My reserved matters application is due to be submitted, can I delay this?
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
Related FAQs
The best advice is that parties should proceed as they would have done before the crisis began.
Companies House guidance on the impact of coronavirus on their services can be found at: https://www.gov.uk/guidance/coronavirus-guidance-for-companies-house-customers-employees-and-suppliers
This flexibility offered by Companies House could be a useful short-term help to businesses that are struggling to deal with the impact of the Covid-19 outbreak, but be sure to take action in advance of your filing deadline.
Many policies will only provide business interruption cover if it arises from property damage. The FCA has acknowledged that insurers are entitled to reject claims in relation to such policies, notwithstanding the success of the FCA’s test case in the Supreme Court, and which was generally favourable to policyholders [Insert a link here to our update on the test case]. In other cases the policy wording will be less clear and businesses may legitimately feel that their insurer is wrongly withholding payment.
One route of challenge to an insurer’s decision is via one of the well-publicised class actions. Another route of challenge is by a complaint to the Financial Ombudsman Service (FOS). This service is open to consumers and small and medium-sized businesses, ‘micro-enterprises’, charities and trusts. The service will be an attractive option for many businesses, as it is free and relatively quick (although it remains to be seen how the service keeps up with an increase in demand as a result of the pandemic). You will need to have complained to your insurer before bringing a complaint with the FOS.
Further details can be found here.
You must only make a report under RIDDOR (The Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013) when:
- An unintended incident at work has led to someone’s possible or actual exposure to coronavirus. This must be reported as a dangerous occurrence
- A worker has been diagnosed as having COVID 19 and there is reasonable evidence that it was caused by exposure at work. This must be reported as a case of disease
- A worker dies as a result of occupational exposure to coronavirus.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.