Skip to content

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

Related FAQs

What happens if someone is asked to restrict their duties but, despite acknowledging the risks to their health involved, they say that they want to continue to work on the front line?

As their employer, you have an overriding duty to provide a safe system of work. The Trust would not be able to run a defence to say that an employee “waived their rights” and chose to continue to work. Provided the decision around restricting duties has been carefully thought out, a full risk assessment undertaken and the employee has been truly consulted about the impact on them, then the decision taken will be a reasonable management instruction. Failing to follow that reasonable management instruction could amount to a disciplinary offence.

Can we rely upon the 'reasonable grounds' point to proceed with a petition?

If the debts owed to you pre-date Covid-19 and your debtor seemed unable to pay well before the Covid-19 pandemic took place, it is entirely possible that you will be able to present a petition on the grounds that the debtor would have been unable to pay its debts even if the Covid-19 had no effect on its financial position. We do not yet have any reliable precedent as to how the Courts are likely to deal with such cases.  Whether you are likely to succeed will depend on the exact circumstances of the debt and your debtor. There has been one case decided in August 2020 where the Court concluded that Covid-19 did not have a financial effect upon the debtor and that the circumstances which gave rise to the petition had arisen long before Covid and would have occurred in any event.  A winding up order was made in that case.  What we do know about the court’s approach is that the purpose of the Act is to allow viable companies to trade through the current times and the Court is likely to set the bar high.

Please contact us if there a debt you would like to discuss. Even if presenting a winding up petition is not available for now, there may still be other forms of legal proceedings that you can use to collect money owed to you, like county court proceedings.

Court proceedings have been issued. What happens to the court timetable?

The parties to litigation should still take the steps they have been ordered to take and comply with any Orders made by the court. If for any reason it looks as if a direction cannot be complied with because of the Covid-19 virus then an extension of time can be agreed with the other party (up to 28 days) or through the court. We are aware that Orders have been made extending the time for certain steps to be taken by 56 days.

Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?

The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.

The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.

The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:

  • Amending the contract requirements
  • Varying timings of deliveries
  • Relaxing KPIs or service levels
  • Extending time for performance (e.g. revising a contract delivery plan), and/or
  • Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).

These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.

A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.

If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.

 

 

Which agreements will qualify for exemption?

There are four criteria which must be satisfied if an agreement is to be considered exempt:

  • It must improve production or distribution, or promoting technical or economic progress – the guidance suggests that cooperation ensuring essential goods and services can be made available to the public, or an important sub-set of the public such as key workers, will satisfy this criterion.
  • It must allow consumers a fair share of the resulting benefit – the guidance suggests this will be the case where the action prevents or reduces shortages.
  • It must not impose on the undertakings concerned restrictions which are not indispensable to the attainment of the above benefits – the guidance suggests this will be the case where the cooperation is the only reasonable option due to the urgency of the crisis and where the cooperation is temporary in nature.
  • It must not afford the undertakings concerned the possibility of eliminating competition – therefore the parties must endeavour to retain competition in respect of the products (in particular price competition).