Skip to content

VIDEO: Commercial law implications of the Corporate Insolvency and Governance Bill

Partners Damien Charlton and Jane Garvin look at the provisions of the Bill which impact on a supplier’s rights under a contract when their customer enters an insolvency procedure. They also outline other changes to insolvency procedures that the new law will introduce.

This webinar is part of a series designed for in-house lawyers.  If you would like to register to receive invitations to future events for in-house legal counsel, please email damien.charlton@wardhadaway.com.

Related FAQs

What does information and consultation involve?

There are two stages:

  • Stage 1 – The provision of written information to the representatives.
  • Stage 2 – Consultation on the proposed redundancies “with a view to reaching agreement” about certain matters

Stage 1: Provision of information

The first stage in the collective consultation process is to provide the representatives with written information including details of the proposed redundancies (often called a section 188 letter). This information must be given to the appropriate representatives and the time limit before dismissals can take effect does not start to run until they have received it. It is this information which ‘starts the clock’.

It is possible that there will be changes to the proposals during the consultation process: indeed that is part of the reason for the process. The employer’s obligation is not just to provide the appropriate representatives with the relevant information at the start of the process. It is under a continuing obligation to provide them with information in writing about any developments during the consultation process (although later changes do not ‘restart the clock’ before dismissals can take effect).

Stage 2: Consultation on the proposed redundancies “with a view to reaching agreement” about certain matters

The consultation process must include consultation “with a view to reaching agreement with the appropriate representatives” on ways of:

  • Avoiding the dismissals
  • Reducing the number of employees to be dismissed
  • Mitigating the consequences of the dismissals
I hold a licence but can’t trade. Can I terminate it?

A licence to occupy premises is not an interest land and operates as a commercial contract between the parties that enter into it. Licences tend to be put in place to cover short periods and consequently they are generally a lot more flexible than commercial leasing arrangements. To that extent occupants under licences should review the contract to establish whether or not there are any provision allowing them to terminate on notice to the Licensor.

Occupants under licences that are granted for longer periods without the option to terminate may try to argue that the contract has frustrated because they are effectively unable to occupy.

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

Is it possible to proceed with a hearing in person for any COP matters?

Any hearings attended in person will need to be approved by the judge hearing the matter, if necessary, in consultation with the regional lead COP judge. Such requests are highly unlikely to be granted during COVID-19 unless there is a genuine urgency. However, it is deemed to be appropriate matters are likely to be adjourned on the basis that a remote hearing is not possible and a hearing in person is not safe or possible.