My reserved matters application is due to be submitted, can I delay this?
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
Related FAQs
It is. If you assess a risk and identify a control measure then fail to deploy it, then you are breaching your legal duties under HASWA and potentially committing a criminal offence. So if you decide for example that N95 respirators have to be used by everyone, you have a duty to provide them.
So the short answer is yes.
In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:
- Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
- Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
- Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
- Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
- Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
- Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
- Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
- Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
- Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!
In general. there is often a stick or twist decision. If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful. Conversely, withholding payments from the contractor may make insolvency a self-fulfilling prophecy. The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.
Employees will be reluctant to take unpaid leave or a sabbatical but when faced with the alternative prospect of redundancy may give it some serious consideration. This would remove the cost of that employee from the employer’s business for an agreed period of time. This is an option which can be offered to employees but again, imposing it without agreement creates significant risk.
The first point to note is that it is the position as at 14 February 2022 which is relevant, as whether or not a lease is a ‘qualifying lease’ for the purposes of recovering costs under the Building Safety Act was effectively frozen at that time.
If a leaseholder owned more than three properties in the UK (and the property in question was not their principal home) at that time, then the lease will not be a qualifying lease. The protections under the Act which prevent or restrict the landlord’s ability to recover the cost of remedial works through the service charge will not therefore apply to that lease (save potentially for the provision that costs cannot be recovered where the landlord is responsible for the defects, which does not expressly refer to qualifying leases).
The lack of a searchable database to assess how many properties a leaseholder has in the UK is however one of the difficulties to be resolved in this regard, as there is currently no way of searching the Land Registry to obtain a list of properties owned by one individual. The guidance appears to rely on the leaseholder completing the leaseholder deed of certificate being open and honest in this regard, and that deed of certificate being passed onto subsequent owners. Making false representations or failing to disclose required information in the deed of certificate may be a criminal offence, although reliance on this to discourage mis-reporting is clearly less satisfactory than having a searchable register.
You will be eligible if you are a self-employed individual or a member of a partnership and you:
- have trading profits of up to £50,000
- earn the majority of your income from self-employment
- have submitted a Tax Return for 2019
- have traded in the tax year 2019/20
- are trading when you apply for a grant, or would be except for Covid-19
- intend to continue to trade in the tax year 2020/2021
- have lost trading/partnership profits due to Covid-19