We are conscious that asking a particular group of people, who have a protected characteristic under the Equality Act 2010, to restrict their duties, could expose the Trust to allegations of discrimination. What steps can we take to avoid someone/a group of people feel that they have been treated differently because of their protected characteristic?
A claim for indirect discrimination is the most likely risk here. The first point to make is that the decision to review duties is being made based on the growing amount of medical evidence that the BAME community is being disproportionately adversely affected by the COVID 19 pandemic compared to other ethnic groups. The key is to ensure that blanket policy decisions are not taken, nor should assumptions be made about the risk to each individual concerned. Decisions should only be made on an individual basis with an open dialogue with the individual concerned. You as their employer, need to ensure that the individual feels listened to and heard; that this is not just a tick box exercise.
Consider having a working group which has an overview of the policy decisions being made. That working group should contain representatives from across the staff groups including staff side, but importantly, representatives from different ethnic backgrounds to ensure the important voices are heard. Accountability should be built into that group. This group should also be a safe environment for staff to raise concerns about their health and safety and safe systems at work.
Related FAQs
If changed circumstances mean that a business wants to exit from a contractual arrangement, then before trying to terminate it, a careful review should be carried out to see whether a right to terminate actually exists. For example:
- Not every contract for the sale of goods contains the right for the buyer to terminate in circumstances where the supplier hasn’t done anything wrong. If a business has entered into a contract on the supplier’s standard terms, it is unlikely to contain any such provision
- A contract for the provision of services is unlikely, if drafted by the customer, to contain a provision that allows the supplier to walk away from the arrangement at short notice, or perhaps at all
If a party tries to terminate a contract when it doesn’t have the right to do so, the other party will likely claim breach of contract and could sue for damages. In the case of a long term or high-value contract, this could amount to a very significant liability.
Even if the right to terminate the contract does exist, there might be particular rules about the following:
- How much notice has to be given
- How such notice has to be served (for example, it might have to be in writing to a particular address)
- When the notice can be served (perhaps on an anniversary of the start of the contract)
- How much a party has to pay if it cancels (for example, for raw materials, for work done to date, or even the whole contract price)
All of these factors must be taken into account, and any contractual processes for termination are followed.
Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.
New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.
For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.
Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.
For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.
Business operators such as travel operators, hotels and restaurants remain vulnerable to claims of failure to protect against contracting the virus. There is a high chance of claims from employees, clients and members of the public. These are likely to be covered under public liability and employer’s liability insurance.
As above, people must not leave their home unless they have a ‘reasonable excuse’ and travelling should be limited to their local area. Employees may leave their home and local area to travel for work if they cannot reasonably work from home. You should attempt to reduce the number of journeys they make.
Many businesses that supply directly to consumers have been concerned to understand their legal position in relation to services that have been cancelled, or that they have been unable to perform, because of the Covid-19 pandemic, and in particular how to deal with deposits paid by consumers for such services. With some degree of restriction on the hospitality and tourism sectors likely to remain in place for some time, such questions will remain important for the foreseeable future.