My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

Related FAQs

How are the Courts applying the new guidance?

Overall it is our experience that the Courts are quickly adapting in the context of the Coronavirus epidemic and making pragmatic decisions. The Judges seem live to the difficulties currently been faced by practitioners dealing with litigation and they are applying the new guidance.

The Courts are also mindful of pressures on NHS frontline staff and are taking steps not to put additional pressures on them at this time, including in our experience vacating an imminent Trial.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

Can an employee on family related leave be furloughed?

Yes, but your claim will be limited to any enhanced contractual payments you make to employees who qualify for the relevant family related pay.

All maternity and parental rights remain in force for anyone in this category who is furloughed. However you may need to calculate average weekly pay differently if the employee was furloughed and then started family related leave on or after 25 April 2020.

Furlough pay cannot be claimed for the period that an employee is receiving Maternity Allowance. An employee can agree to accept furlough pay but they must contact Jobcentre Plus to stop their Maternity Allowance payments for this period.

What if a contractor is deemed to be employed?

The fee payer that pays the fee to the contractor’s PSC for the services (end user client or agency) will be responsible for operating PAYE and deducting NIC’s. The fee payer must also pay employer NIC’s and where applicable the apprenticeship levy so there will be additional costs involved in the event of a change to employed status for tax purposes.

If the assessment concludes that the contractor is self-employed, the PSC can continue to be paid gross.

What are the consequences of the shake up of the planning Use Class system?

The Town and Country Planning (Use Classes) (Amendment) (England Regulations) 2020 were laid before Parliament and come into force on 1 September 2020. They apply in England only.

The changes include the revocation of the following Use Classes;

  • A1 – shops
  • A2 – financial and professional services
  • A3 – restaurants and cafes
  • A4 – drinking establishments
  • A5 – hot food takeaways
  • B1 – business. Also revoked are the sub parts of B1;
    • B1(a) – offices
    • B1(b) – research and development of products and processes
    • B1(c ) – industrial process
  • D1 – non residential institutions
  • D2 – assembly and leisure

The changes include the amendment of the following Use Class;

  • B2 (industry)

The changes include the introduction of the following Use Classes;

  • E – commercial, business and service
  • F.1 – learning and non-residential institutions
  • F.2 – Local community

There are no changes to the following Use Classes;

  • C1 – hotels, boarding and guest houses
  • C2 – residential institutions
  • C3 – dwellinghouses
  • C4 – small HMO

From 1 September 2020;

  • Small retail shops (not more than 280 sq metres net sales area) selling essential goods including food and at least 1 kilometre from another shop will cease being an A1 use and will become a F.2 (local community) use;
  • Other A1 shops will become an E (commercial, business and service) use;
  • A2 uses will become an E (commercial, business and service) use;
  • A3 uses will become an E (commercial, business and service) use;
  • A4 uses will not be in a Use Class, they will be sui generis, ie not in any use class;
  • A5 uses will not be in a Use Class, they will be sui generis, ie not in any use class;
  • B1 uses (included B1(a), B1 (b) and B1 (c) will become an E (commercial, business and service) use;
  • B2 uses will either be B2 uses or will be Class E uses.
  • Clinics, health centres, creches, day nurseries and day centres (previously D1 uses) will become an E (commercial, business and service) use;
  • Schools, non residential education and training centres, museums, public libraries, public halls, exhibition halls, places of worship, law courts (previously D1 uses) will become an F.1 ( learning and non-residential institutions) use;
  • Cinemas, concert halls, live music performance venues, bingo halls and dance halls (previously D2 uses) and will be sui generis, ie not in any use class;
  • Gyms, indoor sport, recreation or fitness not involving motorised vehicles or firearms principally to visiting members of the public (previously D2 uses) will become an E (commercial, business and service) use;
  • Hall or meeting place for the principal use of the local community (previously D2 uses) will become an F.2 (local community) use;
  • Indoor or outdoor swimming baths, skating rinks, outdoor sports or recreation grounds (not involving motorised vehicles or firearms) (previously D2 uses) will become an F.2 (local community) use.

Changes of use within a Use Class do not constitute development. That being the case, provided the Order is applicable, its operation not having been restricted by planning condition, Agreement or Article 4 (1) Direction for example, planning permission would not be required, development as defined not happening.  If legally binding confirmation is required that planning permission is not required this can only be obtained by way of a successful application for a Certificate of Lawfulness. In the absence of such, there is some risk.

It remains the case that planning permission may be required for operational works to buildings. It also remains the case that other consents and permissions may be necessary for example licenses. Furthermore amendments to leases may be required if the property is rented.

The Regulations additionally include transitional arrangements because of permitted development rights for changes of use in the Town and Country Planning (General Permitted Development) (England) Order amongst others.  To respond to this Regulations introduce a ‘material period’ which is defined as meaning the period beginning 1 September 2020 and ending 31 July 2021. It is expected during the material period the Orders giving permitted development rights for changes for use which do constitute development will be amended / updated to reflect the new use classes.

Click here to view the Regulations.

The above is based on our understanding of the new Regulations at the time of issue and in advance of planning practice guidance being issued.