Skip to content

My ex-husband has died and I was receiving maintenance payments from him. He hasn’t left me anything in their Will. What can I do?

You may be able to make a claim against your ex-spouse’s estate on the basis that their Will does not make ‘reasonable financial provision’ for you. You will not be able to bring a claim if you have remarried, or if a condition of your divorce explicitly states that you will not make a claim against their estate.

These types of claims are very fact-specific so it is not possible to give a straightforward yes or no answer as to whether any such claim is available to you.  The court will consider all factors which we can explore with you in more detail.

Related FAQs

Can apprentices be furloughed?

The government has stated that the scheme will apply to apprentices and that they can continue to train whilst they are furloughed. However you must pay at least the Apprenticeship Minimum Wage, National Living Wage or National Minimum Wage for all periods of training during furlough leave, taking into account the rate increases from 1 April 2020 and the increases which will take effect from 1 April 2021. This means that you will be responsible for any shortfall in the amount claimed under the scheme and the appropriate minimum wage.

We recommend that you get in touch to discuss any queries on furloughing apprentices.

What are the alternatives to an injunction?

A quicker and more cost-effective option may be the involvement of the police given their recent allocation of emergency powers to disperse, fine or even arrest persons who flout these rules. Nevertheless, it appears that the Court is willing to support housing providers in their efforts to tackle anti-social behaviour during this time.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

Are there specific examples given?

The guidance gives numerous examples of the types of performance adjustment which parties should consider. For example this includes:

  • Varying deadlines (e.g. for performance or payment)
  • Varying compensation (e.g. to recognise increased costs)
  • Varying the nature of performance (e.g. allowing substitute goods, allowing pert delivery of services)

The guidance also encourages a reasonable approach to enforcement, which might encourage delaying issuing formal proceedings, increased use of mediation or providing more information to the other party than would be volunteered under normal circumstances.