Skip to content

VIDEO: Force majeure during the coronavirus pandemic

Commercial partner Damien Charlton explains the basic principles of force majeure, and how they are relevant in the current extreme circumstances caused by the Covid-19 pandemic.

Related FAQs

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Is the Land Registry functioning?

Yes. The Land Registry published a new service update on 14 May, here:

https://www.gov.uk/guidance/coronavirus-covid-19-impact-on-hm-land-registrys-service

Importantly, the Land Registry will process registrations where documents have been executed using the Mercury signing approach:

For land registration purposes, a signature page will need to be signed in pen and witnessed in person (not by a video call). The signature will then need to be captured, with a scanner or a camera, to produce a PDF, JPEG or other suitable copy of the signed signature page. Each party sends a single email to their conveyancer to which is attached the final agreed copy of the document and the copy of the signed signature page.

To summarise some further points:

  • Most information enquiries are experiencing minimal delays
  • Registrations of new titles, such as on sales of part or new leases, and applications to update existing titles, are experiencing more significant delays but can be expedited via the expedite service
  • Cancellation dates for replying to requisitions are extended until further notice
  • Access to free documents on the land registry portal has been extended to 90 days from completion of the transaction
  • Identity requirements have been relaxed. The Land Registry will now raise a requisition for identity documents, and not cancel applications
  • Requests for extensions to a notice or objection period will be granted if lawfully possible
  • Land charges searches can be submitted electronically with PDF documents
If you have to undertake collective consultation do you also have to carry out individual consultation?

Once the collective process concludes, an employer can make the decision to proceed with the restructure. They will then have 1-on-1 meetings with employees about the impact of the restructure on them. This will include consideration of alternative employment. There is no need to consult further about the proposal, merely the effect of the restructure on the individual.

What challenges to planning permission does the current lockdown situation present?
  • Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
  • Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
  • Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
  • The ability to get people on site to undertake material operations

In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.

If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.

Can I demand that my employees have the vaccine?

In most circumstances the answer will be no. It would be an infringement of their human rights. It could also be a criminal assault.

However where there is a high risk to employees of exposure to COVID-19, such as care homes and healthcare environments, you might be able to make it a requirement of their role to have the vaccine.

First, consider whether you need to have a blanket requirement covering all employees or whether only certain groups who work in the most high risk areas require the vaccine.

You will need to do a thorough risk assessment balancing the amount that the risk of exposure would be reduced against the interference with the employee’s human rights. Consideration will need to be given as to whether insisting on the vaccine is proportionate to the risk and whether other less invasive steps could be taken instead, such as maintaining social distancing, wearing a mask, washing hands.

Any requirement for employees to be vaccinated should be communicated clearly to employees and trade unions together with a clear explanation for why it is necessary.