My reserved matters application is due to be submitted, can I delay this?
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
Related FAQs
No. The greater the gap between the completion of a Prenuptial Agreement and the Wedding the more likely it will be upheld by the Court. If such an Agreement is made shortly before the wedding takes place one of the parties to it could claim that they felt under pressure to sign and the Court may decline to follow it.
This will be dependent upon the how the leasehold structure is set up for each relevant building, but it may be the local authority. We would be happy to provide further advice in relation to specific buildings if you contact us separately with the relevant details and documents.
It really depends on what your measure of success is! We would suggest regular wellbeing surveys – if the results of wellbeing surveys suggest that the culture is becoming more open, more psychologically safe, if people are asking for help or referring colleagues to MHFAs as a safe and effective pair of hands – these would be strong indicators of success.
If such testing is regarded as a “reasonably practicable step” which has been identified as an appropriate control following a risk assessment then it is something you can do.
Although you can’t physically force someone to have something intrusive done, this is very likely to be a reasonable management instruction and therefore if someone refuses to have this done as a condition of entry into the work place then disciplinary action may follow.
Where this is something that is required of employees, employers should be letting their staff know that this is one of a number of measures that are being introduced into the workplace for their own safety. If the employer can explain, in advance of the return, why temperature checks need to be taken, what the consequences of the results will be- i.e. will they be sent home if over a certain temperature, whether this data will be stored (and if the sole purpose is to determine whether or not they are fit to attend work on a particular day then why are they being stored), and the fact that temperature checks are a requirement of entry to company premises for everyone, then there shouldn’t be significant resistance to this measure.
Large scale temperature checks have in some businesses become part of the “new normal” working environment.
All policies will impose a stringent obligation, often with time limits, for you to notify insurers of circumstances that may give rise to a potential claim under the policy and non-compliance may well negate your cover. If therefore you have potential cover under your policy you must make a precautionary notification to Insurers as soon as possible.