have had a claim submitted for them by their prior employer in relation to a furlough period of at least 3 consecutive weeks taking place any time between 1 March 2020 and 30 June. This is subject to the maximum cap the previous employer was subject to.
Should Covid-19 be recorded as a cause of death?

The Chief Coroner supports the position, communicated by NHS England and the Chief Medical Officer that Covid-19 is an acceptable direct or underlying cause of death for the purposes of completing the Medical Certificate of Cause of Death (MCCD) and is considered a naturally occurring disease. This cause of death alone is not a reason to refer a death to a coroner under CJA 2009.

If the cause of death is believed to be due to confirmed Covid-19 infection, there is unlikely to be any need for a post mortem to be conducted and the MCCD should be issued, and guidance is given on how this is delivered to the Registrar in the event of the next of kin/informant being in self-isolation. 

In a hospital setting the MCCD process should be straightforward because of diagnosis and treatment in life. This may be more complex in a community setting. The Coronavirus Act 2020 however expanded the window for last medical review from 14 to 28 days. Outside of this, the death will need to be reported to the coroner.

Although Covid-19 is a naturally occurring disease, there may be additional factors around the death which mean it should be reported to the coroner; for example, the cause of death is unclear, or where there are other relevant factors. Guidance is given to coroners on how to manage such reported deaths, particularly where post mortem examinations may not be readily availability.