Understanding of the extent of the Covid-19 risk to BAME colleagues is evolving – what does that mean for NHS employers?
In practice this means that any risk assessment will need to be reviewed constantly and adjusted as our understanding of the nature and level of the risk grows.
Some service-providers are instigating special Oversight Groups to keep this issue under review but engagement and consultation with those affected is critical and making sure they feel confident to raise concerns and refuse to work if they believe they are not safe.
Related FAQs
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.
On 25th June 2020, the Corporate Insolvency and Governance Act, among other things, introduced new restrictions on suppliers of goods and services to terminate the contract in the event that the customer enters an insolvency process. This has very important consequences for many businesses as it could expose them to greater financial risks.
In the unfortunate event that there will be a significant number of deaths, planning will fall to the local resilience forum; which includes all relevant local organisations and statutory bodies, who will have prior experience in working in excessive death scenarios.
It is for the coroners to ensure that they are familiar with the local resilience forum plans and discussions required. This will include issues regarding storage capacity and post-mortem examination capacity.
Civil Court listing priorities, last updated by HMCTS on 24 April 2020, categorise the Court’s work into the following:
Priority 1 – work that must be done: this includes any applications in cases listed for trial in the next 3 months, any applications where there is a substantial hearing listed in the next month, all multi-track hearings where parties agree that it is urgent (subject to triage).
Priority 2 – work that could be done: Infant and Protected Party approvals, Applications for interim payments in multi-track / personal injury / clinical negligence cases, Applications to set aside Judgment in default, Preliminary Assessment of costs.
The full guidance can be found at:
Yes. The Land Registry published a new service update on 14 May, here:
https://www.gov.uk/guidance/coronavirus-covid-19-impact-on-hm-land-registrys-service
Importantly, the Land Registry will process registrations where documents have been executed using the Mercury signing approach:
For land registration purposes, a signature page will need to be signed in pen and witnessed in person (not by a video call). The signature will then need to be captured, with a scanner or a camera, to produce a PDF, JPEG or other suitable copy of the signed signature page. Each party sends a single email to their conveyancer to which is attached the final agreed copy of the document and the copy of the signed signature page.
To summarise some further points:
- Most information enquiries are experiencing minimal delays
- Registrations of new titles, such as on sales of part or new leases, and applications to update existing titles, are experiencing more significant delays but can be expedited via the expedite service
- Cancellation dates for replying to requisitions are extended until further notice
- Access to free documents on the land registry portal has been extended to 90 days from completion of the transaction
- Identity requirements have been relaxed. The Land Registry will now raise a requisition for identity documents, and not cancel applications
- Requests for extensions to a notice or objection period will be granted if lawfully possible
- Land charges searches can be submitted electronically with PDF documents