My reserved matters application is due to be submitted, can I delay this?
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
Related FAQs
- Integration:
- Is the individual held out as being employed by the business by having a company email address, uniform, how would they introduce themselves to customers?
- Exclusivity:
- Is the contractor restricted from working for other organisations without the consent of the end user client?
- Length of engagement:
- Is the contractor engaged to work on a specific project for a defined period? Or are they engaged for an indefinite period with no reference to a specific task or project?
- Pay:
- Are there regular fixed payments or is payment on completion of specific task or commission based? Is the contractor entitled to benefits or bonuses?
- Facilities:
- Does the contractor provide their own equipment and materials to provide the services?
- Financial risk:
- Is the contractor personally responsible for any loss arising from their work in performing the services? Will they have to rectify unsatisfactory work at their own time and expense? Will they have the opportunity to profit from the success of a project?
The formal Government position relating to construction sites is that construction work should continue on site if it can be conducted safely, and the Business Secretary, Alok Sharma, has written an open letter to the UK Construction Industry thanking it for all its help in the current crisis. The letter also confirms the Government’s current official policy of keeping construction sites open. The full text of the letter can be downloaded.
This also remains the formal position of the Construction Leadership Council (CLC) with the qualification that sites should operate in accordance with Public Health England instructions; without compromising health and safety; and in accordance with the Site Operating Procedures issued last week by the CLC.
In practice, many construction sites have been closed by national developers and house builders due to difficulties with staffing and supply chain, and practical issues with compliance with the social distancing and site operating procedures.
The Scottish Government has recently issued guidance that all non-essential construction sites, which includes housing, office, leisure, schools and retail sites, must close to reduce the risk of the spread of Covid-19.
The Government assured parity for the self-employed but it has since accepted that this would be difficult to achieve. The Association of Independent Professionals and the Self-Employed (IPSE) has worked closely with the Government on implementing the current self-employment income support scheme. IPSE has confirmed that it will continue to work on helping to extend measures to all freelancers in need as a result of Covid-19.
The Government announced an extension to the Self-Employment Income Support Scheme from 1 November 2020.
Under their obligations arising from Regulation 36 of the Gas Safety (Installation and Use) Regulations 1998, landlords must service domestic gas appliances on an annual basis and provide tenants with a record of the service within 28 days of that service. Failure to comply can result in prosecution by the Health and Safety Executive (HSE) or downgrading by the Regulator.
We know how important this is. But how can you comply with your obligations during the Covid-19 epidemic?
The latest restrictions on leaving the home, currently allow registered gas engineers to undertake essential work, whilst taking the appropriate precautions advised to avoid spreading or contracting the virus in a new setting.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.