Skip to content

VIDEO EXPLAINER: Consultation exercises – the why, the who, and the how

This free Getting back to business webinar was held on Thursday 7th May.

On this video, employment partner Edward Nuttman and Graham Vials went through what a consultation exercise is and when you are required to hold one. They then took you step by step through the process, describing all you will need to do to ensure legal compliance whilst at the same time being sensitive to the emotional and motivational impact on your employees and managers.

Related FAQs

Who is responsible for planning in the event of an excess of deaths?

In the unfortunate event that there will be a significant number of deaths, planning will fall to the local resilience forum; which includes all relevant local organisations and statutory bodies, who will have prior experience in working in excessive death scenarios.

It is for the coroners to ensure that they are familiar with the local resilience forum plans and discussions required. This will include issues regarding storage capacity and post-mortem examination capacity.

The employee I need to consider suspending is a doctor – do I have to follow MHPS

Yes probably in our opinion, even if you are not considering taking any formal action against them. Ultimately if a doctor is suspended this could be considered as causing them reputational damage and it therefore is correct that they are afforded the protections (in particular in relation to keeping exclusion/suspension under review) of MHPS. Under Part V of MHPS there is provision for excluding practitioners if they are a danger to patients and they refuse to recognise it or if they refuse to co-operate. It doesn’t refer to a particular risk for the practitioner themselves, but it would appear logical that it would apply.

Can I argue that my contract has been frustrated?

It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.

If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.

It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.

Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.

Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

How important is social distancing when planning your workplace?

It is absolutely critical to creating a safe workplace and to making workers feel secure.

This could include floor markings every 2m (as we’ve seen in grocery stores), stopping or limiting/staggering access to communal or common areas such as toilets and kitchens, rearranging workstations to maintain a 2 metre distance or, where this is not possible (for example in manufacturing facilities or production lines), erecting physical barriers and avoiding face to face working, encouraging the use of stairs and discouraging lift-use, designing a one-way system for entry and exit and looking at aircon/heating systems to see if any modifications are possible to prevent the spread of airborne particles. If you can increase ventilation in your workplace, it will help reduce risk.

The government has published detailed social distancing guidance for workplaces across sectors including manufacturing, retail, offices, construction and transport; it has also promised to continue to add to this.