My dad has left one of my siblings much more than me and I don’t know why. Can I challenge the Will?
You cannot challenge a Will just because you feel that it is unfair (apart from in some limited circumstances where you if the Will does not make ‘reasonable financial provision for you’ – see our Financial Provision Claims FAQs).
However, there may be legitimate reasons for you to contest the Will, including if you think that your dad did not know what they were doing when they made the Will, or if you think someone was being forced to make the Will. See the other FAQs in this section and consider whether any of these apply to your circumstances.
These types of claims are very fact-specific so it is not possible to give a straightforward yes or no answer as to whether any such claim is available to you. You can contact us for advice and we can advise you whether we think that you have a claim.
Related FAQs
In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:
- Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
- Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
- Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
- Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
- Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
- Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
- Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
- Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
- Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!
In general. there is often a stick or twist decision. If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful. Conversely, withholding payments from the contractor may make insolvency a self-fulfilling prophecy. The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.
As mentioned earlier, if an agency is involved you must send them a copy of the status determination statement for each contractor, and they will also have the right to dispute the outcome.
If the agency pays the contractor, they will be responsible for the operation of PAYE and NIC’s deductions and any apprenticeship levy. The agency may try to recover these costs from the end user client.
If workers are supplied by an agency or umbrella company and are already treated as employees by the agency, they will remain unaffected by IR35.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.
If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.
It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.
Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.
Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.
There is no time limit for a claim to contest the validity of a Will. However, it is always advisable to act as soon as possible because – for the reasons explained above – there can be practical difficulties involved once a Grant of Probate has been issued and/or distribution starts to be made from the estate.
Any claims for reasonable financial provision under the 1975 Act must usually be brought within 6 months of the Grant of Probate being issued. For more information see below in the FAQs relating to financial provision.