My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

Related FAQs

ONLINE EVENT: Global Clinic: Covid-19 and International Trade

Hosted by The North East England Chamber of Commerce, this webinar discussed practical advice on Covid-19 and the specific challenges for International Trade.

Partner Damien Charlton along with Andrew Needham,from Haines Watts and Grant Murray from XE Finance, provided an update on the challenges and potential solutions in their field, as well as a look forward for the “New Normal”.

To watch the full recording, please click here or to view the slides, please click here.

 

 

How are the Courts applying the new guidance?

Overall it is our experience that the Courts are quickly adapting in the context of the Coronavirus epidemic and making pragmatic decisions. The Judges seem live to the difficulties currently been faced by practitioners dealing with litigation and they are applying the new guidance.

The Courts are also mindful of pressures on NHS frontline staff and are taking steps not to put additional pressures on them at this time, including in our experience vacating an imminent Trial.

Can I reduce the risk of IR35 applying?

It is possible to review working arrangements for contractors before the new rules come into effect. This will require immediate action.

You could consider terminating current contracts and entering into new terms that reflect working arrangements for a self-employment arrangement.

Another possibility is encouraging contractors to abandon the PSC model and provide services under a compliant umbrella company.

In the event of a determination of employed status you should seek to enter new terms that at the very least reflect the new tax arrangements .

Can an employee on family related leave be furloughed?

Yes, but your claim will be limited to any enhanced contractual payments you make to employees who qualify for the relevant family related pay.

All maternity and parental rights remain in force for anyone in this category who is furloughed. However you may need to calculate average weekly pay differently if the employee was furloughed and then started family related leave on or after 25 April 2020.

Furlough pay cannot be claimed for the period that an employee is receiving Maternity Allowance. An employee can agree to accept furlough pay but they must contact Jobcentre Plus to stop their Maternity Allowance payments for this period.

What is the new Permitted Development Right for the construction of new dwellinghouses?

A new Permitted Development Right has been introduced by The Town and Country Planning (Permitted Development and Miscellaneous Amendments) (England) (Coronovirus) Regulations 2020 providing for the construction of new dwellinghouses on detached blocks of flats.

The new Right comes into force on 1 August 2020 and from this date development consisting of works for the construction of up to two additional storeys of new dwellinghouses immediately above the existing topmost residential storey which is a purpose-built, detached block of flats is permitted development.  The Right additionally covers specified associated works, the construction of fire escapes and ancillary structures, bin stores for example.

The Right is subject to detailed criteria being met and to a prior approval process to the Local Planning Authority who can consider the acceptability of the proposed development in a range of respects.  A link to the Regulations is here.

The Regulations additionally include a number of further amendments including additional rights for the holding of markets and for additional temporary uses of land for a time limited period.  They additionally include amendments to existing permitted development rights for the change of use of buildings to dwellinghouses through a requirement that there be adequate natural light in all habitable rooms.