Skip to content

What actions and measures should be avoided?

The CMA is particularly concerned about certain activities, its guidance highlights:

  • Exchange of commercially sensitive information where this is not necessary in response to the crisis
  • Collaboration which unfairly excludes third parties
  • Abuse of a dominant position (including a dominant position held as a result of the crisis) – particularly to charge excessive prices
  • Seeking to maintain prices or prevent reductions in prices
  • Cooperation going beyond what is necessary to respond to the crisis in the interests of consumers

Related FAQs

What is Coronavirus Business Interruption Loan Scheme (CBILS)?

The Coronavirus Business Interruption Loan Scheme (“CBILS“) is open for applications to provide small businesses with a loan of up to £5m to assist with the Covid-19 outbreak. The Scheme is aimed at businesses who are experiencing lost or deferred revenues, and who otherwise would be denied support from lenders, to be supported by a Government backed guarantee. The Scheme will initially run for six months with the possibility to be extended where required, so businesses should only approach a lender under the Scheme as and when they require assistance.

Do I need Planning Permission to change the use of a warehouse or factory unit to a temporary mortuary?

Mortuaries are a sui generis use, unless ancillary to some other use of land, a hospital for example.

Sui generis uses are not within any Use Class. Consequently planning permission is required for the:

  • Change in the use to a sui generis use
  • Subsequently for the change in the use to an alternative use, whether that be another sui generis use or a use within a Use Class

Acknowledging the above, if the scale of the use is above de minimis, planning permission is likely to be required to change the use of a warehouse or factory unit into a temporary mortuary.

Should planning control be breached, a local planning authority must decide whether to take enforcement action or not. That enforcement is discretionary was recently reiterated in a Ministerial Statement issued on 13 March 2020 a link to which is below.

https://www.parliament.uk/business/publications/written-questions-answers-statements/written-statement/Commons/2020-03-13/HCWS159/

Depending on the form of the enforcement action, there could be a right of appeal.

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Can furloughed workers still continue with union or non-union representation duties?

Yes, they can continue to undertake duties or activities for representative purposes. This includes individual or collective representation of their colleagues. They must not carry out any actual work or generate revenue for their employer or a linked or associated organisation.

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.