Skip to content

Is the Land Registry functioning?

Yes. The Land Registry published a new service update on 14 May, here:

https://www.gov.uk/guidance/coronavirus-covid-19-impact-on-hm-land-registrys-service

Importantly, the Land Registry will process registrations where documents have been executed using the Mercury signing approach:

For land registration purposes, a signature page will need to be signed in pen and witnessed in person (not by a video call). The signature will then need to be captured, with a scanner or a camera, to produce a PDF, JPEG or other suitable copy of the signed signature page. Each party sends a single email to their conveyancer to which is attached the final agreed copy of the document and the copy of the signed signature page.

To summarise some further points:

  • Most information enquiries are experiencing minimal delays
  • Registrations of new titles, such as on sales of part or new leases, and applications to update existing titles, are experiencing more significant delays but can be expedited via the expedite service
  • Cancellation dates for replying to requisitions are extended until further notice
  • Access to free documents on the land registry portal has been extended to 90 days from completion of the transaction
  • Identity requirements have been relaxed. The Land Registry will now raise a requisition for identity documents, and not cancel applications
  • Requests for extensions to a notice or objection period will be granted if lawfully possible
  • Land charges searches can be submitted electronically with PDF documents

Related FAQs

How do I implement temporary contractual arrangements?

The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.

With time and resource precious commodities, focus should be given to documenting:

  • The key changes to your PFI requirements
  • The temporary nature of the measures
  • The requirement for best efforts on behalf of the PFI Contractor
  • The importance of continued health and safety measures at all times
What is the new process for assessing status under IR35?

The end user client will be responsible for assessing if the contractor is employed or self-employed for tax purposes. It is required to take reasonable care in carrying out the assessments.

When an assessment is carried out the outcome must be confirmed to the contractor with accompanying reasons in a Status Determination Statement (SDS). This SDS must be provided to the contractor before making payment to them. It must also be provided to the agency if there is one in the chain (more on this later).

The end user client must have a dispute resolution procedure to enable to the contractor or agency to appeal the assessment outcome.

What is the Flexible Furlough Scheme?

The Flexible Furlough Scheme, ‘FFS’ an unfortunate acronym, allows employees to work for some of the week and be furloughed for the rest.

What is the "Job Retention Bonus"?

As a result of the CJRS being extended, the Job Retention Bonus will no longer be paid in February 2021.

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.