Is there anything I can do to try and settle my claim?
There are several options that can be used at this time to try and settle disputes. If it is not possible to settle a dispute via direct discussions between the parties then some form of Alternative Dispute Resolution (“ADR”) might be appropriate. Mediation is the most popular form of ADR. Most people’s perception of mediation is that it needs to be in person but that does not have to be the case.
Mediation can take place online or on the telephone. Most, if not all, ADR providers remain open for business and are quickly changing their business model to ensure that mediations can still take place. Mediation can be arranged at reasonably short notice and certainly so far as the online model is concerned, it mirrors the process that is adopted when parties appear in person. Online mediation allows for joint sessions with the mediator to take place and also for the parties to break out into their respective rooms for private discussions. If a dispute settles at mediation – and the vast majority do – then the agreement reached between the parties is binding and can be enforced.
A group of senior former judges and legal academics have now called for an acceleration in the use of ADR in light of the current circumstances. They have stated that courts should promote “and where appropriate require” the use of ADR. Mediation has particularly seen an increase in growth at this time.
ADR normally results in a quicker outcome than if the matter proceeds in the courts. Due to its conciliatory nature it is a very useful process where parties continue to be in a trading relationship. Contracting parties should also consider building ADR into dispute resolution clauses in their contracts so that in the event there is a dispute the focus is on resolving the dispute as soon as possible before it escalates into litigation.”
Related FAQs
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
Read more about thisMHFAs are not qualified mental health medical professionals and they should not be diagnosing or giving medical advice, however, their training will equip them to provide initial support to those experiencing symptoms of mental ill health, and to signpost to further professional help when needed. The MHFA training makes the boundaries of the MHFA role very clear and there should be clearly defined role specifications, procedures and support pathways in place to ensure that individuals are referred on appropriately. There should be peer support in place for MHFAs and a system in place to ensure no individual or individuals are overloaded.
Read more about thisAll organisations have underperformers. Capability is a potentially fair reason to dismiss and is separate to any redundancy procedures.
Generally, capability falls into either absences through illness or underperformance in the role. Those who are absent through sickness can be furloughed, but when furlough comes to an end they will need to go back onto sickness. If you are looking to tackle absence then you need to tackle long term and short term absence in a different way.
Long term absence: You need to establish whether the employee is able to return to work (with or without reasonable adjustments) in the medium term. This requires medical opinion and be careful of disability issues. Reasonable adjustments are likely to be important.
Short term absence: You will need to demonstrate that you have fair absence triggers in place and there is normally be a 3 stage procedure: warning and final warning followed by dismissal on notice. Each stage needs a fair procedure, with written information, a fair hearing and the opportunity to appeal. Be careful of disability issues.
As for underperformance: To tackle this, you will need to have clear SMART objectives in place and evidence of the employee failing to meet these. There would then normally be a 3 stage procedure: warning and final warning followed by dismissal on notice. Each stage needs a fair procedure, with written information, a fair hearing and the opportunity to appeal.
Read more about thisThe Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
On Tuesday 23rd June, partner Emma Digby was in conversation with Steve Hamstead and Mark Smith from AON along with Ward Hadaway commercial lawyer Nathan Bilton in a webinar titled Can trade credit insurance help to keep the supply chain moving?
The insurance market is under untold pressure as a result of the pandemic, and in such times there is a risk that insurers will cancel or reduce credit lines, particularly in certain high risk sectors such as retail. However the Government has stepped in to effectively underwrite the existing trade credit insurance agreements, and to keep trade supplies moving. Will this be enough?
In this webinar, we discussed:
- the Government backed scheme and how it will operate
- the prospects of obtaining insurance going forward, and whether it will become too cost prohibitive
- could the new legislation put your business at risk and jeopardise your insurance cover if you cannot cancel a contract when you are not getting paid for your goods or services
- the Brexit effect, and how this will affect the insurance market
- protecting your business with proper risk assessment processes and paperwork